London Borough of Lewisham
Public Accounts Select Committee, Tuesday 10 March 2026 at 7.30pm

IT & Digital Programme Update

Noted Committee 1 paper

AI summaryLewisham Public Accounts Select Committee noted the IT and Digital Programme update covering 85 active projects and asked for future reports to include brief examples and high level timelines.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedAdded call for examples and high level timelines in future IT reports
MoneyFinancial implications sit with each individual project
What happens nextRoadmap under developmentSingle view of all projects including prioritisation, status, and resourcing
Who it affectsAll council directorates and residents85 active IT and Digital projects across six directorates

What was decided

The committee accepted the recommendations in the report, covering governance progress, portfolio health, and key risks and mitigations. Report P5

The committee recommended that future IT reports include brief examples and high level timelines to illustrate project progress and integration, so members can have clearer strategic oversight without detailed project documentation.

Why

Officers want to improve prioritisation, decision making, and alignment with corporate objectives through stronger governance of digital change. Report 4.2, P3

Demand for IT and Digital continues to exceed available capacity in some areas, with projects sometimes proposed too late and with insufficient detail, raising delivery risk. Report P23

A small number of major projects are rated amber or red because of delivery risk, resourcing pressures, or external dependencies. Report P31

What happens next

An IT and Digital Projects Roadmap is being developed to give a single view of all projects, including prioritisation, status, and resourcing. Report P20

IT colleagues are working more closely with directorates to identify needs earlier and shape demand more effectively. Report P24

The IT Programme Board will review how it is functioning within six months of start up, with terms of reference then reviewed annually. Report P85

Options considered

  • Chosen: Note the report and accept the officer recommendations. Committee accepted the recommendations and noted the report Report P5

Implications

  • Financial: Financial implications are covered by each individual project rather than this overview report. Report P32
  • Legal: Legal implications are covered by each individual project rather than this overview report. Report P33
  • Equalities: Equalities implications are covered by each individual project rather than this overview report. Report P35
  • Climate: Climate change and environmental implications are covered by each individual project rather than this overview report. Report P36
  • Risk: The report itself states there are no decisions to be taken, so no direct risk implications arise from it; project level risks are tracked separately. Report P34
  • Other: No crime and disorder, or health and wellbeing implications arise directly from this report. Report P37, P38
  • Staffing: Resourcing pressure is flagged, with demand exceeding available capacity in some areas and difficult prioritisation decisions needed. Report P23

Who and where

  • All six Lewisham Council directorates running IT and Digital projects Report P26
  • Residents and service users, including social care clients, housing tenants, and library users Report P30, P53
  • Council staff using digital systems such as the new social care case management system, housing management system and repairs application Report P30

Timeline

  • 02/06/25: Initial draft of the IT Programme Board Terms of Reference produced by Anna Sehmi Report P46
  • Within six months of start up: IT Programme Board to review how it is functioning, with terms of reference updated then Report P85
  • Annually thereafter: Terms of Reference for IT Programme Boards to be reviewed by the Board Report P85
  • Bi monthly: IT Programme Boards meet for one hour, with papers circulated at least two working days before each meeting Report P71, P72

Plain English for the jargon

  • CEX: Chief Executive directorate of Lewisham Council
  • ASC and H: Adult Social Care and Health services
  • CYP: Children and Young People services
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

That the committee accepted the recommendations and noted the report, they also recommended that: • Future IT reports would benefit from brief examples and high ‑ level timelines to illustrate project progress and integration, allowing clearer strategic oversight without requiring detailed project documentation.
Word for word from the decision Lewisham published for this meeting. Source: councilmeetings.lewisham.gov.uk

Follow this further

Built from Lewisham's papers

What the report saysPro

Report to Public Accounts Select Committee

Summary

1.1The purpose of this report is to provide Members with an overview of the current position of the IT & Digital Programme, including:

• The effectiveness of programme governance arrangements • Overall portfolio health and key programmes • Key risks and issues affecting delivery • Strategic priorities requiring ongoing oversight

The report also highlights areas for improvement and the actions being taken to strengthen delivery and assurance across the organisation 2. Recommendations

Members are asked to:

1. Note the progress made in strengthening IT & Digital programme governance. 2. Note the current portfolio health position and key programmes. 3. Note the key risks and mitigations in place. 4. Review the direction of travel and make any comments for referral to M&C.

3. Policy Context This report aligns with Lewisham’s Corporate Priorities, as set out in the Council’s Corporate Strategy (2022-2026): • Cleaner and Greener • A Strong Local Economy • Quality Housing • Children and Young People • Safer Communities • Open Lewisham • Health and Wellbeing

Is this report easy to understand? Please give us feedback so we can improve. Go to https://lewisham.gov.uk/contact-us/send-us-feedback-on-our-reports 4. Background

4.1IT & Digital services underpin the delivery of all council services. The volume, scale, and complexity of digital change have increased significantly, particularly in relation to social care, corporate transformation, infrastructure, and partnership dependencies.

4.2In response, IT & Digital has implemented a strengthened governance framework to improve prioritisation, decision making, and alignment with corporate objectives. This includes the establishment of D making, and alignment with corporate objectives. This includes the establishment of directorate IT boards, standardised reporting, and clearer escalation routes.

5. Programme Governance – Current Position

5.1Successes

The following improvements have been achieved:

• Clearer decision m-making and escalation routes, with formalised governance and defined accountability. IT Directorate boards (Figure 1) are in place as set out below plus the high level process for end to end project delivery including the requirement for project authorisation (Figure 2).

Figure 1 – Directorate IT Boards Structure

Is this report easy to understand? Please give us feedback so we can improve. Go to https://lewisham.gov.uk/contact-us/send-us-feedback-on-our-reports Figure 2 – IT Project Process

• Standardised board packs and processes, improving consistency and transparency across directorates (see Appendix A for standard agenda) • A formal project request process, ensuring projects are aligned to directorate, corporate, and IT & Digital priorities. Example view of form in figure 3. The form requests a range of information including benefits, risks and costs.

Figure 3 – Copy of the IT Project Request form

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
IT & Digital Programme UpdateReport 442 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
JR
Councillor James RathboneChair, present
JP
Councillor John PaschoudVice-Chair, present
CB
Councillor Chris BarnhamCommittee Member, present
HT
Councillor Hau-Yu TamCommittee Member, present
EK
Councillor Eva KestnerCommittee Member, apologies
JM
Councillor Joan MillbankCommittee Member, present
SW
Councillor Susan WiseCommittee Member, present
RH
Ruth HodsonOfficer, present
KN
Katharine NiddOfficer, present, as expected, virtual
CW
Charlotte WilliamsSecretary, present

More from Lewisham Public Accounts Select Committee

All decisions
MeetingDecisionOutcome
7 Jul 2026 Minutes of previous meetingResolved- That the minutes of the previous meeting be approved as a correct record. Approved Open
7 Jul 2026 Committee Meeting Start Time for the Municipal Year 202627Resolved- That the Committee agree a 7pm start time for its scheduled meetings during the municipal year, subject to ... Agreed Open
7 Jul 2026 Financial Monitoring 2026/27 - Period 2 MonitoringResolved- That the Committee note the forecast position at Period 2 for the year ending 31 March 2027, as presented t... Noted Open
7 Jul 2026 Medium Term Financial StrategyResolved- That the Committee note the Medium Term Financial Strategy, as presented to Mayor and Cabinet on the 1 July... Noted Open
7 Jul 2026 Select Committee Draft Work ProgrammeResolved- That the Committee approves its priorities and agrees to the proposed work programme for 2026-27. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies