Having considered an officer report, and a presentation by the Cabinet Member for Children’s Services and School Performance, Councillor Chris Barnham, the Mayor and Cabinet agreed that: (1) the procurement of contractors to deliver the SMWP 2021/2022 as set out be approved; (2) the extension of the current School Minor Works Programme consultant contract to include the construction phase of this year’s scheme, as set out be approved ; (3) the procurement of a new set of school condition surveys to inform the Schools Minor Works Programmes from 2022 to 2025, as set out be approved ; (4) the procurement of consultant services for the School Minor Works Programmes from 2022 to 2025, as set out be approved; (5) authority be delegated to the Executive Director for Children & Young People, on the advice of the Executive Director for Corporate Resources and Executive Director for Housing, Regeneration & Environment, to finalise the list of works and commence the procurement for the School Minor Capital Works Programme for 2021; and (6) authority be delegated to the Executive Director for Children & Young People, on the advice of the Executive Director for Corporate Resources and Executive Director for Housing, Regeneration & Environment to award and enter into contracts to deliver the Schools Minor Capital Works Programme 2021.
Word for word from the decision Lewisham published for this meeting.Source: councilmeetings.lewisham.gov.uk
Report title: Schools Minor Works Programme 2021 – 2025: approval to procure and budget allocation Date: 13 January 2021
Key decision: Yes
Class: Part 1
Ward(s) affected: Perry Vale, Blackheath, Grove Park, Whitefoot, Telegraph Hill, Forest Hill, Catford South, Brockley, Downham, Evelyn and Rushey Green
Contributors: Acting Group Finance Manager, Director of Law, HR and Governance (Steph Fleck (SZP), Procurement and Commercial Services Manager, and SGM Capital Programme Delivery
Outline and recommendations This report seeks:
Approval to finalise and procure the final programme of works for SMWP 2021,
Delegated authority to the Executive Director for Children and Young People to award works contracts to deliver the School Minor Works Programme (SMWP) 2021,
Approval to procure the consultant services contract for the SMWP 2022 to 2025, and
Approval to procure a new set of school condition surveys to inform the SMWP from 2022 to 2025. Timeline of engagement and decision-making Letter emailed to headteachers commencing development of School Minor Works Programme 2021 on 16 October 2020 (see section 5.1)
Outline proposal agreed at Children & Young People Strategic Asset Board (SAB) meeting on 01 December 2020
1. Summary 1.1. This report seeks:
Approval to finalise and procure the final programme of works for SMWP 2021,
Delegated authority to the Executive Director for Children and Young People to procure and award contracts to deliver the SMWP 2021,
Approval to procure the consultant services contract for the SMWP 2022 to 2025, and
Approval to procure a new set of school condition surveys to inform the SMWP from 2022 to 2025.
2. It is recommended that the Mayor: 2.1. Approve the procurement of contractors to deliver the SMWP 2021/2022 as set out in section 5. 2.2. Approve the extension of the current School Minor Works Programme consultant contract to include the construction phase of this year’s scheme, as set out at 6.3. 2.3. Approve the procurement of a new set of school condition surveys to inform the Schools Minor Works Programmes from 2022 to 2025, as set out in section 8; 2.4. Approve the procurement of consultant services for the School Minor Works Programmes from 2022 to 2025, as set out in section 7. 2.5. Delegate authority to the Executive Director for Children & Young People, on the advice of the Executive Director for Corporate Resources and Executive Director for Housing, Regeneration & Environment, to finalise the list of works and commence the procurement for the School Minor Capital Works Programme for 2021 (noted at 5.3). 2.6. Delegate authority to the Executive Director for Children & Young People, on the advice of the Executive Director for Corporate Resources and Executive Director for Housing, Regeneration & Environment to award and enter into contracts to deliver the Schools Minor Capital Works Programme 2021.
3. Policy Context 3.1. The Local Authority has a duty to ensure the provision of sufficient places for pupils of statutory age and, within financial constraints, accommodation that is both suitable and in good condition. 3.2. The proposal within this report is consistent with the Corporate Strategy 2018-2022, in particular the Corporate Priority of ‘Giving children and young people the best start in life: Every child has access to an outstanding and inspiring education and is given the support they need to keep them safe, well and able to achieve their full potential’. 3.3. As owner of the school buildings and the employer, the Council has a statutory duty under the Health & Safety at Work Act 1974 and associated approved codes of practice, to ensure that schools are fit for purpose and used by pupils and staff. Whilst schools are responsible for day to day maintenance of their buildings, any significant expenditure on capital schemes has to be funded by the Council.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.