CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Lewisham
Mayor and Cabinet, Wednesday 1 July 2026 at 6.00pm

Permission to award the Integrated Community Equipment Service Contract (ICES)

Approved Executive 2 papers

AI summaryLewisham Mayor and Cabinet approved awarding the Integrated Community Equipment Service contract to Medequip Assistive Technology Limited from 1 August 2026, for a total of £13,168,562 over three years with a two-year extension option.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedVia Kent County Council framework, three years plus two-year option
Money£13,168,562Total cost across initial term and extension option
What happens nextContract starts 1 August 2026Initial three-year period, extendable by two years
Who it affectsAdult social care equipment usersService covers community equipment in Lewisham

What was decided

Mayor and Cabinet approved the award of the Integrated Community Equipment Service contract to Medequip Assistive Technology Limited, starting 1 August 2026, via the Kent County Council Integrated Community Care Equipment and Associated Services Y24008 Framework.

The contract runs for an initial three-year period with the option to extend for a further two years.

Total cost of the contract, including the extension option, is £13,168,562.

Why

The award is made through an existing framework agreement (Kent County Council Y24008) rather than a fresh procurement.

Medequip has been the incumbent provider under previous direct awards and short extensions while the new contract was prepared. Report P2, P4

What happens next

The new contract with Medequip Assistive Technology Limited will start on 1 August 2026.

After the initial three-year term, the council has the option to extend the contract for a further two years.

The money

  • £13,168,562 Total cost of the Integrated Community Equipment Service contract across the initial three-year term and the two-year extension option

Options considered

  • Chosen: Award via Kent County Council Integrated Community Care Equipment and Associated Services Y24008 Framework

Implications

  • Legal: Contract awarded through an existing framework agreement, avoiding a separate procurement exercise.
  • Other: Continuity of provider: Medequip has held the Lewisham ICES contract under previous direct awards and extensions. Report P2, P4

Who and where

  • Adults in Lewisham who use community equipment services Report P5
  • Medequip Assistive Technology Limited (awarded provider)
  • London Borough of Lewisham adult social care commissioning team Report P5

Timeline

  • 12 June 2024: Permission to direct award to Medequip Assistive Technology Limited until 30 June 2025 Report P2
  • 14 May 2025: CreditSafe report on Medequip Assistive Technology Limited Report P4
  • 25 June 2025: Permission to award a contract for the Integrated Community Equipment Service to Medequip until 31 March 2026 Report P4
  • 04 March 2026: Executive Director permission to extend the Medequip contract to 31 May 2026 Report P4
  • 12 May 2026: Chief Executive permission to extend the Medequip contract from 1 June 2026 to 31 July 2026 Report P4
  • 1 July 2026: Mayor and Cabinet decision to award the new contract
  • 1 August 2026: New contract with Medequip begins

Plain English for the jargon

  • ICES: Integrated Community Equipment Service, the Lewisham service that provides equipment to support people at home.
  • Y24008 Framework: Kent County Council's Integrated Community Care Equipment and Associated Services framework, used by other councils to buy these services.
  • Direct award: Awarding a contract to a chosen provider without running a competitive procurement process.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14

Resolved

Mayor and Cabinet • Approved the award of the Integrated Community Equipment Service contract from the 1 August 2026 to Medequip Assistive Technology Limited via the Kent County Council Integrated Community Care Equipment and Associated Services Y24008 Framework, for an initial threeyear period with the option to extend for two years, at a total cost of £13,168,562.
Word for word from the decision Lewisham published for this meeting. Source: councilmeetings.lewisham.gov.uk

Follow this further

Built from Lewisham's papers

What the report saysPro

Report to Mayor and Cabinet

KEY DECISION

Mayor and Cabinet

Report title: Permission to award a contract for the Integrated Community Equipment Service to Medequip Assistive Technology Limited up to 31 July 2031 Date: 1 July 2026

Key decision: Yes

Class: Part 1.

Ward(s) affected: All Wards

Contributors: Executive Director for Adult Social Care & Health, Director of Law & Corporate Governance, Executive Director for Corporate Resources, Finance Business Partner and Principal Lawyer. Outline and recommendations It is recommended that Mayor and Cabinet approve:

• The award of the Integrated Community Equipment Service contract from the 1 August 2026 to Medequip Assistive Technology Limited via the KCC Integrated Community Care Equipment and Associated Services Y24008 Framework, for an initial three-year period with the option to extend for two years, at a total cost of £13,168,562

• The new service will be funded by the Council and the Integrated Care Board, the contributions will be 30% from the Council and 70% from the Integrated Care Board.

Is this report easy to understand? Please give us feedback so we can improve. Go to https://lewisham.gov.uk/contact-us/send-us-feedback-on-our-reports Timeline of engagement and decision-making

Date Decision making

24 March Mayor and Cabinet approved decision to extend the Integrated 2021 Community Equipment Service contract until 31 March 2023

21 June Mayor and Cabinet approved decision to direct award to 2023 Medequip Assistive Technology Limited for 12 months until 31 March 2024

20 Mayor and Cabinet approved decision: September 2023 • for officers to procure the Integrated Community Equipment Service via the Kent Framework • approve the award of contract to the preferred provider, provided the contract value is within authorised limit • delegate authority to Executive Director for Community Services, (in consultation with the Director of Law and Corporate Governance and Associate Director, Community Support and Care to select the preferred provider in accordance with the selection criteria published in the tender documentation and agree final form of contract.

12 June Mayor and Cabinet approved decision to award to Medequip 2024 Assistive Technology Limited until 30 June 2025

Mayor and Cabinet approved decision:

• Mayor and Cabinet approved the decision to 25 June tender and select the preferred provider in accordance 2025 with the award criteria published in the tender documentation and agree final form of contract

Is this report easy to understand? Please give us feedback so we can improve. Go to https://lewisham.gov.uk/contact-us/send-us-feedback-on-our-reports • Mayor and Cabinet approved decision to extend the contract to Medequip Assistive Technology Limited until 31 March 2026

Permission was given from the Executive Director to extend the 4 March contract for Medequip Assistive Technology Limited from 1 April 2026 2026 to 31 May 2026 whilst the tender went live.

Permission is given from the Chief Executive Officer to extend the contract for Medequip Assistive Technology Limited from 1 12 May June 2026 to 31 July 2026 whilst the tender process is 2026 concluded leading to the M&C Meeting in July 2026 with the award recommendation.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Permission to award a contract for the Integrated Community Equipment Service REPORTReport 162 KB DownloadRead as text
PDF
Permission to award the Integrated Community Equipment Service Contract (ICES)Report 242 KB Download

At this meeting

Whole meeting

Who was there

10 of 10 attended
ML
Mayor Liam ShrivastavaChair, present
RS
Councillor Rudi SchmidtVice-Chair, present
AA
Councillor Ade AdewunmiCommittee Member, present
SA
Councillor Shireen AsawCommittee Member, present
CA
Councillor Corin AshwellCommittee Member, present
DD
Councillor Daniel DreamCommittee Member, present
SG
Councillor Samantha GardinerCommittee Member, present
RS
Councillor Rotimi SkyersCommittee Member, present
HT
Councillor Hau-Yu TamCommittee Member, present
NT
Councillor Natalie ThomasCommittee Member, present

On this subject at Lewisham

Search all
  1. Permission to award the Integrated Community Equipment Service Contract (ICES)This decision
  2. Permission to Procure and Award Multiple Housing Revenue Works ContractsApproved
  3. Permission to procure and award contracts for adults’ and children’s case management systemsApproved
  4. Permission to Procure and Award Multiple Housing Services (including ICT) & Works ContractsAgreed
  5. Permission to award the Integrated Community Equipment Service contractApproved
  6. Permission to procure and award Repair and Maintenance of Ventilation Plant and ControlsApproved

More from Lewisham Mayor and Cabinet

All decisions
MeetingDecisionOutcome
9 Sep 2026 MinutesThe minutes of the Mayor and Cabinet meeting held on 1 July 2026 were agreed as a correct record. Agreed Open
9 Sep 2026 Matters Raised by Scrutiny and other Constitutional BodiesThere were no matters raised by scrutiny or other constitutional bodies for consideration at the meeting. Decided Open
9 Sep 2026 Smoke Control Area: Whole Borough DesignationMayor and Cabinet • Approved the commencement of the statutory process to revoke the existing Smoke Control Orders fo... Approved Open
9 Sep 2026 Treasury Management Mid-Year Review 2026/27Mayor and Cabinet • Approved and recommended that Council approves the Treasury Management Outturn report for 2025/26... Approved Open
9 Sep 2026 Approval to enact permitted extension to 0-19 Public Health Nursing Service contractMayor and Cabinet • Approved a three-year extension to the 0-19 Public Health Nursing Service contract from 1st April... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies