Resolved
The Committee noted the report and provided comments where necessary.
Overview & Scrutiny Committee noted this item on Thursday 5 June 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee noted the report and provided comments where necessary.
3.1As part of our ongoing commitment to improve the quality of our Development Management services we launched two three-month trials aimed at testing changes to the process for householder and minor planning applications on Monday 3 February. The main aims of the trial were to: • Improve the speed of decision making, • Reduce the time taken to process Householder and Minor applications, with a target of 4-5 weeks for determination, • Eradicate the use of extensions of time, • Reduce the backlog of applications. 3.2 The main features of the trial include:
A Planning Focus Day Tuesdays were set aside for planning officers to focus solely on determining applications and clearing any backlog of applications that have built up. Officers use a specially worded out of office message and responded to messages within 48 hours Publicising planning For a three-month period, we publicised the majority of applications applications by displaying more yellow site notices rather than sending out traditional letters
No amendments Tested speeding up decision making and removing unnecessary delays by not accepting amendments on minor applications. Previously the team would accept amendments to applications for a charge. All agents were written to advising them of this change.
3.3The feedback and results are summarised below.
Feedback and Results- Householder Applications
3.4Since the trials began, there have been marked improvements to the speed in processing of householder applications. The table below sets out the statistics achieved within the 3 months, noting that the trials started on February 1st 2025. September ‘24 and January ‘25 have been provided for comparison purposes.
3.5In summary: • The no amendment policy introduced last April (2024) has been strictly enforced. • 90 householder applications processed during the trials (which began in February), of these 2 applications were extended (2%). Both were linked to corporate complaints, and one was also a committee item, now linked to a JR challenge. • The number of householder applications dealt within 6 weeks of submission has significantly increased, with nearly 20% of apps being determined within week 4/5. • 42 decisions issued in April - high number despite all three officers spending 6 days at university in London and supporting elections as poll clerks/ presiding officers & count assistants.
3.6During the first part of the trial, officers dealing with the householder applications also dealt with administrative support and back-office processes for the whole team, when it was noted, there was a definite spike in applications received and validated. On 1st April 2025, a nationally set increase in planning application fees was introduced, which resulted in an influx of planning application submissions in March, where, as applicants/agents attempted to avoid the increased cost of applying for planning permission. 3.7 It is worth highlighting that Lichfield District Council are, at this point, based on March and April’s data, ranked no. 1 in England for processing 98% of Householder applications within the statutory 8-week time period. More information on this is set out below.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Planning Performance ProgressReport | 218 KB | DownloadRead as text |
Follow Overview & Scrutiny Committee at Lichfield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2026 | Exclusion of press and public“That as publicity would be prejudicial to the public interest by reason of the confidential nature of the business t... | Decided | Open |
| 27 Jan 2026 | Review of the Young Voices EventRESOLVED : The Committee reviewed the information set out in the report including feedback received from attendees an... | Decided | Open |
| 18 Nov 2025 | Compliments, complaints, MP and FOI enquiries report 2024/2025RESOLVED : That the O&S Committee commented and provided feedback on the customer feedback annual review 2024/2025. T... | Noted | Open |
| 18 Nov 2025 | Planning Performance Progress (6 month review)It was agreed that sending the supplementary report out earlier is something that could be explored. The Chief Execut... | Agreed | Open |
| 18 Sep 2025 | LWM Strategic End of Year ReviewRESOLVED : The committee reviewed the 2024/25 Annual Report for LWM and scrutinised the details enclosed. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.