RESOLVED that: 1) Feedback be provided to the committee on whether a post implementation review took place on the Boultham Park Project 2) O fficers be tasked to feedback the reasons why the Malware anti-virus and IT Policy had been extended until December 3) A n update on the changes to the Internal Audit Recommendations be referred to Executive 4) Further updates on the audit recommendations be presented to members in future meetings . 5) Updates on audit recommendations older than 12 months be noted.
Word for word from the decision Lincoln published for this meeting.Source: democratic.lincoln.gov.uk
Audit Recommendations Appendix A September 2020 Reports that are over 2 years old (under the Follow Up protocol these recommendations will no longer be monitored by IA and Audit Committee). They are still available to management on the recommendation tracker.
Management have been notified of the new protocol and advised to continue monitoring these actions via DMTs.
Audit Area Date Assurance No of Implmntd Outstanding Comments / Progress Recs (extended or overdue)
ICT Mobile Devices Mar 16 Substantial 6 5 1 High Identify mobile IT assets not connected to the network. Officers previously attended Committee Rollout of new devices to staff will be linked to specific employees Remove Responsive Jun 17 Substantial 6 5 1 Medium Take photos of repairs – linked to software upgrade Repairs Officers previously attended Committee Remove Boultham Park Jun 17 High 2 1 1 Medium Complete revised partnership agreement Refurbishment Officers previously attended Committee. Remove IT Disaster Oct 17 Substantial 18 17 1 Medium Ensure that the next BCP desktop exercise includes the IT DR Recovery plan IT DR is being monitored as an AGS issue Remove Code of Corporate Oct 17 Substantial 6 5 1 Medium Refresh of Asset Management Plan Governance Remove IT Applications Nov 17 Substantial 6 5 1 Medium Review the agreement arrangements for MyInfo Remove
Tenancy Services Jan 18 Substantial 11 3 2 High The two high priority actions: 6 Medium • Consider a permanent transfer of the Voids team to Tenancy Services (High) – Void Support is with Tenancy Services now (now completed) • Develop pre-tenancy processes to improve sustainability (High) – ongoing, process being mapped. Was on hold due to Covid budget funding but the working group has been set up and pilot should start in October. • Medium actions will be removed Reports that are between 1 and 2 years old
Audit Area Date Assurance No of Implmntd Outstanding Not Yet Comments / Progress Recs (extended or Due overdue)
HMO Licensing Jun 18 Limited 20 16 3 High Awaiting Update – moved to Dec 2020 and Hazards 1 Medium Follow up • Consider automating the process to report review Dec 19 on and monitor conditions. (High) • APP system reporting on gas certificates due / overdue. (High) • Reconfigure the IT system so that different codes can be used to record the hazard and category (High) • Remind staff of the need to ensure that the process for monitoring and reminding of licences expiring operates consistently.
Risk Management Jul 18 Substantial 8 7 1 Medium Periodic review of partnership risk registers This is linked to current work to update the Partnership register. Remove
Commercialisation Oct 18 Substantial 4 1 3 Medium The CFO has advised that the TFS programme has changed focus and this area is no longer a priority. The recommendations will be marked as superseded but can be resurrected in the future. Remove IT Applications Oct 18 Limited 8 1 1 High Update & circulate System Administrator guidance 6 Medium (High) Extended to December 2020 Malware / Anti- Nov 18 Substantial 9 7 1 High Device control software management (High) virus 1 Medium Extended to December 2020
Revised IT Security Policy (Med) Extended to December 2020
Transport Hub Dec 18 Substantial 3 2 1 Medium Formal project closure & post implementation review Extended to March 21 Reports that are less than 1 year old
Audit Area Date Assurance No of Implmntd Outstanding Not Yet Comments / Progress Recs (extended or Due overdue)
Fees & Charges Apr 19 Substantial 3 3 Med Moving forward with new issues and workloads arising from Covid unlikely to be progressed as part of the 21/22 process Remove
Information June Substantial 16 15 1 Medium Assist IAOs to review access to their network drives management 19 Extended to December 2020
Procurement OJEU July 19 Substantial 4 4 Ensure that the LPMM Checklist A and the PIR & Framework checklist include a prompt / requirement for 'lodging contracts with Legal Now completed
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Confirmation of Minutes - 1 June 2026RESOLVED that the minutes of the meeting held on 1 June 2026 be confirmed and signed by the Chair as a correct record.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.