Resolved
RESOLVED that Mazars be engaged to undertake the additional non-audit work as detailed at paragraph 1 of the report.
Audit Committee decided this item on Tuesday 15 November 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that Mazars be engaged to undertake the additional non-audit work as detailed at paragraph 1 of the report.
1.1This report requests the Audit Committee to approve the proposed engagement of the Council’s external auditor, Mazars, to undertake the:
Housing Benefits – Reporting Accountants report on the 2021/22 return and; Pooling of Housing Capital Receipts – Reporting Accountant report on the 2021/22 return.
2.1For 2018/19, for a period of 5 years, Mazars have been appointed to undertake the external audit of the Councils financial statements under a formal tender process, administered by Public Sector Audit Appointments (PSAA), under the Local Audit and Accountability Act 2014.
2.2This arrangement does not cover the provision of an Independent Reporting Accountant, required for the certification work on the Housing Benefit subsidy which is undertaken on behalf of the Department for Work and Pensions (DWP). Neither does the arrangement cover the provision of an Independent Reporting Accountant, required for the certification work on the Pooling of Housing Capital Receipts Scheme, which is undertaken on behalf of the Department for Levelling Up, Homes and Communities (DLUHC). These appointments need to be made separately.
2.3The requirement to obtain an independent report on these returns is set by the relevant Government department (DWP and DLUHC) and the work is carried out in line with the instructions and work programmes issued by the departments. The reporting deadline for this work is end of January 2023.
2.4The Council has, since 2018/19, appointed Mazars to perform the certification work required for these two returns. The appointment for the Housing Benefits return was undertaken through a direct approach to Mazars through the Crown Commercial Service: Management Consultancy Framework and was awarded for a period of 5-years. The appointment for the Housing Capital Receipts Scheme is awarded on an annual basis through a direct approach to Mazars.
3. Engagement for 2021/22
3.1It is proposed that for 2021/22 the Council engages Mazars to perform the certification for required for the two returns. Historically this has not required the approval of the Audit Committee, however Mazars have requested that the engagements for 2021/22 are formally approved by the Audit Committee, as per the attached letter.
3.2External Audit will be in attendance at the meeting to answer any questions the Audit Committee has regarding these returns.
4. Strategic Priorities
4.1There are no direct implications for the Council’s strategic priorities. The external certification and independent report of these returns is a requirement of relevant Government Department and as such contributes towards the fitness for purpose of the Council’s governance arrangements.
5. Organisational Impacts
5.1Finance (including whole life costs where applicable)
The estimated fees for these two engagements are £6,000 for the Housing Benefits report and £3,250 for the Pooling of Housing Capital Receipts. Budget provision for these costs is already provided for with the Council’s Medium Term Financial Strategy.
5.2Legal Implications including Procurement Rules
There are no direct legal implications. The procurement of Mazars for these non- audit works has been undertaken in accordance with the Council’s Contract Procedure Rules.
5.3Equality, Diversity and Human Rights
The Public Sector Equality Duty means that the Council must consider all individuals when carrying out their day-to-day work, in shaping policy, delivering services and in relation to their own employees.
It requires that public bodies have due regard to the need to:
Eliminate discrimination Advance equality of opportunity Foster good relations between different people when carrying out their activities
There are no specific equality, diversity and human rights issues arising as result of this report.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CoL AC non audit services approval request 2021_22Appendix A | 113 KB | Download |
PDF |
Audit Committee: External Audit Non Audit Work 15.11.22Report | 143 KB | DownloadRead as text |
Follow Audit Committee at Lincoln and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Jul 2026 | Confirmation of Minutes - 1 June 2026RESOLVED that the minutes of the meeting held on 1 June 2026 be confirmed and signed by the Chair as a correct record. | Decided | Open |
| 13 Jul 2026 | Annual Complaints Performance and Service Improvement Report 2025-2026RESOLVED that the Annual Complaints Performance and Service Improvement Report 2025-2026 and comments made be noted. | Noted | Open |
| 13 Jul 2026 | Internal Audit Recommendations Follow UpRESOLVED that the Internal Audit Agreed Action Progress Report be noted. | Agreed | Open |
| 13 Jul 2026 | Draft Statement of Accounts 2025/26RESOLVED that the draft Statement of Accounts be scrutinised and comments made be noted. | Noted | Open |
| 13 Jul 2026 | External Audit: Audit Plan and Strategy 2025/26RESOLVED that the content of the Audit Plan and Strategy be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.