AI summaryLewisham Mayor and Cabinet approved the 2026/2027 annual business plan for the Besson Street joint venture with Grainger, extended funding and option agreements to 1 October 2027, and appointed a new council representative.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedBesson Street LLP plan for 2026/2027 with Grainger joint venture
MoneyLoan value increased, amount in Part 2Specific sums held in confidential Part 2 report
What happens nextS73 planning decision October 2026GLA grant confirmation also expected October 2026
Who it affectsTelegraph Hill ward, New CrossFuture Besson Street tenants and nearby residents
What was decided
Approved the 2026/2027 annual business plan for the Besson Street LLP, the 50/50 joint venture with Grainger plc for a Build to Rent development in Telegraph Hill, and delegated authority to the Executive Director for Place to implement it. Report P10, P11, P12, P17
Extended the Pre-Development Loan Agreement to 1 October 2027, with an increase in the maximum loan value, and extended the Option Agreement to the same date. Report P13, P17
Appointed Nnenna Urum-Eke to replace Patrick Dubeck as the council's second Member Representative on Lewisham Grainger Holdings LLP and Besson Street LLP, and as Director of Besson Street Second Member Limited, and agreed a Deed of Indemnity. Report P14, P15, P17
Why
The development has faced significant challenges over the past decade and remains unviable at present, with the update taking account of ongoing viability pressures, the Section 73 application, and pending GLA grant funding applications. Report P16
GLA Social and Affordable Homes Programme grant funding is needed to deliver the 35% affordable homes and community facilities, with results anticipated in Autumn 2026; an application to the New Homes Accelerator was also submitted in February 2026. Report P16
The Section 73 application increases the number of homes from 324 to 383, with affordable homes rising from 114 to 134, while aligning fire safety design with the latest Approved Document B and BS9991:2024 and switching to a decentralised heat pump strategy. Report P25
What happens next
Section 73 planning determination and GLA grant confirmation are both expected in October 2026, after which a comprehensive update on the procurement strategy will follow. Report 6.29, P31
Completion of RIBA Stage 4a design and main contractor PQQ is scheduled from November 2026 to March 2027, with main contractor tendering from March to June 2027. Report 6.29, P31, P32
The Pre-Construction Services Agreement and Gateway 2 preparation are planned from June to November 2027, with main works currently scheduled from July 2028 to August 2031. Report 6.29, P33, P34, P35
Options considered
Chosen: Extend the Pre-Development Loan Agreement and Option Agreement to 1 October 2027 with an increased maximum loan value. Aligns agreements with the updated development programme and the anticipated start of the Pre-Construction Services Agreement with the preferred main contractor Report P13
Rejected: Keep the existing loan and option arrangements. The current loan agreement expires at the end of September 2026 and the option longstop date was previously set to May 2027, so a further extension is needed to keep the scheme in delivery
Implications
Financial: The development remains unviable and the council is asked to extend a pre-development loan; the Business for Lewisham Commercial Accountant provided comments for the Executive Director of Finance, Digital and Corporate Resources. Report P9, P45
Legal: The council relies on the general power of competence in section 1 of the Localism Act 2011 and may indemnify officers under the Local Authorities (Indemnities for Members and Officers) Order 2004, save for fraud, deliberate wrongdoing or recklessness.
Equalities: The scheme will deliver 134 affordable homes, wheelchair-accessible homes and community facilities, with homes built to high environmental standards intended to help alleviate fuel poverty.
Climate: Carbon emission reductions are expected in excess of 60% above Part L 2021 requirements, with Passivhaus design standards, around 550 cycle parking spaces, sustainable drainage and biodiversity enhancements.
Risk: Commercial risks and construction risks are set out in the Part 2 report; the project must secure Gateway 1 and Gateway 2 approvals under the Building Safety Act before a building contract can be signed. Report P36
Staffing: Nnenna Urum-Eke, Assistant Director for Housing Development, is appointed to two LLP boards and as a Director of Besson Street Second Member Limited, replacing Patrick Dubeck following his departure from the council. Report P8, P14
Who and where
Future residents of the Besson Street development in Telegraph Hill ward, New Cross, including 134 affordable homes at 35% of the scheme Report P6
Existing residents of Telegraph Hill ward, including neighbours, the Besson Street Trust, the Music Room and local community groups consulted in January 2026 Report P6
Lewisham Council as 50% joint venture partner, sharing risk and long-term income with Grainger plc
A future For-Profit Registered Provider to be set up by Besson Street LLP to draw down the GLA grant and manage the affordable homes
Timeline
20 January 2026: Public consultation event held at The Sommerville on Queen's Road, attended by 80 people
26 January 2026: 8th Besson Street Business Plan approved by Mayor and Cabinet Report P16, P43
25 February 2026: New Homes Accelerator application submitted to the GLA
March 2026: Section 73 planning application submitted Report P25
15 April 2026: Social and Affordable Homes Programme grant application submitted to the GLA
9 September 2026: Mayor and Cabinet decision approving the 9th Annual Business Plan Report P3
October 2026: S73 planning consent expected and GLA grant confirmation expected Report 6.29, P31
November 2026 to March 2027: Completion of RIBA Stage 4a design and main contractor PQQ Report 6.29, P31
March to June 2027: Main contractor tender process Report 6.29, P32
1 October 2027: New longstop date for the Pre-Development Loan Agreement and Option Agreement Report P13
June to November 2027: Pre-Construction Services Agreement and Gateway 2 preparation Report 6.29, P33
November 2027 to April 2028: Gateway 2 determination (assumed 22 weeks) Report 6.29, P34
July 2028: Start on site for main works Report 6.29, P35
August 2031: Practical completion Report 6.29, P35
Plain English for the jargon
Joint Venture (JV): A 50/50 partnership between Lewisham Council and Grainger plc to deliver a Build to Rent housing scheme
Build to Rent: Homes built specifically for the rental market and owned by the company that developed them
Pre-Development Loan Agreement: Funding provided by Grainger Bank to the JV for the early design and planning stage of the scheme
Option Agreement: Agreement governing the future transfer of the Besson Street site from the Council to Besson Street LLP once viability and development conditions are met
Section 73 application: Application to vary an existing planning consent, here to amend building designs, fire safety and energy strategy
Gateway 1 and Gateway 2: Building Safety Act approval stages that must be secured before a building contract can be signed and main construction works can start
London Living Rent: Intermediate affordable rent product aimed at low to median earning Lewisham households
Passivhaus: A high energy efficiency design standard for buildings
GLA: Greater London Authority, which administers grant programmes including the Social and Affordable Homes Programme
For-Profit Registered Provider: A registered provider organisation that manages affordable housing and is to be set up by Besson Street LLP
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item16
Resolved
Mayor and Cabinet • Approved the Annual Besson Street Business Plan 2026/2027 • Delegated authority to the Executive Director for Place, in consultation with Executive Director for Finance, Digital Corporate Resources, to implement the Besson Street Business Plan. • Approved the extension of the Pre-Development Loan Agreement, including an increase in the maximum loan value, to 1 October 2027, and the extension of the Option Agreement to the same date. • Approved the appointment of Nnenna Urum-Eke (to replace Patrick Dubeck) as a Member Representative on Lewisham Grainger Holdings LLP and Besson Street LLP and as a Director of Besson Street Second Member Limited; and • Agreed to enter into a Deed of Indemnity with Nnenna Urum-Eke in respect of the appointments referred to in recommendation.
Word for word from the decision Lewisham published for this meeting.Source: councilmeetings.lewisham.gov.uk
Besson Street: Business Plan Update Date: 9 September 2026
Key decision: Yes
Class: Part 1
Ward(s) affected: Telegraph Hill
Contributors:
Nnenna Urum-Eke, Assistant Director for Housing Development
Sandra Gray, Building for Lewisham Commercial Accountant
Outline and recommendations It is recommended that the Mayor & Cabinet:
Approve the 2026-2027 Council’s Annual Business Plan for the Besson Street LLP.
Delegate authority to the Executive Director for Place in consultation with the Executive Director for Finance, Digital Corporate Resources to implement the Besson Street Business Plan.
Approve the extension of the Pre-Development Loan Agreement, including an increase in the maximum loan value, to 1 October 2027, and the extension of the Option Agreement to the same date.
Approve the appointment of Nnenna Urum-Eke (to replace Patrick Dubeck) as a Member Representative on Lewisham Grainger Holdings LLP and Besson Street LLP and as a Director of Besson Street Second Member Limited; and
Agrees to enter into a Deed of Indemnity with Nnenna Urum-Eke in respect of the appointments in a form agreed with the Director of Law and Corporate Governance.
Timeline of engagement and decision-making Business Plan Part 1 report, approved by Mayor and Cabinet, 26 January 2026 1. Summary 1.1. As part of the JV Governance, Reporting and Council Oversight arrangements approved by Mayor and Cabinet in March 2018, it was agreed that the Besson Street Business Plan would be updated annually and then presented to Mayor and Cabinet for approval. 1.2. The development of the Besson Street scheme has faced a range of significant challenges over the past decade, many of which reflect the wider obstacles affecting residential development across London and the UK. These factors have impacted the scheme's delivery and, at present, the development remains unviable. 1.3. This report provides an update to the 2025/26 Business Plan, taking account of ongoing viability pressures, the outcome of the Section 73 planning application, and the GLA grant funding applications, the results of which are anticipated in Autumn 2026. The report sets out the current position of the scheme and the actions being taken to improve viability and support progression towards delivery.
2. Recommendations It is recommended that the Mayor & Cabinet: 2.1. Approve the Annual Besson Street Business Plan 2026/2027 2.2. Delegate authority to the Executive Director for Place, in consultation with Executive Director for Finance, Digital Corporate Resources, to implement the Besson Street Business Plan. 2.3. Approve the extension of the Pre-Development Loan Agreement, including an increase in the maximum loan value, to 1 October 2027, and the extension of the Option Agreement to the same date. 2.4. Approve the appointment of Nnenna Urum-Eke (to replace Patrick Dubeck) as a Member Representative on Lewisham Grainger Holdings LLP and Besson Street LLP and as a Director of Besson Street Second Member Limited; and 2.5. Agrees to enter into a Deed of Indemnity with Nnenna Urum-Eke in respect of the appointments referred to in recommendation 2.4.
3. Policy Context 3.1. This report aligns with the ambitions and priorities of the administration elected in May 2026, as reflected within the Council’s emerging corporate delivery plan, including: • Safe, affordable homes • Cleaner streets and greener neighbourhoods • An economy of care • Healthier, happier communities • Justice, sanctuary and care 3.2. This report is closely aligned to the administration’s priority relating to tackling the Housing Crisis, by delivering more social homes for Lewisham residents, working to provide as many people as possible with safe, comfortable accommodation that they can be proud of and happy living in.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.