Resolved
RESOLVED that the request for the Council to appoint Mazars to undertake the be agreed.
Audit Committee agreed this item on Thursday 15 July 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the request for the Council to appoint Mazars to undertake the be agreed.
1.1This report requests the Audit Committee to agree to appoint the Council’s external auditor, Mazars, to undertake the 2021 Homes England Compliance Audit.
2.1The Council is currently under contract with Homes England (HE) to deliver several schemes: De Wint Court and 15 no. schemes under the Next Steps Accommodation Programme (NSAP). The annual Compliance Audit programme provides assurance that the Council has met all of HE’s requirements and funding conditions; and has properly exercised its responsibilities as set out in HE’s Capital Funding Guide (CFG). The Council is required to appoint an independent auditor to undertake a Compliance Audit, the standardised terms of which are set out by HE, of one or more schemes.
2.2HE advised the Council on 24 June 2021 that the Compliance Audit system had opened and the longstop date for auditors submitting reports is 15 September 2021. The Council has been advised that one scheme is to be subject to Compliance Audit. The address of this scheme is not provided to the Council until up to four weeks before the agreed date of the Compliance Audit.
2.3Given Mazars is the external auditor for the Council, which is a Public Interest Entity, the Financial Reporting Council (FRC) now requires the Council’s Audit Committee to approve Mazars undertaking any non-external audit work.
3. Strategic Priorities
3.1Let’s deliver quality housing Currently, the Council is under contract with HE to receive approximately £4m of capital grant funding for De Wint Court and NSAP. Without this funding the Council would not have been able to deliver these schemes.
4. Organisational Impacts
4.1Finance
As stated above, the annual Compliance Audit programme provides assurance that the Council has met all of HE’s requirements and funding conditions and has properly exercised its responsibilities as set out in HE’s CFG. Mazars is unable to provide a quote for the cost of the Compliance Audit until the Audit Committee gives approval for Mazars to be appointed. Last year’s Compliance Audit (which was undertaken by Mazars) cost £3,500 excluding VAT. This year’s fees will be paid from the Housing Strategy and Investment budget using the fees received for management of the NSAP and Purchase and Repair schemes.
4.2Legal Implications including Procurement Rules
The Council’s contract (known as a grant agreement) with HE requires grant funded schemes to be subject to annual Compliance Audit.
4.3Equality, Diversity and Human Rights
The Public Sector Equality Duty means that the Council must consider all individuals when carrying out their day-to-day work, in shaping policy, delivering services and in relation to their own employees.
It requires that public bodies have due regard to the need to: Eliminate discrimination Advance equality of opportunity Foster good relations between different people when carrying out their activities
5.1(i) Options Explored: (a) To appoint Mazars as the independent auditor to undertake the Compliance Audit; and (b) To appoint an alternative independent auditor to undertake the Compliance Audit.
5.2(ii) Key risks associated with the preferred approach: The preferred approach is to appoint Mazars, on the basis that they are the Council’s external auditor. The key risk is Mazars’ availability to undertake the audit.
6.1The Audit Committee to agree for the Council to appoint Mazars to undertake the HE Compliance Audit.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Homes England Compliance AuditReport | 135 KB | DownloadRead as text |
Follow Audit Committee at Lincoln and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Jul 2026 | Confirmation of Minutes - 1 June 2026RESOLVED that the minutes of the meeting held on 1 June 2026 be confirmed and signed by the Chair as a correct record. | Decided | Open |
| 13 Jul 2026 | Annual Complaints Performance and Service Improvement Report 2025-2026RESOLVED that the Annual Complaints Performance and Service Improvement Report 2025-2026 and comments made be noted. | Noted | Open |
| 13 Jul 2026 | Internal Audit Recommendations Follow UpRESOLVED that the Internal Audit Agreed Action Progress Report be noted. | Agreed | Open |
| 13 Jul 2026 | Draft Statement of Accounts 2025/26RESOLVED that the draft Statement of Accounts be scrutinised and comments made be noted. | Noted | Open |
| 13 Jul 2026 | External Audit: Audit Plan and Strategy 2025/26RESOLVED that the content of the Audit Plan and Strategy be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.