Lincoln Town Deal Board, Friday 12 March 2021 at 10.00am

Project Updates

Agreed Committee 1 paper

Lincoln Town Deal Board agreed this item on Friday 12 March 2021. Below is the council's own wording, with the papers it was decided on.

Item40

Resolved

It was agreed, therefore, that it would potentially be very difficult for the Board to facilitate delivery of all fourteen projects as part of the Town Deal funding allocation. Lord Cormack, was of the opinion that the projects associated with the Drill Hall and Greyfriars were particularly important for Lincoln’s position as a centre of tourism in Lincolnshire and its status as a historic city. In respect of the Drill Hall, Lord Cormack said that there was no other public venue comparable in the city which should not be lost and instead must be improved and enhanced. Similarly, the Greyfriars was a significant historic part of the city. He declared an interest as President of Heritage Lincolnshire but stated that he would be disappointed to see these two projects disappear from the list as they preserved Lincoln and should be considered as priorities. Lord Cormack agreed, however, that some projects would need to be removed as £19 million, compared to the £25 million originally bid for, equated to nearly £1 million per project which, in terms of realistic deliverability, was not very much. Mary Stuart, Chair of the Lincoln Town Deal Board, was pleased to see that progress had been made with projects to date but agreed that the next couple of months would be key in determining which would progress to the next stage, with the likelihood being that the number of projects for inclusion would need to be reduced. Jacqui Bunce, NHS Lincolnshire, asked for further clarity in respect of the conditions that had been placed on projects. It was reported that conditions were set out in the Heads of Terms and related to five specific projects. The documentation included with the agenda pack for the ... view the full minutes text for item 40.
Word for word from the decision Lincoln published for this meeting. Source: democratic.lincoln.gov.uk

Follow this further

Built from Lincoln's papers

What the report saysPro

Report to Lincoln Town Deal Board

Project Update: Summary of Position, March 2021

£m @ Oct 2020 Key Updates @ March 21 Towns Co- Total Fund Funding Cost £ RIBA Tenure Outputs Timescale Commentary Project Stage (Start) No change n/a n/a 2021 Open CMS Development of Lincoln Connected Open CMS business case using the GLLEP Local Growth Assurance Framework. External guidance utilised to inform the business case approach.

Digital Screens

Sites have been surveyed and chosen for the new digital screens. Digital specifications have been drawn up. Work is also taking place on looking at a digital wallet and signage.

The Lincoln Create Fund

Being developed and work has been done with local cultural groups in the City to redefine how the fund may operate going forward to ensure joined up cultural support. Arts Council funding is being explored.

Light Up Lincoln

A small lighting trail was piloted in the Christmas period. This demonstrates the demand for the lighting projects. Discussions are taking place with regard to which sites and building lend themselves better for this programme. Lincoln Connected 1.514 0.542 2.056 Lincoln Made Smarter 1.290 1.050 2.340 New project sponsor; update to follow. 2023 Programme has been reviewed – estimated start on site/completion during 2023/24. No other progress on development of scheme. Awaiting decision on Lincoln Investment Plan before progressing further. Wigford Way/St. Mary's Street 5.040 0.000 5.040 2023 Programme has been reviewed – estimated start on site/completion during 2023/24. No other progress on development of scheme. Awaiting decision on Lincoln Investment Plan before progressing further. Sincil Bank Green Corridor 3.040 0.000 3.040 No change 3 Secure No change 2021 Phase 1 (Regeneration of 3G Pitch) is 90% completed and on schedule for completion in March 2021. Additional works incorporated to the programme have included new drainage systems and a spectator viewing gallery

Commissioned a construction consultancy to deliver a comprehensive procurement report which included an industry scoping of potential architects, designers and construction teams. This report has helped shape the next stage of our planning.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Project Update ReportReport 499 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 28 attended
AA
Angela AndrewsCommittee Member, expected
JB
James BatyCommittee Member, expected
PB
Peta BroughCommittee Member, expected
JB
Jacqui BunceCommittee Member, expected
RC
Ruth CarverCommittee Member, expected
TC
Tim ChambersCommittee Member, expected
RD
Councillor Richard DaviesCommittee Member, expected
JD
Joanne DavisonCommittee Member, expected
KE
Kate EllisCommittee Member, expected
SF
Scott FlemingCommittee Member, expected
AG
Andy GuthersonCommittee Member, expected
GH
Gary HeadlandCommittee Member, expected

All 28 on the meeting page

On this subject at Lincoln

Search all
  1. Project UpdatesThis decision
  2. Lincoln Tenants Panel Project UpdatesNoted
  3. Lincoln Tenants Panel Project UpdatesNoted
  4. Lincoln Tenants Panel Project UpdatesNoted

More from Lincoln Lincoln Town Deal Board

All decisions
MeetingDecisionOutcome
5 Jun 2026 Minutes of the Last Meeting held on 13 March 2026RESOLVED that the minutes from the 13 March 2026 be confirmed subject to the following amendment: Item 37: Apologies ... Decided Open
5 Jun 2026 Pride in Place Birchwood Programme UpdateRESOLVED that the report be noted. Noted Open
5 Jun 2026 Communications UpdateRESOLVED that the update be noted by Board members. Noted Open
5 Jun 2026 Exclusion of Press and PublicRESOLVED that the press and public be excluded from the meeting during consideration of the following item(s) of busi... Decided Open
5 Jun 2026 Focus Project Update & Risk Assessment (Paper)RESOLVED that the update be noted by Board members with thanks. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies