Having considered an officer report, and a presentation by the Cabinet Member for Environment & Transport, Councillor Sophie McGeevor, the Mayor and Cabinet agreed that: (1) the strategy for highway service delivery via works contracts as set out be approved ; (2) the current Highways Maintenance & Planned Works procurement exercise be ceased; (3) a one year extension of the current Highways Maintenance & Planned Works, to March 2022 be approved to align the end date with the Highways Footway works Contract ( Footway works) and the Highways Resurfacing Works Contract ( Carriageway Works ) at a cost of £2.8 million; and (4) a new procurement of a new consolidated Highways Works Partnering Contract be approved for a period of 8 years, with the option to extend for a further 2 years.
Word for word from the decision Lewisham published for this meeting.Source: councilmeetings.lewisham.gov.uk
Report title: Highways and Traffic Works Partnering Contract Date: 10 February 2021
Key decision: Yes.
Class: Part 1
Ward(s) affected: All
Contributors: Executive Director for Housing, Regeneration and Public Realm; Head of Highways and Transport, Senior Lawyer, Procurement and Contracts Manager
Outline and recommendations The report reviews the recent and ongoing Highways Maintenance & Planned Works procurement exercise, assesses future strategic need and recommends a procurement route to benefit the council.
The recommendations are:
To agree the strategy for highway service delivery via works contracts as set out in this report; To agree to cease the current Highways Maintenance & Planned Works procurement exercise; To agree to a one year extension of the current Highways Maintenance & Planned Works, to March 2022, to align the end date with the Footway Maintenance Contract and the Resurfacing Contract; and To agree to a new procurement of a new consolidated Highways Works Partnering Contract, for a period of 8 years, with the option to extend for a further 2 years. Timeline of engagement and decision-making Formal decision on the Contract Strategy was approved by the Mayor and Cabinet in February 2020
1. Summary 1.1. This report reviews the recent and ongoing Highways Maintenance & Planned Works procurement exercise, considers the strategic needs for the council in its delivery of highways projects and improvements with a view to other existing highways contracts. 1.2. Consideration is given to an alternate route, halting the present exercise, extending the present contract by one year and combining all highways contracts, for the benefit of the council.
2. Recommendations 2.1. It is receommended that Mayor and Cabinet agree: a. To the strategy for highway service delivery via works contracts as set out in this report; b. To cease the current Highways Maintenance & Planned Works procurement exercise; c. To a one year extension of the current Highways Maintenance & Planned Works, to March 2022, to align the end date with the Highways Footway works Contract (Footway works) and the Highways Resurfacing Works Contract (Carriageway Works) ) at a cost of £2.8 million; and d. To a new procurement of a new consolidated Highways Works Partnering Contract, for a period of 8 years, with the option to extend for a further 2 years.
3. Policy Context 3.1. The Council, as Highway Authority, has a duty under Section 41 of the Highways Act 1980, to maintain the highway in a safe condition. The Contractor is required to assist the Council (where applicable) to discharge its duty where possible. 3.2. Capital and revenue investment on the public highway network is required to ensure the Council discharges its legal duties, and traditionally external contractors assist the Council by carrying out highway construction and repair works. 3.3. The Council Corporate Plan (2018-22) sets out how the Council’s corporate strategy, values, priorities and budget. The contents of this report are consistent with the Council’s policy framework with particular relevance to the many economic,
Is this report easy to understand? Please give us feedback so we can improve. Go to https://lewisham.gov.uk/contact-us/send-us-feedback-on-our-reports environmental and social improvement that rely on a modern transport system. The goal, objectives and outcomes for the intelligent management and delivery of the highways’ service are aligned with the Council’s Corporate Priorities. In particular highways services impacts on the following Priorities: open Lewisham making Lewisham greener building safer communities
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.