- The Committee approved and recommended to full Council the adoption of the updated Contract Procedure Rules as Part 4 Section 7 of Lichfield District Council’s Constitution with an amendment to Section T – Changing and Extending Contracts as suggested above.
Word for word from the decision Lichfield published for this meeting.Source: democracy.lichfielddc.gov.uk
Appendix A Formatted: Right Formatted: Font: 12 pt
SECTION 7
CONTRACT PROCEDURE RULES
1 Part 4 Summary of the main controls and procedures shown in these Contract Procedure Rules (“CPRs”)
THESE CONTRACT PROCEDURE RULES MUST BE READ IN ACCORDANCE WITH THE COUNCIL’S CURRENT PROCUREMENT PLAN
Do the rules apply? Check the guidance on the Council’s Intranet and in the event of any doubt you can contact the Procurement ServiceMonitoring Officer about whether these CPRs apply to a specific contract. If there is any doubt then the Monitoring Officer should be contacted as they are responsible for making the final decision in ensuring the proposed route is in line with the constitution and law.
Responsibility - Individual Heads of Service will be responsible for governing the procurement process, deciding whether we should buy anything and if so ensuring that there is budget for the proposed purchase. If the rules are breached it is potentially a matter for disciplinary action. (see Rule C11).
Joint Procurement – Heads of Service must look at options for joint procurement and use of Framework agreements. (See Rule C11 and Section F).
Compliance with other policies including equality, health and safety- When buying anything for us, you have to consider the importance and effect of our other policies, for example, the relevant Health and Safety Policy and the Council’s Equality Statement. (See Rules B3 and D3).
Conflicts - If you are involved in the procurement process or manage any contracts, you must declare any possible conflict of interest to your manager and the Monitoring Officer. The golden rule is, iIf in doubt then it should be ; declared it; (See Rules C2 - C4).
Contract Value - The contract value does not just mean its yearly value but all payments over the length of the contract (including any extensions – even if those extensions are never activated) – special rules apply if there is no set length for the contract (see Rules C7-8 and H1-3).
Record Retention - You must keep all tender-related documents in line with our policies on keeping documents and to satisfy audit requirements. You must also place all contracts over £5,000 the contract on the Contract Register (see Rule N1-N3).
Publicising the Contract – All invitations to tender for contracts at and over £25,000 must be placed on the Tenders and Contracts part of the website, and the Government’s Contract Finder website and all awarded contracts over £5,000 must be entered on to the Council’s contract register and those awards at and over £25,000 must also be entered on the Contract Finder Website. (See Rules N4, F10 and F13).
Delegations - Staff involved in the procurement process must act in line with the Scheme of Delegation. Heads of Service and Members of Leadership Team have authority to sign contracts up to £75,000. Contracts of £75,000 and above must have the authority of a Member of Leadership team and a member of Cabinet (see rule F10).
Follow the process carefully - You must follow the correct tendering process – this will depend on the value of the contract and the extent to which a framework agreement is 2 Part 4 already in place.
Higher Value Contracts - For all contracts over £75,000, you must consult the Procurement Service Monitoring Officer before buying what is needed (See Rule F9 - 10).
Electronic Procurement - Electronic procurement (including e-tendering) is a developing area and one the Council is keen to encourage. However it is important that you discuss this with the Procurement Service Monitoring Officer to ensure compliance with the Council’s rules. (See Rules F16 and 17).
Tender Evaluation - When you evaluate a tender using MEAT (most economically advantageous tender), you must use the tender evaluation methodology referred to in these CPRs (See Rules M1 and M2).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.