CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
City of Lincoln Council
Audit Committee, Tuesday 21 March 2023 at 5.00pm

Internal Audit Recommendations Follow Up

Noted Finance 2 papers

Audit Committee noted this item on Tuesday 21 March 2023. Below is the council's own wording, with the papers it was decided on.

Item62

Resolved

RESOLVED that updates on Audit Recommendations report be noted.
Word for word from the decision Lincoln published for this meeting. Source: democratic.lincoln.gov.uk

Follow this further

Built from Lincoln's papers

What the report saysPro

Report to Audit Committee

Audit Recommendations March 2023

For all your assurance needs Summary of Agreed Actions We have carried out a review of the actions due by the end of February 2023 and the following graphs summarise the current position of the implementation of all agreed actions in response to the recommendations made:-

Total number of Actions to be implemented by age and priority 4

2 High Medium 1

0 2+ years 1-2 years 0-1 year

High Priority Actions by age and status Medium Priority Actions by age and 4 status 4

3 3

2 2

1 1

0 0 2+ years 1-2 years 0-1 year 2+ years 1-2 years 0-1 year

Not Due Overdue Extended and not due Not Due Overdue Extended and not due

Page | 2 High Priority Actions outstanding The following table provides the detailed information for the high priority actions which have not yet been implemented and are overdue:-

Original Current Latest Progress / Audit Recommendation Agreed Action Due Date Due Date Owner Comments There are none.

Page | 3 Changes since the previous report

A report on the outstanding recommendations was presented to Committee in December 2022. There have been a number of changes in the implementation of actions outstanding at that time and these are detailed below.

All recommendations have now been implemented for the following reports:-

Audit Area Date Assurance Progress

Creditors Jun 21 High Action implemented. Review and approve authorising officers on Agresso. Information is being collated in a format for the appropriate Assistant Directors to approve/confirm and this will be distributed at the latest by the end of next week. Extension approved to Nov 22. Licensing Feb 20 Substantial Action implemented Review performance measures. Extension required to allow time to procure the new system. Extended to Jan 23 from Jun 22– approved.

Progress made on implementing actions for the remaining reports are as follows in date order:-

Audit Date Assurance No of Recs Implmntd Outstanding Not Yet Comments / Progress since Due previous report H M Overdue Extended ICT Anti- Mar 20 Substantial 1 8 8 0 1 0 High action closed. Malware Review and update the Incident management policy / procedure. Policy has been drafted and working with IT Auditor to review any extra requirements. Housing Aug 20 Substantial 0 4 3 0 1 0 No change Allocations Annual review of applications. Testing phase of upgrade revealed some issues so not yet able to implement into the live system.

Page | 4 Audit Date Assurance No of Recs Implmntd Outstanding Not Yet Comments / Progress since Due previous report H M Overdue Extended Homelessness Aug 20 Substantial 0 2 1 0 1 0 No change. Ensure compliance with document retention & disposal requirements. The new Enterprise system is in place, however the retention timescales have not been set yet. Extended to March 2023, this is the last extension to be granted. Office 365 May 21 Substantial 0 6 5 0 1 0 No change. Enable, set-up and use DLP policies for Exchange Online and SharePoint Online content. Consultancy has now been completed to set out a framework for change. This will be developed into a plan for migration of data etc. A significant amount of resource will be required for completion. Extended to Jun 2024 – approved. Visitor Jan 22 Substantial 1 6 5 0 2 0 No change Information Obtain agreement of whether Centre discount scheme to continue Being progressed as part of a wider review. Extension to Apr 23 approved. Develop a Business Plan Extension requested until April 23 from July 22 due to staff recruitment and busy summer season. Approved. Safeguarding Jan 22 Substantial 0 5 4 0 1 0 No change. Use the E-CINS IT system to record and track referrals. System and guidance in place and testing has been completed. New Safeguarding Lead will implement

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Audit Recommendations Report Mar 2023 v2Report 724 KB DownloadRead as text
PDF
Internal Audit Recommendations Follow UpReport 33 KB Download

At this meeting

Whole meeting

Who was there

7 of 10 attended
RL
Councillor Rebecca LongbottomChair, present
JK
Councillor Jackie KirkVice-Chair, present
DC
Councillor David ClarksonCommittee Member, present
TD
Councillor Thomas DyerCommittee Member, apologies
GH
Councillor Gary HewsonCommittee Member, present
CW
Councillor Calum WattCommittee Member, present
EW
Councillor Emily WoodCommittee Member, present
JN
Jane NellistCo-Optee, present
JM
Jon MachejPublic, expected
MS
Mark SurridgePublic, expected

On this subject at Lincoln

Search all
  1. Internal Audit Recommendations Follow UpThis decision
  2. Internal Audit Recommendations Follow UpAgreed
  3. Internal Audit Annual Audit ReportNoted
  4. Internal Audit Annual Fraud ReportNoted
  5. Review of the Effectiveness of Internal AuditNoted
  6. Internal Audit External Quality AssessmentApproved

More from Lincoln Audit Committee

All decisions
MeetingDecisionOutcome
13 Jul 2026 Confirmation of Minutes - 1 June 2026RESOLVED that the minutes of the meeting held on 1 June 2026 be confirmed and signed by the Chair as a correct record. Decided Open
13 Jul 2026 Annual Complaints Performance and Service Improvement Report 2025-2026RESOLVED that the Annual Complaints Performance and Service Improvement Report 2025-2026 and comments made be noted. Noted Open
13 Jul 2026 Internal Audit Recommendations Follow UpRESOLVED that the Internal Audit Agreed Action Progress Report be noted. Agreed Open
13 Jul 2026 Draft Statement of Accounts 2025/26RESOLVED that the draft Statement of Accounts be scrutinised and comments made be noted. Noted Open
13 Jul 2026 External Audit: Audit Plan and Strategy 2025/26RESOLVED that the content of the Audit Plan and Strategy be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies