It was agreed to amend this and there was only one concern around the planned number of days spent on Finance & Procurement – a query was raised whether 10 days was enough for the Property Investment Strategy audit. [name removed] and [name removed] agreed and stated that once an area was scoped and identified a better idea of the number of days involved was mapped. The planned days are an estimate as some areas could take less or some more but the plan would be monitored throughout the year. RESOLVED :- Members approved the Annual Planned Audit Work Programme.
Word for word from the decision Lichfield published for this meeting.Source: democracy.lichfielddc.gov.uk
INTERNAL AUDIT PLAN 2019/20 Cabinet Member for Finance & Democratic Services Date: 27 March 2019 Agenda Item: 7 Contact Officer: Angela Struthers Tel Number: 01543308030 Email: [email protected] AUDIT & Key Decision? NO MEMBER Local Ward Members STANDARDS COMMITTEE
1. Executive Summary 1.1 To consider the 2019/20 Work Programme of the Internal Audit Section.
2. Recommendations 2.1 To approve the Annual Planned Audit Work Programme as detailed at Appendix 1.
3. Background 3.1 As part of its responsibilities the Internal Audit Section is responsible for conducting independent reviews of the Council’s internal control systems as a contribution towards the proper, economic, efficient and effective use of the Council’s resources and feeds in to the Annual Governance Statement. The diagram below shows how the setting of the plan forms part of this process. 3.2 The Internal Audit Section’s duties are laid out in legislation, the Accounts and Audit Regulations 2015 and the Council’s Financial Procedure Rules. 3.3 This year, as in previous years, we are proposing to take a hybrid approach. A review of the Audit Universe (all possible audits that can be done) has been undertaken, considering the risk rating assigned, the frequency of review and also the previous audit opinion given. Also included in the work programme are new or emerging areas and areas which we feel would benefit from audit attention. The aim is to move away from routine audit and focus on high risk, new and emerging areas in order to provide a responsive service which can inform and guide council and service response to the challenges of Local Government and support continuous improvement.
3.3In order to produce the Annual Planned Audit Work Programme (Appendix 1), we need to work out the resources available to undertake planned audit work, taking into account all the other demands on the audit team with a full time equivalent (FTE) of 2.7(including an Apprentice), we have identified that we have 297 days available. This will assist in ensuring an efficient, cost effective service whilst still delivering audit work programme which gives annual assurance on the soundness of the governance, risk management and control arrangements to be given to the Council.
3.4Having calculated that we have 297 days available, we then took the following into account: -
What we were already committed to do, e.g. Key Financial Systems work, Fraud Awareness/Proactive Fraud work, Pensions Assurance work, National Fraud Initiative, Annual Governance Statement and Follow Up Reviews. Areas identified by Internal Audit, using their understanding of the Council and their own risk assessments.
3.5The Annual Planned Audit Work Programme has been discussed and agreed with the Leadership Team, but separate meetings will be held with Directors & Heads of Service to ensure the right focus for the allocated days is maintained as the year progresses.
3.6By delivering this Planned Audit Work Programme, Internal Audit will either provide senior managers with the necessary assurance that internal controls are in place and are operating effectively, or will be able to point to key areas of weakness for their consideration, in relation to the key risk areas of the Council.
3.8At the conclusion of each audit review, an audit report will be issued to Officers and appropriate Members, as per the Internal Audit Protocol, detailing the findings of the review together with any recommendations required to be implemented in order to achieve the required level of control.
3.9A progress report of the work undertaken by the Internal Audit Section is presented to the Audit & Member Standards Committee on a regular basis
Alternative Options 1. None.
Consultation 1. Leadership Team has been consulted regarding the inclusion of the audit reviews in the Annual Planned Work Programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.