It was MOVED, SECONDED and RESOLVED to agree that the Executive Director of Place to use her delegated powers to consider any objections received during statutory consultation on the permanent traffic order and make any applicable decision as a result.
Word for word from the decision Lewisham published for this meeting.Source: councilmeetings.lewisham.gov.uk
Sustainable Streets – Recommendation approval for Existing CPZ reviews Date: 21 May 2025
Key decision: Yes
Ward(s) affected: Blackheath, Lewisham Central, Ladywell, Rushey Green, Brockley, Lee Green and Deptford
Contributors: Hayley Whitchurch, Project Manager
Outline and recommendations Mayor and Cabinet are recommended to:
• Agree for the Executive Director of Place to use their delegated powers to consider any objections received during statutory consultation on the permanent traffic order and make any applicable decision as a result. Timeline of engagement and decision-making 7 December 2022: Mayor and Cabinet approval of the Sustainable Transport and Parking Improvements programme
17 January-5 March 2023: Sustainable Streets public consultation for Phase 1a areas (Deptford and Catford/Crofton Park)
19 July 2023: Mayor and Cabinet approval of Sustainable Streets zones in Deptford, Honor Oak Park and Ravensbourne Park, and to proceed to consultation in Evelyn
11 August -24 September 2023: Sustainable Streets consultation for Phase 1b Evelyn and New Cross Gate area 4 September-1 October 2023: Sustainable Streets review of existing Lewisham Central, Blackheath and Rushey Green West CPZs
6 December 2023: Mayor and Cabinet approval of engagement and consultation of Phase 2: Hither Green & Lee, Brockley, and Catford15 January 2024: Implementation of Phase 1: Catford and Crofton Park area
20 November -21 January 2024: Sustainable Streets review of Deptford Central, Deptford South, Elverson and Ladywell CPZs.13 May 2024: Implementation of Phase 1: Deptford Park area
18 September 2024: Mayor and Cabinet approval of the Existing CPZ reviews for Lewisham Central (Zone B), Rushey Green West (Zone E), and Blackheath (Zone BHA), Deptford Central (Zone S), Deptford South (Zone DS), Elverson (Zone G) and Ladywell (Zone T)
1. Summary 1.1. The Sustainable Transport and Parking Improvements programme was approved by Mayor and Cabinet on 7 December 2022 and has an overarching aim of encouraging active travel in Lewisham through the provision of sustainable transport measures in combination with parking controls. Without adequate parking control measures in place this can lead to parking pressures being created within residential areas and also encourage greater car use. 1.2. Areas of the borough not yet covered by Controlled Parking Zones (CPZs) make up approximately 60% of the borough since the Sustinable Streets Programme was first implemented. The programme has been divided into phases for the proposed engagement and consultation of the Sustainable Streets programme (see Figure 1). 1.3. This report covers the review of the existing CPZs which the council undertook pubic consultation on amendments to align them towards the Sustainable Streets Programme and to ask whether residents would like amendments. The outcome of the public consultations were appproved at the Mayor and Cabinet meeting in September 2024. 1.4. As set out in the Sustainable Transport and Parking Improvements Programme report presented to Mayor and Cabinet in December 2022, ‘no waiting at any time’ junction protection markings (double yellow lines) are proposed to be
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.