Having considered an open and a confidential officer report, and a presentation by the Deputy Mayor, Councillor Chris Best, the Mayor and Cabinet agreed that the initiation of the procurement of a 4 year supported living contract via a mini-competition under Lot 1: Supported Living of the Framework Agreement for Adults with Learning Disabilities 2019-2023 be approved.
Word for word from the decision Lewisham published for this meeting.Source: councilmeetings.lewisham.gov.uk
Report title: Learning Disability Framework - Request for permission to procure a contract for Supported Living through call off from the Framework (Mayow Road Supported Living units) Date: 10 March 2021
Key decision: Yes
Class: Part 1
Ward(s) affected: Perry Vale
Contributors: Tom Bird, Integrated Commissioning Manager Stephanie Fleck, Principal Lawyer, Contracts Team Yusuf Shaibu – Interim Group Finance Manager
Outline and recommendations The purpose of this report is to seek agreement from Mayor and Cabinet to initiate a procurement process. The procurement will involve the commissioning of a supported living contract as a call off under the Framework Agreement for the Provision of Services to Adults with Learning Disabilities.
The service will be delivered to people with learning disabilities and / or autism with challenging behaviour living in 6 new Supported Living flats which is part of the new Mayow Road social housing development
The development of this new supported living scheme is strategically supported by the Council and the CCG. NHS England have made grant funding available for the development of the Supported Living element of the Mayow Road scheme as a part of the ‘Transforming Care’ programme. A grant of c. £900k has been made available following the award of planning approval for the scheme in November 2019 Timeline of engagement and decision-making On 13th February 2019 Lewisham’s Mayor and Cabinet approved that the Council should pursue the development of new high-quality Supported Living and temporary accommodation homes at the Mayow Road Warehouse site.
On 7th August 2019 Lewisham’s Mayor and Cabinet authorised the scheme be submitted for Planning Approval
On 1st November 2019 Planning Permission was granted
Three consultation events were held between December 2018 and March 2019 with the general public on the housing development at Mayow Road, including the development of the supported living unit.
The capital grant agreement between NHSE and Lewisham Council finalised and signed February 2020 to confirm NHS funding for the housing development of the supported living flats in Mayow Road
A housing / service design development workshop was held in December 2018 involving Framework providers, adult social care and LD Specialist Therapy and Psychology lead professionals. Adult social care and health clinicians have been involved in ongoing design meetings.
1. Summary 1.1. The purpose of this report is to seek agreement from Mayor and Cabinet to initiate a procurement process. The procurement will involve the commissioning of a supported living contract as a call off under the Framework Agreement for the Provision of Services to Adults with Learning Disabilities. 1.2. The service will be delivered to the 6 new Supported Living homes for residents with learning disabilities which is part of the new Mayow Road social housing development 1.3. The development of this new supported living scheme is strategically supported by the Council and the CCG. NHS England have made grant funding available for the development of the Supported Living element of the Mayow Road scheme as a part of the ‘Transforming Care’ programme. A grant of c. £900k has been made available following the award of planning approval for the scheme in November 2019 1.4. The Joint Commissioning Teams for Adults and Children Services (CCG and LBL) have agreed the approach to delivering the supported living scheme which will provide an alternative to residential care locally for people with a learning disability and/or autism with challenging behaviour in Lewisham, and is an important new service which will expand the local offer to meet the needs of young people coming through Transition from Children and Young People’s services and reduce the need for out of borough placements. 1.5. This Part 1 report is accompanied by a Part 2 report which contains commercially sensitive financial information.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.