Quarter 2 2025/26 Operational Performance Report

Noted Executive 3 papers

AI summaryCity of Lincoln Executive noted the Quarter 2 2025/26 performance report covering 88 measures, with 70.3% of targeted measures within or exceeding targets, and confirmed the report format continues to meet requirements.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedQ2 2025/26 performance noted; format confirmed to meet requirements
MoneyNot stated
What happens nextNot stated
Who it affectsCouncil performance monitoringPerformance across four directorates, six themes

What was decided

The Executive noted the achievements and challenges in the Quarter 2 2025/26 operational performance report at Appendices A and B. Report 10.1

The Executive confirmed the report format continues to meet its requirements. Report 10.2

Two typographical errors were corrected: the Ermine Exchange officially opened on Ermine East, Lincoln, and measure HI 1 on page 12 of Appendix B was corrected to read 'X21 HHSRS Radon'.

Why

Regular monitoring of the Council's performance is a key component of the Local Performance Management Framework, and the report covers strategic performance measures identified by members and the Corporate Management Team. Report 3.1

Out of 88 quarterly measures reported, 64 had targets, and 45 of those targeted measures (70.3%) were within or exceeding the targets set. Report 2.1, P4

Detailed outturns grouped by directorate, with a colour coding system, make it easier to assess and scrutinise performance of each priority and portfolio. Report 3.5

What happens next

Targets for the street cleansing contract are expected to be reviewed ahead of the new contract date in September 2026. Report P27

The Housing and Investment service area expects the void and re-let time figures to remain similar in Q3 while properties requiring damp and mould repairs continue to be processed. Report P22, P25

The Benefits service area will continue working to clear the higher volume of assessment work received in the previous two quarters. Report P17

Options considered

  • Rejected: No alternative options were considered. None were considered

Implications

  • Financial: There are no direct financial implications because of this report; further financial detail sits in the quarterly financial performance report. Report P43
  • Legal: There are no direct legal implications as a result of this report. Report P44
  • Equalities: The report has no direct equality and diversity implications, though the Public Sector Equality Duty is noted. Report P46, P48, P49
  • Risk: Key risks and options are recorded as N/A for this monitoring report. Report P51, P53
  • Staffing: Staff turnover was 3.1% (20 leavers excluding apprentices) in Q2, down from 3.8% in Q1; vacancies stood at 62.56 FTE; sickness was 2.16 days lost per FTE; 72.20% of appraisals were recorded as complete between October 2024 and 30 September 2025. Report 6.2, P31, P33, P34, 6.4
  • Other: The Council dealt with 160 complaints in Q2, with 90% responded to within service standard and 30 compliments recorded; 0 LGO complaints decided and 1 LHO complaint decided with no maladministration. Report 6.6

Who and where

  • Housing tenants, where 120 voids were in the system at the end of Q2 and longer re-let times were driven by damp and mould repair works and decant moves Report P19, P20, P21, P23, P24
  • Housing Benefits and Council Tax support customers, with 2,256 customers awaiting assessment (1,851 awaiting first contact) Report P17
  • Street cleansing service users in Lincoln, following increased contractor performance points in Q2 Report P27
  • Council staff covered by appraisals, sickness, vacancy and turnover reporting Report 6.2, 6.4, P31, P33, P34
  • Lincoln residents and visitors engaging with council communications, events, the Citizens Panel and venues including the Guildhall and Ermine Exchange Report P13, 6.7

Timeline

  • Q2 2025/26: 88 quarterly performance measures reported across the four directorates, with 14 Red, 15 Blue, 30 Green, 24 volumetric and 5 data not available Report 2.1, P3
  • Q2 2025/26: 20 leavers (3.1% turnover), 62.56 FTE vacancies and 2.16 days sickness per FTE recorded Report 6.2, P31, 6.4
  • Q1 2025/26: Previous sickness was 1.67 days per FTE and turnover was 3.8% Report 6.2, 6.4
  • Q2 2024/25: Sickness figure for comparison was 2.69 days per FTE Report 6.4
  • October 2024 to 30 September 2025: 465 appraisals recorded as complete, a 72.20% completion rate Report P34
  • September 2026: Standards of the new street cleansing contract take effect; current targets expected to be reviewed Report P27

Plain English for the jargon

  • CMT: Corporate Management Team, the council's senior officer group
  • FTE: Full-time equivalent, a measure of staff hours
  • Red, Blue, Green status: Performance colour coding: Red is below lower target, Blue is within target boundary, Green meets or exceeds the higher aspirational target
  • Volumetric measure: A performance measure recorded as a count rather than judged against a target
  • Voids: Empty housing properties in the council's stock
  • LGO and LHO: Local Government Ombudsman and Local Housing Ombudsman, who handle complaints about councils and social landlords
  • Vision 2030: City of Lincoln Council's long-term strategic priorities
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item50

Resolved

Decision 1. That the achievements and challenges identified in the Quarter 2 2025/26 operational performance report found at Appendices A and B of the officer’s report be noted. 2. It be confirmed that the format of the performance report continued to meet requirements. Alternative Options Considered and Rejected None were considered. Reasons for the Decision Regular monitoring of the Council’s performance was a key component of the Local Performance Management Framework. This report covered the key strategic performance measures identified by members and Corporate Management Team (CMT) as of strategic importance. The outturn summary at the end of quarter 2 2025/26 detailed performance against a total of 88 quarterly performance measures, reported during the quarter across the Directorates of Chief Executive’s, Communities & Environment, Housing & Investment and Major Developments: Out of the 88 performance measures monitored during the quarter 64 had targets allocated to them. Of these targeted measures 45 (70.3%) were within or exceeding the targets set. Of the 88 performance measures monitored against targets, 14 were below target; 15 were within target boundaries; 30 had met or exceeded a higher target; 24 measures were recorded as volumetric, and 5 measures were recorded as data not available for this quarter. Appendix A contained a wide range of performance information, including qualitative data in the form of case studies and service highlights. These were grouped into six themes, namely the four Vision Priorities and the two inward looking portfolios ‘Climate and Corporate Strategy’ and ‘Customer Experience, Review and Resources.’ The more detailed performance data tables were grouped together in Appendix B, including the suite of corporate measures. Performance data was grouped by directorate; a colour coding system had been introduced to make it simpler to identify which portfolio each measure related to. Appendix B also included a quarterly Communications update. When read together, Appendices A and B aimed to enhance the range of performance information presented via the quarterly reporting process and made it easier to assess and scrutinise the performance of each priority/portfolio. Key highlights of some of the positive work of the Council and its impact during the quarter were summarised at paragraph 4, a brief summary of areas which required monitoring were detailed within paragraph 5, and corporate measures reported at paragraph 6 of the officer’s report. *A typographical error within page 9 Appendix A of the report was corrected to denote that the Ermine Exchange had officially opened on Ermine East, Lincoln and a typographical error at page 12 of Appendix B measure HI 1 corrected to read ‘X21 HHSRS Radon’.
Word for word from the decision Lincoln published for this meeting. Source: democratic.lincoln.gov.uk

Follow this further

Built from Lincoln's papers

What the report saysPro

Report to Executive

Purpose of report

1.1To present to Executive an outturn summary of the Council’s performance in quarter 2 of 2025/26.

Executive summary

2.1At the end of quarter 2 2025/26 of the 88 quarterly performance measures reported during the quarter across the Directorates of Chief Executive’s, Communities & Environment, Housing & Investment and Major Developments:

- 14 measures (15.9%) were Red (below lower target boundary) - 15 measures (17.0%) were Blue (within target boundaries – acceptable) - 30 measures (34.1%) were Green (meeting or exceeding the higher target) - 24 measures (27.9%) were recorded as volumetric - 5 measures (5.7%) were recorded as data not being available for this quarter

Out of the 88 performance measures monitored during the quarter 64 had targets allocated to them. Of these targeted measures 45 (70.3%) were within or exceeding the targets set.

Background

3.1Regular monitoring of the Council’s performance is a key component of the Local Performance Management Framework. This report covers the key strategic performance measures identified by members and Corporate Management Team (CMT) as of strategic importance.

3.2Each targeted measure is monitored against a target boundary range.

If a performance measure outturn status is Blue (acceptable), the measure is seen as performing on track. If a performance measure outturn status is green, the measure is seen to be achieving or exceeding the aspirational target. If a performance measure outturn status is red, the measure is seen to be performing below target and should be an area of focus.

3.3Appendix A contains a wide range of performance information, including qualitative data in the form of case studies and service highlights. These are grouped into six themes, namely the four Vision Priorities and the two inward looking portfolios ‘Climate and Corporate Strategy’ and ‘Customer Experience, Review and Resources.’ 3.4 The more detailed performance data tables are grouped together in Appendix B, including the suite of corporate measures. Performance data is presented by directorate, and a colour coding system is used to make it simple to identify which portfolio each measure relates to.

3.5When read together, Appendices A and B aim to enhance the range of performance information presented via the quarterly reporting process and make it easier to assess and scrutinise the performance of each priority.

4. Performance Measure Outturns – Quarter 2 2025/26

4.1As set out in section 3, Appendix A provides an overview of the Council’s performance by Directorate and Vision 2030 theme. Highlight reports detailing some of the positive work of the Council during the quarter, and the impact of this, are also included in Appendix A.

Highlights from across the Council include:

• Reducing Inequality Vision Priority – the opening of the Ermine Exchange wellbeing hub and coffee house. • Customer Experience, Review and Resources – refresh of the Lincoln Citizens Panel questions format and feedback mechanism to participants. • Remarkable Place Vision Priority – exciting and varied schedule of events across the City during this quarter. • Quality Housing Vision Priority – the popular Trade Day at Hamilton House hosted in partnership between the Housing Repairs Service and Jewson Partnership Solutions. • Inclusive Economic Growth Vision Priority – Lincon’s Guildhall successes with TripAdvisor ‘Visitor Choice Award’ and Visit England ‘Quality Mark.’

5. Areas to Monitor

5.1To support Appendix A, a full list of all performance measure outturns and supporting service area commentary are provided at Appendix B.

5.2Those areas to note within Chief Executive’s Directorate are:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Performance Overview Q2 25-26Appendix A 6.7 MB Download
PDF
Performance Tables Q2 25-26Appendix B 1.2 MB Download
PDF
Quarter 2 2025/26 Operational Performance ReportReport 192 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 6 attended
NT
Councillor Naomi TweddleChair, present
DN
Councillor Donald NannestadVice-Chair, present
RL
Councillor Rebecca LongbottomCommittee Member, present
LP
Councillor Lucinda PrestonCommittee Member, present
CR
Councillor Callum RoperCommittee Member, present
JW
Councillor Joshua WellsCommittee Member, present

On this subject at Lincoln

Search all
  1. Quarter 2 2025/26 Operational Performance ReportThis decision
  2. Quarter 1 2026/27 Operational Performance ReportNoted
  3. Quarter 4 2025/26 Operational Performance ReportApproved
  4. Quarter 3 2025/26 Operational Performance ReportApproved
  5. Quarter 3 Operational Performance ReportAgreed
  6. Quarter 2 2025/26 Operational Performance ReportNoted

More from Lincoln Executive

All decisions
MeetingDecisionOutcome
15 Sep 2026 Confirmation of Minutes - 18 August 2026RESOLVED that the minutes of the meeting held on 18 August 2026 be confirmed and signed by the Chair as a correct rec... Decided Open
15 Sep 2026 Variation to the Constitution – Responsibility for Functions; Adoption of National Scheme of Delegation and Amendments to Planning ProtocolsDecision 1. That a variation to Part 3 – Responsibility for Functions of the Council’s Constitution to reflect the ch... Approved Open
15 Sep 2026 Updated Rechargeable Repairs PolicyDecision 1. That the policy be implemented and briefing sessions to all staff within customer services and housing on... Approved Open
15 Sep 2026 Playground FundingDecision That the progression of this new project and inclusion of a capital estimate of £511,335 in the General Inve... Approved Open