CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
City of Lincoln Council
Performance Scrutiny Committee, Thursday 13 August 2026 at 6.00pm

Treasury Management & Prudential Code – Quarterly Update

Deferred Scrutiny 1 paper

AI summaryPerformance Scrutiny Committee deferred the Treasury Management and Prudential Code quarterly update to its next meeting, postponing scrutiny of the council's investment and borrowing position as at 30 June 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDeferredQuarterly update not scrutinised at this meeting
MoneyNot stated
What happens nextNext Performance Scrutiny Committee meetingItem to be reconsidered at the following meeting
Who it affectsTreasury management oversightQuarterly review of investments and borrowing

What was decided

The committee resolved to defer the item to the next meeting of the Performance Scrutiny Committee, so the quarterly Treasury Management and Prudential Code update was not noted or scrutinised at this meeting.

What happens next

The Treasury Management and Prudential Code quarterly update will be brought back to the next meeting of the Performance Scrutiny Committee for consideration.

The money

  • £9.522m Investments held as at 30th June 2026 Report P9
  • £145k Actual interest earned in the 3 months to 30th June 2026 Report P9
  • £0.618m Forecast interest income for the year, matching the budget Report P10
  • £118.148m External borrowing held as at 30th June 2026 Report P22

Options considered

  • Rejected: Note the Prudential and Treasury Indicators and performance against the Treasury Management Strategy 2026/27, and consider any recommendations to refer to the Executive. Item deferred to the next meeting instead Report 8.1

Implications

  • Governance: Quarterly scrutiny of the council's Treasury Management position and Prudential Indicators, required under the CIPFA Code of Practice, was not completed at this meeting and will be carried over. Report 1.2
  • Financial: Officers confirmed that approved limits within the Annual Treasury Management Strategy were not breached during the quarter ended 30th June 2026, though this was not formally noted by the committee. Report 2.2

Who and where

  • City of Lincoln Council's General Fund investments and borrowing Report P10, P22
  • City of Lincoln Council's Housing Revenue Account investments and borrowing Report P10, P22
  • Council taxpayers and HRA tenants, as the report covers returns on invested balances and borrowing costs Report P12, P30

Timeline

  • 3rd March 2026: Treasury Management Strategy and Prudential Indicators approved by Council Report 3.1, P52
  • 30th June 2026: Quarter end for the Treasury Management and Prudential Indicators reported Report 1.1, P9
  • 2026-08-13: Performance Scrutiny Committee meeting at which the item was deferred

Plain English for the jargon

  • Prudential Code: Framework requiring councils to monitor capital expenditure plans, Prudential Indicators and treasury management, and to set affordable borrowing limits.
  • Authorised Limit: Statutory limit beyond which external borrowing is prohibited, set under section 3(1) of the Local Government Act 2003, with headroom for unexpected movements.
  • Operational Boundary: Indicator of the probable level of external debt during the year, used to help ensure the Authorised Limit is not breached.
  • Capital Financing Requirement (CFR): The council's underlying need to borrow for a capital purpose, compared with actual external debt to show under or over borrowing.
  • PWLB: Public Works Loan Board, a government body that lends to local authorities, offering preferential rates including a lower HRA rate.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item26

Resolved

RESOLVED that this item be deferred to the next meeting of the Performance Scrutiny Committee.
Word for word from the decision Lincoln published for this meeting. Source: democratic.lincoln.gov.uk

Follow this further

Built from Lincoln's papers

What the report saysPro

Report to Performance Scrutiny Committee

Purpose of report

1.1The purpose of this report is to summarise and review the Council’s Treasury Management activity and the prudential indicators at 30th June 2026.

1.2CIPFA’s Code of Practice for Treasury Management (2021) recommends that Elected Members should be informed of the Council’s Treasury Management activities on a quarterly basis. This report, therefore, ensures this Council is adhering to best practice for the scrutiny of capital and investment activity in accordance with the Code of Practice (CIPFA).

Executive summary

2.1The Treasury Management position and performance results for the 3 months ended 30th June 2026 are set out in the body of the report & Appendix A (prudential Indicators).

2.2Officers can confirm that the approved limits within the Annual Treasury Management Strategy were not breached during the quarter ended 30th June 2026.

Background

3.1The prudential system for capital expenditure is well established. One of the requirements of the Prudential Code is to ensure adequate monitoring of the capital expenditure plans, Prudential Indicators (PIs) and treasury management response to these plans. This report fulfils that requirement and includes a review of compliance with Treasury and Prudential Limits and the Prudential Indicators at 30th June 2026. The current Treasury Management Strategy and Prudential Indicators were approved by Council on 3rd March 2026.

3.2The Council has adopted the CIPFA Code of Practice for Treasury Management in the Public Sector and operates its treasury management service in compliance with this Code and the above requirements. These require that the prime objective of treasury management activity is the effective management of risk, and that its borrowing activities are undertaken in a prudent, affordable and sustainable basis.

3.3This report highlights the changes to the key prudential indicators, to enable an overview of the current status of the capital expenditure plans. It incorporates any new or revised schemes previously reported to Members. Changes required to the residual prudential indicators and other related treasury management issues are also included.

4. Treasury management Update 4.1 Investment portfolio

4.1.1 The Council held £9.522m of investments as at 30th June 2026 achieving an average interest rate of 3.98% (4.16% 25/26). Actual interest earned in the 3 months period to 30th June 2026 totalled £145k.

4.1.2 Forecast interest income for the year is £0.618m (£0.163m General Fund & £0.454m HRA), this matches the £0.618m budget.

4.1.3 As at 30th June 2026, 100% of the council’s investment portfolio was held in low risk specified investments, the requirement for the year being a minimum of 25% of the portfolio to be specified investments.

4.1.4 Where possible the council seeks sustainable investments and are working with our advisors on the best way to score banks and funds ESG ratings, whilst balancing this against generating returns that are in the best interest of the tax payer.

4.1.5 Liquidity – The Council seeks to maintain liquid short-term deposits of at least £5m available with a week’s notice, and has maintained a balance above this throughout the quarter. At 30th June 2026, the Council held liquid short term deposits of £9.522m

4.1.6 Security - The Council’s maximum security risk benchmark for the portfolio as at 30th June 2026 was 0%, based on the historic risk of default of the counterparties and types of accounts in which the council’s funds are placed.

4.1.7 Yield – The Council achieved an average return of 3.98% on its investment portfolio for the 3 months ended 30th June 2026. This is comparable to the average SONIA rate for the quarter, of 3.73%.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Treasury Management & Prudential Code: Quarterly UpdateReport 211 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 11 attended
AP
Councillor Anita PritchardChair, present
LA
Councillor Lesley AllinsonCommittee Member, present
CB
Councillor Chris BurkeVice-Chair, present
AC
Councillor Andrew CurrieCommittee Member, apologies
AC
Councillor Annie CurrierCommittee Member, apologies
TD
Councillor Thomas DyerCommittee Member, present
DH
Councillor Darrell HardingCommittee Member, apologies
LK
Councillor Liam KellyCommittee Member, present
AW
Councillor Aiden WellsCommittee Member, present
CW
Councillor Calum WattSubstitute, present
JB
Councillor James BrownSubstitute, present

On this subject at Lincoln

Search all
  1. Treasury Management & Prudential Code – Quarterly UpdateThis decision
  2. Treasury Management and Prudential Code - Quarterly UpdateNoted
  3. Treasury Management Stewardship and Actual Prudential Indicators Report 2025/26 (Outturn)Noted
  4. Treasury Management Stewardship and Actual Prudential Indicators Report 2025/26(Outturn)Agreed
  5. Treasury Management Stewardship and Actual Prudential Indicators Report 2025/26 (Outturn)Noted
  6. Prudential Indicators 2025/2026 to 2028/2029 and Treasury Management Strategy 2026/2027Approved

More from Lincoln Performance Scrutiny Committee

All decisions
MeetingDecisionOutcome
13 Aug 2026 Confirmation of Minutes - 9 July 2026RESOLVED that the minutes of the meeting held on 9 July 2026 be confirmed subject to the following amendment: - Counc... Decided Open
13 Aug 2026 To Receive the Minutes of Housing Scrutiny Sub-Committee - 4 June 2026RESOLVED that the minutes of the Housing Scrutiny Sub-Committee meeting held on 4 June 2026 be received. Decided Open
13 Aug 2026 Financial Performance - Quarterly MonitoringRESOLVED that this item be deferred to the next meeting of the Performance Scrutiny Committee. Deferred Open
13 Aug 2026 Income and Arrears MonitoringRESOLVED that the report be noted. Noted Open
13 Aug 2026 Work Programme 2026/27RESOLVED that the work programme 2026/27 be noted. Noted Open