Building for Lewisham (BfL) - Procurement Strategy and Programme Update

Approved Executive 3 papers

Mayor and Cabinet approved this item on Wednesday 4 December 2024. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

REOLVED to: A. procure an Investment Partner, to act as Main Contractor or Developer, for the Council’s Building for Lewisham (BfL) major development projects as outlined in this report. Further approval will be sought from Mayor and Cabinet prior to entering into an overarching agreement with an Investment Partner (IP) as the delivery vehicle for current and future major projects. B. Delegate authority to the Executive Director of Place, in consultation with the Executive Director of Finance, Digital and Corporate Resources and the Cabinet Member for Inclusive Regeneration and Planning, to bid for grant funding as required to assure delivery of the Achilles Street Regeneration Phases 1 - 3 and Thomas Lane Yard. C. note that the Council has submitted a bid for additional funding (top up) for Achilles Estate regeneration from the London Estate Regeneration Fund (LERF) as outlined in Part 2 and if the bid is successful, delegate approval of the entry into the grant agreement to the Executive Director of Place in consultation with the Executive Director of Finance, Digital and Corporate Resources. NOTED: A. The progress of the Building for Lewisham (BfL) programme since July 2024 and the ongoing risks and market challenges that are impacting the delivery of the programme and the steps being taken to seek to address and mitigate them. B. The impact of the changes announced in the Chancellor’s Budget to Right to Buy and the likely impact on the programme and schemes reliant on future receipts which will need to be reassessed due to potential funding gaps negatively impacting their viability. C. The Investment Partner (IP) procurement will be in the form of a Competitive Procedure with Negotiation or Competitive Flexible Procedure to select a partner. The two schemes, Achilles Street Regeneration Phase 1 and Thomas Lane Yard, are to be used as part of the selection of an Investment Partner (IP), as the “contracting” element and other sites will be proposed for the “development” element. D. The Investment Partner contract approach will enable individual call offs for pre-contract design services and for works. Each call off will be subject to sufficient capacity within the overall programme budget, viability parameters for each relevant phase or project, and relevant approvals required.
Word for word from the decision Lewisham published for this meeting. Source: councilmeetings.lewisham.gov.uk

Follow this further

Built from Lewisham's papers

What the report saysPro

Report to Mayor and Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Building for Lewisham (BfL): Procurement Strategy and Programme UpdateReport 153 KB Copy on its way
PDF
M&C BfL update Investment Partner Procurement Part 1 December 2024 FINALReport 156 KB Copy on its way
PDF
Part 1: Appendix 1 IP Contracting ApproachAppendix 169 KB Copy on its way

At this meeting

Whole meeting

On this subject at Lewisham

Search all
  1. Building for Lewisham (BfL) - Procurement Strategy and Programme UpdateThis decision
  2. Building for Lewisham: Approval of Contract Award for Strategic Partner and Capital BudgetNoted
  3. Building for Lewisham: small and complex sitesApproved
  4. Building for Lewisham - Achilles Street PART 1Approved
  5. Building for Lewisham Programme UpdateNoted
  6. Building for Lewisham Programme update PART 1Approved

More from Lewisham Mayor and Cabinet

All decisions
MeetingDecisionOutcome
9 Sep 2026 MinutesThe minutes of the Mayor and Cabinet meeting held on 1 July 2026 were agreed as a correct record. Agreed Open
9 Sep 2026 Matters Raised by Scrutiny and other Constitutional BodiesThere were no matters raised by scrutiny or other constitutional bodies for consideration at the meeting. Decided Open
9 Sep 2026 Smoke Control Area: Whole Borough DesignationMayor and Cabinet • Approved the commencement of the statutory process to revoke the existing Smoke Control Orders fo... Approved Open
9 Sep 2026 Treasury Management Mid-Year Review 2026/27Mayor and Cabinet • Approved and recommended that Council approves the Treasury Management Outturn report for 2025/26... Approved Open
9 Sep 2026 Approval to enact permitted extension to 0-19 Public Health Nursing Service contractMayor and Cabinet • Approved a three-year extension to the 0-19 Public Health Nursing Service contract from 1st April... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies