City of Lincoln Council
Executive, Wednesday 28 August 2019 at 6.00pm

Cornhill, Markets & City Centre Vibrancy

Approved Executive 1 paper

Executive approved this item on Wednesday 28 August 2019. Below is the council's own wording, with the papers it was decided on.

Item30

Resolved

Decision That the Executive: (1) Notes the proposed scope of works, process and timescale for the demolition of the Cornhill Kiosk, retention and protection of the tree and provision of integral seating as a first phase of improvements to Cornhill Square. (2) Authorises officers to develop proposals for a second phase of improvement works to include paving, seating, street furniture and a potential water feature, in consultation with key partners, and notes that the implementation of the final scheme will be subject to securing external funding. (3) Authorises officers to procure and commission feasibility and design works to inform a full business case for the future development of the Central Market building and City Square, in consultation with key partners. (4) Approves the use of the ring-fenced budget of £300,000 to support the cost of the above schemes and as leverage to secure additional, external and match-funding as described within the report. (5) Approves to delegate the final allocation of the £300,000 budget between the identified projects to the Major Development Strategic Director and Chief Finance Officer. Other options considered and rejected were set out in paragraphs 7.1 and 7.2 of the report. Updates were reported on the following aspects of the Cornhill, markets and city centre: Cornhill Phase 1 Consent had been granted for the demolition of the kiosk and proposals had been modified to allow for the retention and protection of the associated tree. Designs had been produced to allow for the protection of the three roots through a ‘root bridge’ system and the creation of a new seating plinth below the tree canopy. The cost of the scheme was expected to increase as a result of the additional trees. It was proposed to prioritise this scheme and fund the work from a ring-fenced £300,000 budget. The residual budget would then be used to support the implementation of the phase 2 works and Central Market. It was anticipated that works would commence on-site in November 2019 to be completed within three months, however, it was noted that fee proposals were due to be returned by 13 September 2019 with the contract due to be let early in October. Cornhill Phase 2 Concept designs and estimated costs were also being produced for a wider scheme of public realm improvements to Cornhill Square. This included natural stone paving, with a palette of materials to mirror the wider Cornhill Quarter, new seating and a potential water feature. The final scheme design would be subject to consultation with key ... view the full minutes text for item 30.
Word for word from the decision Lincoln published for this meeting. Source: democratic.lincoln.gov.uk

Follow this further

Built from Lincoln's papers

What the report saysPro

Report to Executive

Purpose of report

1.1To update Members on proposals seek approval to: 1. To provide an update on a scheme of works which has already been approved to demolish the Cornhill Kiosk, and put in place measures to protect the existing tree, create a new seating platform and restore the immediate public realm. To seek approval to: 2. Develop proposals for a second phase of improvement works to include paving, seating, street furniture and a potential water feature, in consultation with key partners. The implementation of this scheme will be subject to securing additional, external funds for implementation. 3. Undertake feasibility and design works to inform a full business case for the future development of the Central Market building and City Square, in consultation with key partners. 4. To utilise the approved budget of £300k to support the cost of the above work and as leverage to secure additional, external match-funding. 2. Executive Summary

2.1This report provides an update on proposals for the Cornhill Square and Central Market. This includes a first phase of works which has already been approved to demolish the Cornhill Kiosk and put in place measures to protect the existing tree, create a new seating platform and restore the immediate public realm.

Further approvals are sought to develop proposals for a second phase of public realm works at the Cornhill Square to connect with the new paving work already carried out as part of the Cornhill Quarter regeneration scheme. The implementation of this scheme will be subject to securing additional external funding.

Finally, Officers are seeking approval to procure design and feasibility work to inform a full business case for the development and restoration of the Central Market and City Square. These projects form part of a wider City Centre Vibrancy programme with the aim of securing Lincoln’s future as a vibrant, sustainable and inclusive City.

An initial resource of £300k has been identified to support these schemes and assist in leveraging additional funding to enable full delivery.

Background

3.1The City of Lincoln Council and Local Partners established a vision for the City Centre through a comprehensive Master planning process over 12 years ago. This vision has been refreshed and embedded in current policy and a number of key interventions have been delivered to improve the townscape, connectivity and overall offer, notably a new £30m Transport Hub and £70m redevelopment of the Cornhill Quarter. 3.2 The Council is now developing a new City Centre Vibrancy programme to build on this success and to bring partners together to co-ordinate the future development of the High Street. The key driver is the need to adapt and to future proof the City to provide for a growing population and secure its position as a vibrant, sustainable and inclusive regional centre. The restoration and development of public assets such as the Cornhill Square and Central market are integral to this programme and a key priority for the Council.

3.3A budget of £300k has been allocated to support this programme of works within the MTFS 2019-24, funded from the 100% Business Rates Retention pilot. It is proposed to utilise these funds in order to progress work on the Cornhill and Central Market and to lever in additional, external funds to enable full delivery.

4. Programme of Work

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cornhill, Markets & City Centre VibrancyReport 1.2 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 6 attended
RM
Councillor Ric MetcalfeChair, present
DN
Councillor Donald NannestadVice-Chair, present
CB
Councillor Chris BurkeCommittee Member, present
BB
Councillor Bob BushellCommittee Member, present
RK
Councillor Rosanne KirkCommittee Member, present
NM
Councillor Neil MurrayCommittee Member, present

On this subject at Lincoln

Search all
  1. Cornhill, Markets & City Centre VibrancyThis decision
  2. Cornhill, Markets and City Centre Vibrancy ProjectAgreed

More from Lincoln Executive

All decisions
MeetingDecisionOutcome
15 Sep 2026 Confirmation of Minutes - 18 August 2026RESOLVED that the minutes of the meeting held on 18 August 2026 be confirmed and signed by the Chair as a correct rec... Decided Open
15 Sep 2026 Variation to the Constitution – Responsibility for Functions; Adoption of National Scheme of Delegation and Amendments to Planning ProtocolsDecision 1. That a variation to Part 3 – Responsibility for Functions of the Council’s Constitution to reflect the ch... Approved Open
15 Sep 2026 Updated Rechargeable Repairs PolicyDecision 1. That the policy be implemented and briefing sessions to all staff within customer services and housing on... Approved Open
15 Sep 2026 Playground FundingDecision That the progression of this new project and inclusion of a capital estimate of £511,335 in the General Inve... Approved Open
15 Sep 2026 Exclusion of the Press and PublicRESOLVED that the press and public be excluded from the meeting during consideration of the following item of busines... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies