Strategic Plan Progress - Quarterly Review

Noted Executive 1 paper

Executive noted this item on Monday 26 February 2018. Below is the council's own wording, with the papers it was decided on.

Item126

Resolved

Decision That the report be noted. None. 20 strategic projects were being monitored, 18 of which were currently on track in terms of their physical and financial milestones and risk profiles. 8 of these projects had been completed and were currently awaiting a Post Implementation Review for submission and sign-off. There were no projects off track in terms of physical progress, financial position and risk analysis. Two projects were currently off track in either one or two of the areas of monitoring and beyond just missing Post Implementation Reviews. These were noted as follows: · CCTV upgrade – works schedule, staff training and contracts milestones had missed deadlines but work was drawing to an end; · compulsory acquisition of 13 Albany Terrace – 5 milestones had been missed, primarily relating to the legal aspects. Strategic projects that had completed their defined actions and were awaiting the completion of a Post Implementation Review were noted as follows: · car park safety – Broadgate car park improvements; · new build scheme – Birchwood Bungalows (20 new build affordable units); · phase 2 proposed alterations – City Hall improvements; · replacement of the CMS depot master – updated software; · St Botolph’s Court – modernisation project at sheltered housing complex; · new surface car parks – purchase of two new surface car parks in the city. The following projects had submitted an initial Post Implementation Review but additional data was requested, so they would be finalised in the next quarter: · Data Register and back up; · Bereavement Services – improvements to facilities. The report set out mega project updates in respect of the Western Growth Corridor and the Transport Hub, consisting of the Multi-Storey Car Park and the Bus Station. Updates were also provided on the Section 106 Group, which was responsible for the monitoring of the Council’s Section 106 Agreements, together with annual ongoing projects including: · disabled facilities grants; · delivering decent homes in the private sector; · the housing revenue account business plan.
Word for word from the decision Lincoln published for this meeting. Source: democratic.lincoln.gov.uk

Follow this further

Built from Lincoln's papers

What the report saysPro

Report to Executive

Purpose of report

1.1To provide the Executive with a progress report on the strategic projects, against their milestones for the third quarter of 2017/18.

2. Programme Summary

2.1There are currently 20 strategic projects being monitored.

2.218 projects are currently on track in terms of their physical and financial milestones and risk profiles.

Of these 8 projects have been completed and are currently awaiting a Post Implementation Review to be submitted and signed off.

2.3There are no projects off track in terms of all three of the areas of monitoring: physical progress, financial position or risk analysis.

2.4There are 2 projects currently off track in either one or two of the areas of monitoring above and beyond just a missing PIR.

 CCTV Upgrade – Works schedule, Staff Training, and contracts milestones have missed deadlines but work is drawing to an end.  Compulsory Acquisition - 13 Albany Terrace – 5 missed milestones, primarily relating to the legal aspects

It has been concluded that there are no projects of sufficient concern to bring to CMT’s attention.

3. New Projects Approved

3.11 new project was reviewed and recommended to the Executive for approval in the third quarter. Land and Buildings Acquisition

This project is an outcome of the Asset Rationalisation report presented to the Executive on 8th January 2018.

The project is to purchase a piece of land and building under construction within the city that is expected to generate surplus revenue income for the Council.

This scheme was reported to Executive on 8th January 2018 (minute no.112). 4. Completed Projects and those awaiting PIR’s

4.1Where it is felt appropriate and beneficial for continuous improvement at the conclusion of a project a completion report and post implementation review (PIR) will be produced. Once they are received and reviewed a project is considered to be complete.

4.2Strategic Projects awaiting completion of a PIR

There are eight projects which have completed their defined actions and just now await the completion of a PIR

 Car Park Safety - Broadgate Car Park improvements  New Build Scheme – Birchwood Bungalows, 20 new build affordable units  Phase 2 Proposed alterations – City Hall improvements  Replace CMS Depot Master – (Servitor project) updated software  St Botolphs Court – Modernisation project at Sheltered Housing Complex  New Surface Car Parks – Purchase of two new surface car parks in the city

The following projects have submitted an initial PIR, but additional data was requested, so they will be finalised in the next quarter  DR and back up  Bereavement Services improvements to facilities

4.3There were no projects signed off as completed during the third quarter.

5. Mega Project Update – Western Growth Corridor

5.1The public consultation on the proposed masterplan ended on 15 November 2017 and this feedback is being fully considered alongside the results of the updated highway traffic modelling work which we received at the beginning of January 2018.

The key concern from the consultation has been the traffic impact so it is important to ensure that the most suitable transport and movement strategy is identified and incorporated into the Masterplan. Once this has been agreed in principle with the statutory organisations an updated version of the masterplan will be produced.

At this point, a revised project plan (including a timetable for delivery, cost plan and a schedule of proposed Member briefings and public consultation/workshops) will be prepared for consideration by the Executive (expected to be in early Summer 2018).

5.2Mega Project Update – Transport HUB

Multi Storey Car Park

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Strategic Plan Progress: Quarterly ReviewReport 86 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 6 attended
RM
Councillor Ric MetcalfeChair, present
DN
Councillor Donald NannestadVice-Chair, present
RK
Councillor Rosanne KirkCommittee Member, present
NM
Councillor Neil MurrayCommittee Member, present
FS
Councillor Fay SmithCommittee Member, present
PW
Councillor Peter WestCommittee Member, present

On this subject at Lincoln

Search all
  1. Strategic Plan Progress - Quarterly ReviewThis decision
  2. Vision 2030 Strategic Plan - 24 Month Delivery PlanApproved
  3. Vision 2030 Strategic PlanApproved
  4. Central Lincolnshire Joint Strategic Planning Committee/Local Plan Annual Report 2022/23Noted
  5. Central Lincolnshire Joint Strategic Planning Committee/ Local Plan Annual Report 2021/22Noted
  6. Vision 2025 Strategic PlanApproved

More from Lincoln Executive

All decisions
MeetingDecisionOutcome
15 Sep 2026 Confirmation of Minutes - 18 August 2026RESOLVED that the minutes of the meeting held on 18 August 2026 be confirmed and signed by the Chair as a correct rec... Decided Open
15 Sep 2026 Variation to the Constitution – Responsibility for Functions; Adoption of National Scheme of Delegation and Amendments to Planning ProtocolsDecision 1. That a variation to Part 3 – Responsibility for Functions of the Council’s Constitution to reflect the ch... Approved Open
15 Sep 2026 Updated Rechargeable Repairs PolicyDecision 1. That the policy be implemented and briefing sessions to all staff within customer services and housing on... Approved Open
15 Sep 2026 Playground FundingDecision That the progression of this new project and inclusion of a capital estimate of £511,335 in the General Inve... Approved Open
15 Sep 2026 Exclusion of the Press and PublicRESOLVED that the press and public be excluded from the meeting during consideration of the following item of busines... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies