Community Infrastructure Levy (CIL)

Approved Executive 1 paper

AI summaryCity of Lincoln Executive approves spending local Community Infrastructure Levy funds on the Carholme Neighbourhood Plan and a city centre greening scheme.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedTwo projects: Carholme Neighbourhood Plan and City Centre Greening
Money£49,268.83 in Local CIL receipts to date£4,875 to Carholme NP, £44,000 to City Centre Greening
What happens nextFurther Executive approval for greening schemeSubject to feasibility, design and final cost estimates
Who it affectsLincoln city residents and visitorsCarholme area and city centre near Central Bus station

What was decided

The Executive approved the proposal to spend Local CIL monies as outlined in the officer's report, funding two identified projects. Report 8.1

The Carholme Neighbourhood Plan group is to receive £4,875 to pay a planning professional for support preparing the plan. Report 4.5, 4.6

The City Centre Greening scheme at the Central Bus Station is to receive £44,000 from the remaining Local CIL funds, as part of a wider funding package. Report 4.7, 4.8

Why

Under CIL Regulation 59F, with no parish or town councils in the city, the City Council decides how to spend the 15% local share of CIL receipts to address the demands development places on the area. Report 3.4, 3.5

Officers reviewed the four options from the 2019 Policy Scrutiny report and concluded that funding defined projects would have the most meaningful impact, since spreading funds across all 11 wards would be too thinly spread. Report 3.7, 3.8, 4.3, P20

Both projects help mitigate the impact of development and can be delivered before any local government reorganisation spend restrictions take effect. Report 4.3, 4.4

What happens next

Further Executive approval will be sought for the City Centre Greening scheme once feasibility, design and costing work is complete, in line with Financial Procedure Rules. Report P38

Local CIL monies that continue to accumulate may be awarded to other neighbourhood plan groups as proposals come forward in other parts of the city.

The money

  • £49,268.83 Total Local CIL receipts received since 5 February 2018 Report 3.6, 4.1, P37
  • £4,875 Quote from a planning professional to support the Carholme Neighbourhood Plan Report 4.6
  • £44,000 Contribution of remaining Local CIL funds to the City Centre Greening scheme Report 4.8
  • £4,478 Amount per ward if Local CIL were spread evenly across all 11 wards Report P20
  • £4,744 Amount banked at the time of the June 2019 Policy Scrutiny Committee decision Report 3.8
  • £25 per square metre CIL rate for residential development in Zone 1 (the City) Report P7
  • £20 per square metre CIL rate for residential development in Zone 2 (Sustainable Urban Extensions) Report P7
  • £40 per square metre CIL rate for convenience retail (supermarkets) Report P9

Options considered

  • Chosen: Distribute funds to defined projects addressing development demands in identified areas of the city. Funds more likely to have a meaningful impact in the City than spreading thinly Report P20, 4.3
  • Rejected: Continue to bank Local CIL monies for a further 2 to 3 years. Risk under local government reorganisation that funds will not be spent supporting local infrastructure Report P20
  • Rejected: Distribute evenly across all 11 Council Wards. Limited funds spread thinly will be unlikely to generate meaningful impact Report P20
  • Rejected: Distribute via Neighbourhood Boards. No longer possible due to neighbourhood working restructure Report P20

Implications

  • Financial: The £44,000 contribution to the City Centre Greening scheme forms part of a wider funding package including a Vision 2030 allocation and earmarked reserves; further Executive approval will be needed once final costs are known. Report P38
  • Legal: The Council will continue to comply with the Planning Act 2008 and the CIL Regulations 2010 (as amended) in implementing, collecting, monitoring and distributing CIL. Report P40
  • Equalities: A full equality assessment has not been carried out, but the council considers that CIL promotes equal access to housing and employment and has no negative impact on those with protected characteristics. Report P45
  • Risk: Not all parts of the city would directly benefit, but spreading such a small amount across the whole city would also fail to deliver significant impacts. Report P49, 7.2
  • Other: There is a risk that, with local government reorganisation, accrued Local CIL monies could end up not being spent on local infrastructure if banked for too long. Report P20

Who and where

  • Residents of the Carholme area of Lincoln, through neighbourhood planning support Report 4.5, 4.6
  • Visitors, workers and city centre users near the Central Bus Station Report 4.7, 4.8
  • Other neighbourhood plan groups emerging elsewhere in the city, who may receive future CIL funding
  • Developers building eligible new development in the City of Lincoln, who pay the CIL charge Report 2.1, 3.1

Timeline

  • 5th February 2018: CIL came into force; the Council began charging on eligible development Report 3.1, 3.6
  • June 2019: Policy Scrutiny Committee considered options for distributing Local CIL monies Report 3.7, 3.8
  • June 2025: Central Government grant funding for neighbourhood planning was ceased Report 4.5
  • 2026-06-02: Executive approved spending of Local CIL monies on the two identified projects

Plain English for the jargon

  • Community Infrastructure Levy (CIL): A non-negotiable planning charge that local authorities in England and Wales can levy on eligible new development, used to fund infrastructure
  • Section 106 agreement: A planning obligation between a developer and a local authority, used alongside CIL for site-specific mitigation
  • Neighbourhood Plan: A plan prepared by a community group setting out local planning policies reflecting local priorities
  • Reg 59A and Reg 59F: CIL Regulations requiring 15% of CIL receipts to be passed to local councils, or where none exist, spent by the charging authority on local infrastructure
  • LGR (Local Government Reorganisation): Changes to local authority boundaries and structures, referred to as a risk that banked CIL funds may not be spent locally
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item3

Resolved

Decision That the proposal to spend Local CIL monies as outlined in the officer’s report be approved. Alternative Options Considered and Rejected Given the relatively small amount of money available, in reality this would be unable to deliver significant impacts if funds were spread across the whole of the city. Reasons for the Decision Local authorities in England and Wales could levy the , a planning charge on new development in their area. The City Council had been charging on eligible forms of development since 2018. Under CIL regulations (Reg 59A), 15% of CIL receipts (25% where there was a neighbourhood plan in place) were passed on to local councils to be spent in the local area to help mitigate the impact of development. In Lincoln where there were no Parish or Town Councils in place, it fell to the Council to decide how and where these monies were spent. Since CIL came into force on 5 th February 2018, to date, Local CIL receipts had totalled £49,268.83 which was eligible for spending in the City to support local infrastructure needs. Policy Scrutiny Committee received a report in June 2019 on options for the distribution of local CIL monies. It was agreed that once a significant amount had grown a report would be taken to Executive to recommend how the monies would be spent. In terms of the CIL distribution, a review of these options had been undertaken resulting in the outcomes detailed at paragraph 4.2 of the officer’s report. Two projects which required funding had been identified as detailed within the officer’s report, both of which would be in accordance with Local CIL regulations in that they both helped address the demands that development placed on areas in the City: • Carholme Neighbourhood Plan • City Centre Greening Scheme It was noted that there were two neighbourhood plan proposals currently in initial stages of development across the city; CIL monies accumulated in time could be awarded to other groups as they came forward in other parts of the city to undertake a neighbourhood plan
Word for word from the decision Lincoln published for this meeting. Source: democratic.lincoln.gov.uk

Follow this further

Built from Lincoln's papers

What the report saysPro

Report to Executive

Purpose of report

1.1To provide members with an update on the Community Infrastructure Level (CIL) since it was implemented on 5th February 2018 and recommend how the designated ‘Local’ CIL monies are spent in the City.

Executive summary

2.1Community Infrastructure Levy (CIL) is a planning charge that local authorities in England and Wales can levy on new development in their area. The City Council has been charging Community Infrastructure Levy (CIL) on eligible forms of development since 2018.

2.2Under CIL regulations, a proportion of the CIL monies collected can be spent in the local area to help mitigate the impact of development. In Lincoln where there are no Parish or Town Councils in place, it falls to the Council to decide how and where these monies are spent.

2.3This report presents members with a recommended option to spend ‘local’ CIL monies in accordance with CIL regulations that will also help deliver significant outputs.

Background

3.1Since 5th February 2018, the Council has been charging CIL on eligible forms of development. CIL has been developed and aligned with the other Central Lincolnshire Charging Authorities - North Kesteven and West Lindsey District Councils. The CIL charging schedule sets out the rates of CIL rates as follows:

For Residential Development

• Zone 1: The City £25 per square metre • Zone 2: Sustainable Urban Extensions £20 per square metre

For Convenience Retail (supermarkets)

• £40 per square metre

3.2Unlike Section 106 agreements CIL is a non-negotiable charge that developers must pay for eligible forms of development. It is worth noting that affordable housing is not eligible for CIL and affordable housing schemes therefore do not pay CIL. Apartments are also not eligible to pay CIL.

3.3In order to support the levels of growth as set out in the Central Lincolnshire Local Plan, the majority (80%) of CIL receipts will be used to contribute to agreed Central Lincolnshire Strategic Infrastructure priorities - namely the Lincoln Eastern Bypass and Secondary Education. CIL Regulations allow charging authorities to use up to a maximum of 5% of the funds from CIL to recover the costs of administering the levy.

3.4CIL regulations (Reg 59A) require that 15% of CIL receipts (25% where there is a neighbourhood plan in place) are passed onto local councils e.g. Parish or Town Councils. Where there are no local councils as in the City, CIL Regulation 59F requires the Local Authority to use 15% of CIL to support the development of the relevant area by funding the “the provision, improvement, replacement, operation or maintenance of infrastructure” or “anything else that is concerned with addressing the demands that development places on an area”.

3.5For these ‘Local’ CIL receipts, for the City (where there are no Parish or Town Councils) under the CIL regulations it is up to the discretion of the City Council to effectively decide how to distribute the funding to support the delivery of local infrastructure.

3.6Since CIL came into force on 5th February 2018, to date, Local CIL receipts have totalled £49,268.83 which is eligible for spend in the City to support local infrastructure needs as set out in para 3.4 in accordance with the CIL regulations.

3.7A report was taken to Policy Scrutiny Committee in June 2019 where a number of options on the distribution of Local CIL monies were presented. These were:

• Distribution via Neighbourhood Boards • Distribution evenly across all Council Wards • Distribution to targeted areas in the City e.g. Sincil Bank • ‘Bank’ local CIL monies for a period of time e.g. 2-3 years until a more substantial pot is built up

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Community Infrastructure Levy (CIL)Report 119 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 6 attended
NT
Councillor Naomi TweddleChair, present
DN
Councillor Donald NannestadVice-Chair, present
RL
Councillor Rebecca LongbottomCommittee Member, present
LP
Councillor Lucinda PrestonCommittee Member, present
CR
Councillor Callum RoperCommittee Member, apologies
JW
Councillor Joshua WellsCommittee Member, present

On this subject at Lincoln

Search all
  1. Community Infrastructure Levy (CIL)This decision
  2. Community Infrastructure Levy PolicyDecided

More from Lincoln Executive

All decisions
MeetingDecisionOutcome
15 Sep 2026 Confirmation of Minutes - 18 August 2026RESOLVED that the minutes of the meeting held on 18 August 2026 be confirmed and signed by the Chair as a correct rec... Decided Open
15 Sep 2026 Variation to the Constitution – Responsibility for Functions; Adoption of National Scheme of Delegation and Amendments to Planning ProtocolsDecision 1. That a variation to Part 3 – Responsibility for Functions of the Council’s Constitution to reflect the ch... Approved Open
15 Sep 2026 Updated Rechargeable Repairs PolicyDecision 1. That the policy be implemented and briefing sessions to all staff within customer services and housing on... Approved Open
15 Sep 2026 Playground FundingDecision That the progression of this new project and inclusion of a capital estimate of £511,335 in the General Inve... Approved Open
15 Sep 2026 Exclusion of the Press and PublicRESOLVED that the press and public be excluded from the meeting during consideration of the following item of busines... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies