It was MOVED, SECONDED and RESOLVED that Mayor and Cabinet 1. Approve the budget increase as set out in the Part 2 report; noting that the Council is obliged under the terms of the contract dated 3 October 2022 with Charles Edwards Ltd to pay the contractor increased costs associated with prolongation and party wall matters and the steps being taken to mitigate the Council’s liability for increased costs as set out in the Part 2 report. 2. Delegate to the Executive Director of Place to agree the associated contract variation required. 3. Note how the scheme is being sufficiently progressed to meet BSA deadline of 6 April 2024 and prevent further significant cost increases.
Word for word from the decision Lewisham published for this meeting.Source: councilmeetings.lewisham.gov.uk
Report title: 52-54 New Cross Road Budget Update Date: 28 February 2024
Key decision: Yes
Class: Part 1
Ward(s) affected: New Cross
Contributors: Executive Director for Housing, Regeneration and Public Realm, Executive Director of Corporate Resources and Director of Law, Governance and Elections.
Outline and recommendations This report sets a proposal and recommendation for the Council to approve increased costs to the scheme budget and note revised programme to completion as a result of party wall awards and unforeseen works discovered during demolition.
The scheme received M&C approval in July 2022. The consented scheme is for demolition of existing structure and construction of 35 flats for general needs rent. The new homes will contribute to the delivery of the Councils’ building for Lewisham programme and to the corporate commitment to deliver new social homes.
It is recommended that Mayor and Cabinet: Approves the budget increase as set out in the Part 2 report; noting that the Council is obliged under the terms of the contract dated 3 October 2022 with Charles Edwards Ltd to pay the contractor increased costs associated with prolongation and party wall matters and the steps being taken to mitigate the Council’s liability for increased costs as set out in the Part 2 report. Delegate to the Executive Director of Place to agree the associated contract variation required. Notes how the scheme is being sufficiently progressed to meet BSA deadline of 6 April 2024 and prevent further significant cost increases. Timeline of engagement and decision-making M&C approval 12 July 2022.
This report is a Key Decision; therefore, any decision will be subject to scrutiny.
This report is a Key Decision, therefore any decision will be subject to scrutiny.
This is the Part 1 of two Parts. Part 2 is commercially sensitive.
1. Summary 1.1 The scheme at 52-54 New Cross Road is on site and the contract (for demolition and newbuild development of 35 flats for affordable rent, and associated landscaping) is being progressed.
1.2During demolition in September 2023 it was discovered that the neighbouring property belonging to Christ Faith Tabernacle (CFT) had inadequate foundations. Works were suspended while additional party wall awards for underpinning are pursued. Technical design work is progressing. The development falls within the transitional arrangements for higher risk buildings, under the Building Safety Act (BSA) and, as such, must have significantly progressed works by 6 April 2024. The current anticipated practical completion date has moved from November 2024 to May 2025.
1.3Prolongation claims as a result of delays to concluding the party wall awards for demolition and for underpinning to neighbouring CFT property and the mitigations to meet the BSA deadline have resulted in additionnal contract costs that exceed the scheme’s approved budget.
2. Recommendations 2.1 It is recommended that Mayor and Cabinet: 2.2 Approves the budget increase as set out in the Part 2 report; noting that the Council is obliged under the terms of the contract dated 3 October 2022 with Charles Edwards Ltd to pay the contractor increased costs associated with prolongation and party wall matters and the steps being taken to mitigate the Council’s liability for increased costs as set out in the Part 2 report. 2.3 Delegate to the Executive Director of Place to agree the associated contract variation required. 2.4 Notes how the scheme is being sufficiently progressed to meet BSA deadline of 6 April 2024 and prevent further significant cost increases.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.