Decision That the Council’s strategic risks, as at the end of quarter 2 2022/23, be noted. None were considered. The Strategic Risk Register contained the key strategic risks to the delivery of the Council’s medium and longer term priorities. A failure to monitor the action that was being taken to manage those risks would undermine the Council’s governance arrangements. Since reporting to Members in August, the Strategic Risk Register had been refreshed and updated by the Risk Owners, and Corporate Management Team and had identified that there have been some positive movement in the Risk Register. It contained twelve strategic risks as detailed within paragraph 3 of the officer’s report, along with details of relevant mitigations. The updated register was contained with Part B of this agenda, (Minute 56 referred), as it was considered to contain exempt information.
Word for word from the decision Lincoln published for this meeting.Source: democratic.lincoln.gov.uk
1.1To provide Members with a status report of the revised Strategic Risk Register as at the end of the second quarter 2022/23.
Background
2.1An update of the Strategic Risk Register, developed under the risk management approach of ‘risk appetite,’ was last presented Members in August 2022 and contained twelve strategic risks.
2.2Since reporting to Members in August, the Strategic Risk Register has been refreshed and updated by the Risk Owners and Corporate Management Team and has identified that there have been some positive movement in the Risk Register.
2.3This updated register is contained with Part B of this agenda, it contains twelve strategic risks which are listed below, along with details of relevant mitigations.
3. Strategic Risks
3.1The Strategic Risk Register contains twelve existing risks, as follows:
1) Failure to engage & influence effectively the Council’s strategic partners, council staff and all stakeholders to deliver against e.g., Council’s Vision 2025.
2) Failure to deliver a sustainable Medium-Term Financial Strategy (that supports delivery of Vision 2025).
3) Failure to deliver the Towards Financial Sustainability Programme whilst ensuring the resilience of the Council.
4) Failure to ensure compliance with statutory duties/functions and appropriate governance arrangements are in place.
5) Failure to protect the local authority's vision 2025 due to changing structures and relationships in local government and impact on size, scale and scope of the Council. 6) Unable to meet the emerging changes required in the Council’s culture, behaviour and skills to support the delivery of the council’s Vision 2020/2025 and the transformational journey to one Council approach.
7) Insufficient levels of resilience and capacity exist in order to deliver key strategic projects & services within the Council.
8) Decline in the economic prosperity within the City Centre.
9) Failure to deliver key strategic projects.
10) Failure of the Council’s key contractors and partners to remain sustainable and continue to deliver value for money
11) Failure to protect the vulnerable in relation to the Council’s PREVENT and safeguarding duties.
12) Failure to mitigate against the risk of a successful cyber-attack against the council
3.2A number of control actions have now been progressed or completed and the key movements are outlined as follows:
Risk No 2. Failure to deliver a sustainable Medium Term Financial Strategy – due to the unavoidable and unforeseen changes in the majority of the key assumptions underpinning the current MTFS, an assessment of the likely financial challenges the Council faces in the short and medium-term has been undertaken, this has identified significant financial pressures for the Council. All political parties have been briefed on the position. Work has now commenced on a financial recovery programme, alongside this the Council has commenced a lobbying campaign to seek additional financial support for local authorities from Central Government.
Risk No 3. Failure to deliver the Towards Financial Sustainability Programme (TFS) – in light of the financial pressures the Council is facing, as part of the financial recovery programme, a new phase of TFS is currently being scoped. In addition, the existing programme of reviews are continuing to be delivered.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Confirmation of Minutes - 18 August 2026RESOLVED that the minutes of the meeting held on 18 August 2026 be confirmed and signed by the Chair as a correct rec...
Updated Rechargeable Repairs PolicyDecision 1. That the policy be implemented and briefing sessions to all staff within customer services and housing on...
Exclusion of the Press and PublicRESOLVED that the press and public be excluded from the meeting during consideration of the following item of busines...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.