Resolved
RESOLVED that the minutes of the meeting held on 19 February 2024 be confirmed and signed by the Chair as a true record.
Executive decided this item on Monday 18 March 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the minutes of the meeting held on 19 February 2024 be confirmed and signed by the Chair as a true record.
1. To provide an update on the progress with the delivery of the Skellingthorpe Road (southern access) works and proposed housing development.
2. To provide an update on proposals for the design and delivery of the main bridge and road link, which would form the eastern access point into the Western Growth Corridor site.
3. To seek approval to move forward with enabling works, relating to vegetation clearance and the diversion of statutory services, in order to maintain the programme for delivery of the eastern access work, in line with funding timescales.
Decision
1. That the progress being made in respect of the first phases of delivery to open up the Western Growth Corridor site, which was of strategic importance to the future growth of the city, be acknowledged.
2. That the proposed enabling works associated with the eastern access be approved, in order to maintain the programme for delivery to meet the required funding timescales.
Alternative Options Considered and Rejected
None.
The delivery arrangements proposed within the officer’s report would open up the Western Growth Corridor (WGC) development via its eastern access, creating opportunities for housing growth and contributing directly and indirectly to the economic growth of the city.
The creation of this access would then further provide the opportunity to deliver a connecting spine road (to link with the Skellingthorpe Road – Southern Access), thereby opening up the full potential of the site and resulting opportunities to support sustainable economic growth.
The development would bring a number of positive benefits in respect of reducing inequality and supporting inclusive growth through the provision of affordable housing, sustainable transport links and wider energy efficiency measures, employment opportunities and access to leisure and green spaces.
Delivery of the Eastern Access would directly open up the land within the ownership of the City Council and forming part of the Western Growth Corridor site. This would provide the opportunity for the delivery of a range of housing across all types and tenures to serve the needs of the City. The Council would be ensuring that a high quality of development was achieved, in line with its objectives and wider vision statement to create sustainable, inclusive communities.
The area for development had a fantastic environment and some very special attributes in terms of existing quality landscape, views of the historic area and the biodiversity of the natural environment, which would be utilised to create a quality community environment. The detailed development proposals for both the infrastructure and subsequent housing development, would be required to take account of these assets and to seek to preserve key landscape features and enhance biodiversity across the site.
The vision for the Western Growth Corridor was to deliver a high quality, sustainable development which sought to address the challenge of climate change in terms of the overall scheme design and its constituent parts – housing layout and built form, energy, biodiversity, transport and construction methodology.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Confirmation of Minutes: 19 February 2024Minutes | 472 KB | DownloadRead as text |
Follow Executive at Lincoln and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Sep 2026 | Confirmation of Minutes - 18 August 2026RESOLVED that the minutes of the meeting held on 18 August 2026 be confirmed and signed by the Chair as a correct rec... | Decided | Open |
| 15 Sep 2026 | Variation to the Constitution – Responsibility for Functions; Adoption of National Scheme of Delegation and Amendments to Planning ProtocolsDecision 1. That a variation to Part 3 – Responsibility for Functions of the Council’s Constitution to reflect the ch... | Approved | Open |
| 15 Sep 2026 | Updated Rechargeable Repairs PolicyDecision 1. That the policy be implemented and briefing sessions to all staff within customer services and housing on... | Approved | Open |
| 15 Sep 2026 | Playground FundingDecision That the progression of this new project and inclusion of a capital estimate of £511,335 in the General Inve... | Approved | Open |
| 15 Sep 2026 | Exclusion of the Press and PublicRESOLVED that the press and public be excluded from the meeting during consideration of the following item of busines... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.