Resolved
RESOLVED that 1. the contents of the report be noted. 2. a further update be reported to Housing Scrutiny Sub Committee in March 2022 when the pilot process had been completed.
Housing Scrutiny Sub-Committee noted this item on Monday 24 January 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that 1. the contents of the report be noted. 2. a further update be reported to Housing Scrutiny Sub Committee in March 2022 when the pilot process had been completed.
1.1This report provides an update on the Scheduled Repairs project delivered during the extended trial period.
2.1The extended Scheduled Repairs trial period began on 9th August 2021 and completes on 4th February 2022.
2.2It is considered that there are numerous advantages and benefits for tenants and for the Council in delivering a Scheduled Repairs service, compared to the previous service delivery. These advantages relate to tenant satisfaction, operational efficiency, operational performance, financial savings, and the environment.
2.3A full analysis of the Scheduled Repairs trial extension will be available in March 2022 following the completion of the trial period on 4 th February 2022. This report is an interim update on the extended trial from 9th August 2021 until 4th January 2022.
3.1Prior to August 2020 Housing Repairs Service operated a Responsive Repairs service whereby all non-urgent repairs were completed within 20 days and emergency repairs within 24 hours. Operatives were assigned to attend repairs anywhere within the city boundary. Repairs were not organised by location and following the completion of a repair operatives were deployed to undertake the next repair job without reference to the geographical proximity of the next repair to be undertaken.
3.2Scheduled Repairs were introduced on 17th August 2020 on a trial basis for 24 weeks to explore whether the new method of delivering repairs would assist in easing the backlog of repairs. Priority repairs continued to be completed within 24 hours and urgent repairs within 3 days. Scheduled repairs are currently being carried out at set times of the year, across four set areas in the city. Via the Scheduled Repairs model repairs for each of the four areas are scheduled every 12 weeks over a 3-week period.
3.3The Four Areas of the City are
North (Ermine East, West and Newport) East (St Giles and Monks Road) Central (Boultham Moor, Bracebridge, Manse and City Centre) South (Birchwood and Hartsholme).
3.4In principle, carrying out scheduled repairs in one geographic area for a concentrated period means that overall a greater number of repairs can be undertaken with the same amount of labour resource. The reasons for this are:
Customers can block book appointments that are most suitable for them.
Unproductive travelling time between different areas of the city is minimised as once a repair or batch of repairs in a property have been completed the operatives next repair appointment will be in the same geographic area of the city.
Material usage can be planned to ensure that the correct materials are delivered or obtained in time for the appointment. This reduces operative standing time as the materials required for a repair will be available on the operative’s vehicle or pre delivered to site to enable the repair or batch of repairs to be completed without delay. This also reduces operative visits to Hamilton House, the JPS Managed Stores, and local merchants.
4. Update on the Scheduled Repairs Trial Period Extension
4.1Since the trial began on 17th August 2020 it is evident that potentially, there are potential advantages and benefits to delivering Scheduled Repairs when compared to service delivery via the previous system. This included:
Tenant satisfaction Operational efficiency and performance Financial savings Environmental impact Housing stock standard
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Update on the Schedule Repairs Trial ExtensionReport | 190 KB | DownloadRead as text |
Follow Housing Scrutiny Sub-Committee at Lincoln and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Aug 2026 | Confirmation of Minutes - 4 June 2026RESOLVED that the minutes of the meeting held on 4 June 2026 be confirmed and signed by the Chair as a true record. | Decided | Open |
| 17 Aug 2026 | Lincoln Tenants Panel (LTP) UpdateRESOLVED that: 1. Details of tenant’s contents insurance options from both Marsh and Thistle companies be forwarded t... | Noted | Open |
| 17 Aug 2026 | Financial Performance Quarterly MonitoringRESOLVED that this item be deferred to the next meeting of Housing Scrutiny Sub-Committee to be held on Wednesday 23 ... | Deferred | Open |
| 17 Aug 2026 | Estate Regeneration ProgrammeDecision made – happy with this approach • Projects/Initiatives : • Support to national initiatives • Exploration of ... | Decided | Open |
| 17 Aug 2026 | Tenancy Agreement ProgressRESOLVED that an additional agenda item entitled ‘Summary/Digest Document of Tenancy Agreement Policy’ be added to th... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.