Decision That the Council’s strategic risks, as at the end of 2020/21, be noted. None. The Strategic Risk Register had been presented to the Executive in November 2020 and had contained fifteen strategic risks. Although regular monitoring of the Council’s strategic risks had continued since this time, there had been no report for quarter three. Since November 2020, the Strategic Risk Register, which had been reviewed by the Corporate Leadership Team, reflected the significant changes since the onset of the pandemic and the different challenges and opportunities, which the Council had faced. The review had identified that there had been some positive movement in the register, along with the addition of one new, emerging, risk. The updated register contained sixteen strategic risks, along with details of relevant mitigations. There had been a new risk added to the register: Mitigating against the risk of a successful cyber-attack against the council with significant / critical impact as part of the review.
Word for word from the decision Lincoln published for this meeting.Source: democratic.lincoln.gov.uk
1.1To provide the Executive with a status report of the revised Strategic Risk Register as at the end of 2020/21.
Background
2.1An update of the Strategic Risk Register was developed under the risk management approach of ‘risk appetite’, was last presented Members in November 2020 and contained fifteen strategic risks. Although regular monitoring of the Council’s strategic risks has continued since the last report to Members, reporting (along with other routine performance reporting for Council services), was not undertaken for quarter three.
2.2Since reporting to Members in November, the Strategic Risk Register has been refreshed and updated by the Corporate Leadership Team. The Strategic Risk Register reflects the significant change in circumstances in which the Council has been operating since the onset of the pandemic and the different challenges and opportunities it faces. This review has identified that there have been some positive movement in the register, along with the addition of one new, emerging, risk.
2.3The updated Register is contained with Part B of this agenda, it contains sixteen strategic risks which are listed below, along with details of relevant mitigations.
1) Failure to engage & influence effectively the Council’s strategic partners, council staff and all stakeholders to deliver against e.g. Council’s Vision 2025.
2) Failure to deliver a sustainable Medium Term Financial Strategy (that supports delivery of Vision 2025).
3) Failure to deliver the Towards Financial Sustainability Programme whilst ensuring the resilience of the Council.
4) Failure to ensure compliance with statutory duties/functions and appropriate governance arrangements are in place. 5) Failure to protect the local authority's vision 2025 due to changing structures and relationships in local government and impact on size, scale and scope of the Council.
6) Unable to meet the emerging changes required in the Council’s culture, behaviour and skills to support the delivery of the council’s Vision 2020/2025 and the transformational journey to one Council approach.
7) Insufficient levels of resilience and capacity exist in order to deliver key strategic projects & services within the Council.
8) Decline in the economic prosperity within the City Centre.
9) Failure to mitigate against the implications for the Council following the outcome of Brexit.
10) Failure to deliver key strategic projects.
11) Failure of the Council’s key contractors and partners to remain sustainable and continue to deliver value for money
12) Failure to work in partnership to sustain support to vulnerable residents post COVID19.
13) Failure to put in place safe working practices and social distancing measures to protect officers and service users.
14) Failure to comply with current safeguarding legislation and procedures.
15) Failure to Meet the councils PREVENT duties.
3.2A number of control actions have now been progressed or completed and the key movements are outlined as follows:
Risk 2. Failure to deliver a sustainable Medium Term Financial Strategy that supports delivery of Vision 2025 – a refreshed MTFS 21-26, reflecting the significant impact of Covid19 on the Council’s future financial projections, was approved by Full Council in March 21. This included a new, increased savings target.
Risk 3. Failure to deliver the Towards Financial Sustainability Programme whilst ensuring the resilience of the Council – The in year TFS target for 20/21 was overachieved. A programme of reviews is now in place for the increased savings target in the MTFs 21-26, with the first reviews being presented to the Executive in March 21.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Confirmation of Minutes - 18 August 2026RESOLVED that the minutes of the meeting held on 18 August 2026 be confirmed and signed by the Chair as a correct rec...
Updated Rechargeable Repairs PolicyDecision 1. That the policy be implemented and briefing sessions to all staff within customer services and housing on...
Exclusion of the Press and PublicRESOLVED that the press and public be excluded from the meeting during consideration of the following item of busines...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.