Environment Scrutiny Committee Work Programme

Agreed Scrutiny 1 paper

AI summaryLincolnshire County Council's Environment Scrutiny Committee agreed its work programme with changes and that a separate item could be scheduled. The programme covers environmental policy, nature recovery and the Mixed Dry Recycling Contract.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedChanges suggested above are to be included.
MoneyNot stated
What happens nextSchedule a separate itemThe Committee agreed this could be scheduled.
Who it affectsEnvironment Scrutiny Committee work programmeIt covers policy, nature recovery and recycling contract scrutiny.

What was decided

The Committee agreed the work programme, provided the suggested changes are made.

It agreed that a separate item could be scheduled.

Why

The programme focuses scrutiny on proposed decisions within the Committee's remit. Report P4

It records consultation routes, key dates, consulted groups, affected decisions and decision makers. Report P5, P6, P7

What happens next

Reflect the suggested changes in the work programme.

Schedule the separate item.

Options considered

  • Chosen: Agree the work programme with the suggested changes
  • Chosen: Schedule a separate item

Implications

  • Other: The agreement is conditional on the suggested changes.
  • Other: A separate item can be scheduled.
  • Legal: The programme records statutory consultation for the Local Nature Recovery Strategy. Report P7
  • Other: The work programme covers three proposed decisions. Report P6, P7

Who and where

  • Council Departments Report P7
  • Wildlife organisations Report P7
  • Greater Lincolnshire Local Authorities Report P7
  • Landowner Organisations Report P7
  • Commercial and Procurement Services Report P7
  • Environment Scrutiny Committee Report P6, P7
  • Head of Environment Report P6, P7
  • Executive, Executive Manager and Councillor for Environment Report P6, P7

Timeline

  • 2026-02-13: The Committee agreed the work programme with changes and that a separate item could be scheduled.
  • 3 Mar: Environmental Policy is listed for scrutiny. Report P6
  • 9 Jun: Adoption of the Local Nature Recovery Strategy is listed for scrutiny. Report P7
  • 29 June - 10 July: Procurement of the Mixed Dry Recycling Contract is listed for scrutiny. Report P7

Plain English for the jargon

  • Work programme: The Committee's planned scrutiny subjects and related arrangements.
  • Scrutiny: Committee review of decisions through its work programme.
  • Statutory consultation: The consultation listed for the Local Nature Recovery Strategy.
  • Mixed Dry Recycling Contract: The contract included for scrutiny in the programme.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item52

Resolved

It was agreed that a separate item could be scheduled. RESOLVED That the work programme be agreed subject to the changes suggested above.
Word for word from the decision Lincolnshire published for this meeting. Source: lincolnshire.moderngov.co.uk

Follow this further

Built from Lincolnshire's papers

What the report saysPro

Report to Environment Scrutiny Committee, 6 pages

Agenda Item 9

Open Report on behalf of Andrew McLean, Interim Executive Director - Resources

Report to: Environment Scrutiny Committee Date: 13 February 2026 Subject: Environment Scrutiny Committee Work Programme Decision Key Reference: decision? No Summary: This item enables the Committee to consider its work programme.

Actions Required: The Committee is invited to review its work programme and highlight any items which could be added to the programme.

1. Work Programme

The Committee’s work programme is set out below: -

13 February 2026– 10:00am Item Contributor(s) Notes

Chris Miller, Head of Environment Humber 2100+ Representatives from the 1 Scrutiny Report Programme Environment Agency Representatives from West Lindsey District Council

On 3 March 2026, the Chris Miller, 2 Environment Policy Executive is due to consider Head of Environment a new Environment Policy.

Page 59 13 February 2026– 10:00am Item Contributor(s) Notes

Service Level Performance Reporting Chris Yorston, Head of Waste This quarterly report covers 3 Against the Performance Chris Miller, Head of performance for quarter 3. Framework 2025-26 as Environment at Quarter 3

This report provides an update on the handbook, ensuring an appropriate Lincolnshire Archaeology Ian George, Historic Places 4 recording of the county's Handbook Manager archaeological heritage through the planning process.

27 March 2026– 10:00am Item Contributor(s) Notes

Chris Miller, Head of Environment Morgan Wray, Area Flood and Coastal Risk Manager, Environment Agency Flood Risk Management Matt Moore, Strategic 1 Scrutiny Report Authorities Update Partnership Manager, Anglian Water Jane Froggatt, Chief Executive of Upper Witham, Witham First and Witham Third Internal Drainage Boards

This item will provide an Justine Robson, Senior update on the Streets 2 Streets Design Code Development Management Design Code project, now Officer titled Better Streets for Lincolnshire.

Collaborative Working This item was requested by Chris Miller, 3 on Strategic Flood Risk Committee on 1 August Head of Environment Management Schemes 2025.

Page 60 27 March 2026– 10:00am Item Contributor(s) Notes

Salix Scheme – Conclusion to Scheme Chris Miller, Head of Environment, 4 NOTE: This item may Scrutiny Report include the use of solar Dan Clayton, Environmental panels on the roofs of Strategy Manager Council properties

15 May 2026– 10:00am Item Contributor(s) Notes

Chris Miller, On 9 June 2026, the Adoption of the Local Head of Environment Executive is due to make a 1 Nature Recovery decision on the adoption of Strategy Dan Clayton, Environmental the local nature recovery Strategy Manager strategy.

19 June 2026– 10:00am Item Contributor(s) Notes

Between 29 June - 10 July 2026 the Executive Procurement of the Chris Yorston, Head of Waste Councillor for Environment 1 Mixed Dry Recycling Carl Newell, Commercial and is due to make a decision on Services Contract Procurement Manager the procurement of the mixed dry recycling services contract.

Chris Miller, Head of Environment Morgan Wray, Area Flood and Flood Risk Management Coastal Risk Manager, 2 Scrutiny Report Authorities Update Environment Agency Matt Moore, Strategic Partnership Manager, Anglian Water

Page 61 19 June 2026– 10:00am Item Contributor(s) Notes

Service Level Performance Reporting Against the Performance Chris Miller, Head of Framework 2025 - 2026 This quarterly report covers 3 Environment Quarter 4: performance for quarter 4. Chris Yorston, Head of Waste Environment (including Flood Risk Management and Waste)

2. Items to be Programmed

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Environment Scrutiny Committee Work ProgrammeReport 6 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Lincolnshire

Search all
  1. Environment Scrutiny Committee Work ProgrammeThis decision
  2. Environment and Economy Scrutiny Committee Work ProgrammeNoted
  3. Environment and Economy Scrutiny Committee Work ProgrammeApproved
  4. Environment and Economy Scrutiny Committee Work ProgrammeAgreed
  5. Environment and Economy Scrutiny Committee Work ProgrammeAgreed
  6. Environment and Economy Scrutiny Committee Work ProgrammeAgreed

More from Lincolnshire Environment Scrutiny Committee

All decisions
MeetingDecisionOutcome
13 Feb 2026 Minutes of the Meeting held on 16 January 2026RESOLVED That the minutes of the previous meeting on 16 January 2026 be signed by the Chairman as a correct record. Decided Open
13 Feb 2026 Humber 2100+ ProgrammeRESOLVED That the Committee acknowledges the work undertaken across the Humber 2100+ programme and recommends the Exe... Decided Open
13 Feb 2026 Lincolnshire Archaeology HandbookRESOLVED That the report be noted. [Note: Cllr Bean entered the meeting at 12:16] Noted Open