Item7
Resolved
RESOLVED to • Enter into grant agreement with the Greater London Authority’s Civic Partnership Programme for a total of £2.486m capital works funding. • Approve match funding of £1m as detailed in section 8 of this report. • Use the GLA’s Architecture and Urbanism (A+U) framework and delegate appointment of a lead consultant to the Executive Director of Place. The recommended Framework Lot is Lot 4: Landscape, Green Infrastructure & Public Realm. The Supplier will act as the Design and Community Co-Design Lead to deliver the capital works project by March 2027, together with subconsultants with relevant technical expertise. • Procure a capital works contractor through a competitive, open tender process, and delegate appointment of the Lead Contractor to the Executive Director of Place.
Word for word from the decision Lewisham published for this meeting.
Source: councilmeetings.lewisham.gov.uk