Audit and Risk Committee, Tuesday 8 September 2026 at 7.30pm

Risk Management and Corporate Risk Register Update

Noted Finance 8 papers

AI summaryLewisham Audit and Risk Committee noted the updated Corporate Risk Register, with overall risk exposure down slightly, and asked for more detail in future updates, including figures and dates.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedMore detail requested on heat preparedness and future risk register updates
MoneyNoneDelivered within existing budgets
What happens nextMore detailed risk register updatesIncluding figures and dates, plus heat preparedness report
Who it affectsAll wardsCouncil-wide risk management and services

What was decided

The Committee noted the contents of the Risk Management and Corporate Risk Register update report. Report P8

The Committee asked for a more detailed report on extreme heat preparedness and Exercise Helios. Report P17, P18

Future Corporate Risk Register updates must include more detail, including figures and dates, to help assess and quantify risk likelihoods.

Why

Overall corporate risk exposure has reduced slightly since the last report, driven by reductions in Housing Management Software, Housing Compliance and Strategic Health Partners risks. Report P9

Two risks have increased in score due to external pressures: LBL013 Cost of Living Impact on Residents, and LBL006 Major Information Governance Failure, with cyber-related threats a key factor.

Three risks reduced in score: LBL021 Housing Management Software, LBL026 Strategic Health Partners, and LBL001 Council Housing Stock Compliance, with progress on Decent Homes, EICR and LOLER cited.

What happens next

Two remaining divisions within the Place directorate will complete risk workshops in September 2026, with a final catch-up session to follow. Report P9

Responses to the EMT Risk Appetite consultation will be collated in September 2026 and used to develop a formal Risk Appetite Framework. Report P14, P15

Mitigations are being planned to reduce disruption to Lewisham following Southwark Council's decision to exit the STS IT partnership.

Implications

  • Risk: Two Very High risks remain unchanged: LBL009 Significant Cyber Security Breach and LBL023 Significant Disruption to IT Partner (STS), with the external environment described as volatile.
  • Risk: Five of the 16 Corporate Risk Register risks have changed score, but none were added or removed since the previous report.
  • Climate: Exercise Helios, held in April 2026, tested the Council's response to an escalating heat emergency and informed the response to summer 2026 extreme heat periods. Report P17
  • Governance: Updated corporate risk scoring guidance was approved by EMT in February 2026, replacing the 'reputational' category with 'trust and public perception'. Report P10
  • Other: Financial, legal, equalities, climate, crime and disorder, and health implications are stated as none arising directly from the report.

Who and where

  • All wards in the London Borough of Lewisham Report P5
  • All Council directorates, through risk workshops and refreshed directorate risk registers Report P9
  • Residents affected by cost of living pressures (risk LBL013)
  • Council housing tenants, through progress on Decent Homes, EICR and LOLER compliance (risk LBL001)
  • Integrated Care Board staff, following the consultation outcome on capacity and budget pressures (risk LBL026)

Timeline

  • February 2026: Updated corporate risk scoring guidance approved by EMT Report P10
  • April 2026: Exercise Helios cross-service heat emergency exercise undertaken
  • Summer 2026: Periods of extreme heat experienced, with response informed by Exercise Helios learning Report P18
  • September 2026: Remaining Place directorate risk workshops to be completed; EMT Risk Appetite consultation responses to be collated Report P9, P15
  • 8 September 2026: Report presented to Audit and Risk Committee Report P2

Plain English for the jargon

  • ICB: Integrated Care Board
  • STS: Shared Technology Service
  • EICR: Electrical Installation Condition Report
  • LOLER: Lifting Operations and Lifting Equipment Regulations, including passenger lifts
  • EMT: Executive Management Team
  • DMT: Directorate Management Team
  • HMS: Housing Management Software
  • CHC: Continuing Health Care
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

RESOLVED that the contents of the report be noted. With these additional recommendations agreed: - A more detailed report be provided addressing the Committee’s outstanding questions on extreme heat preparedness and Exercise Helios. - Future updates to the Corporate Risk Register include more detail, including figures and dates, to assist the Committee in assessing and quantifying risk likelihoods.
Word for word from the decision Lewisham published for this meeting. Source: councilmeetings.lewisham.gov.uk

Follow this further

Built from Lewisham's papers

What the report saysPro

Report to Audit and Risk Committee

Audit and Risk Committee

Risk Management and Corporate Risk Register update September 2026 Date: 8 September 2026

Key decision: No.

Class: Part 1

Ward(s) affected: All

Contributors: Richard Benjamin, Head of Assurance Colin Burns, Audit and Risk Manager Kelly Thompson, Risk Officer

Outline and recommendations This report provides an overview of the Council's Corporate Risk Register and provides updates on the continued development of risk management arrangements across the organisation. It highlights progress made during the reporting period and sets out key areas of focus for the further embedding of risk management practices. The accompanying appendix contains the current Corporate Risk Register.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
6a, Appendix A: Corporate Risk Register: August 2026Appendix 306 KB Download
PDF
6a, Appendix A: Corporate Risk Register: August 2026Appendix 306 KB Download
PDF
6b, Appendix B: Impact and Likelihood guidance 2026Appendix 205 KB Download
PDF
6b, Appendix B: Impact and Likelihood guidance 2026Appendix 205 KB Download
PDF
6c, Appendix C: Extreme Heat Briefing and Exercise Helios update: August 2026Appendix 86 KB Download
PDF
6c, Appendix C: Extreme Heat Briefing and Exercise Helios update: August 2026Appendix 86 KB Download
PDF
Risk Management and Corporate Risk Register UpdateReport 112 KB DownloadRead as text
PDF
Risk Management and Corporate Risk Register UpdateReport 112 KB Download

At this meeting

Whole meeting

Who was there

6 of 22 attended
HF
Councillor Heather FarnworthChair, expected
EF
Councillor El FryVice-Chair, apologies
TD
Councillor Tanya DunneCommittee Member, apologies due to council business
GM
Councillor Gavin MooreCommittee Member, present
JR
Councillor James RathboneCommittee Member, present
CW
Councillor Claire WillsCommittee Member, present
AJ
Andrew JonesCo-Optee, in attendance
MM
Mark McLaughlinCo-Optee, in attendance
MO
Marcus O’TooleCo-Optee, in attendance
GD
Gillian DouglasOfficer, in attendance
MR
Michael ReeceOfficer, in attendance
HF
Councillor Heather FarnworthChair, expected

All 22 on the meeting page

On this subject at Lewisham

Search all
  1. Risk Management and Corporate Risk Register UpdateThis decision
  2. Flood risk management strategyNoted
  3. Flood risk managementNoted
  4. Local Flood Risk Management StrategyAgreed
  5. Flood risk management strategyNoted
  6. Risk Management StrategyNoted

More from Lewisham Audit and Risk Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Apologies for AbsenceApologies were received from Councillor Tanya Dunne and Councillor El Fry. Decided Open
8 Sep 2026 Declarations of InterestCouncillor Rathbone declared during Item 6: Risk Management and Corporate Risk Register Update that he is an employee... Decided Open
8 Sep 2026 MinutesRESOLVED that the minutes of the meeting of the Audit and Risk Committee held on 25 June 2026 be confirmed and signed... Noted Open
8 Sep 2026 External Audit UpdateRESOLVED that the contents of the report be noted. Noted Open
8 Sep 2026 Internal Audit Progress Update (delivery of the 2026/27 plan)RESOLVED that the Internal Audit Progress Report be noted. With this additional recommendation agreed: • The findings... Noted Open