Resolved that – (i) the contents of this report, be noted: (ii) the Executive Director for Regeneration be authorised to accept ERDF grant totalling £1,055,937 and, in doing so, permit the City Council to accept the role of accountable body; (iii) the Highways Manager be appointed as the nominated officer for the purposes of monitoring compliance with the terms and conditions of the grant. (The duties of the nominated officer will include maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year that the liability is likely to arise); (iv) expenditure totalling £2,111,874 be committed from the 2003/04 Transportation Capital Programme and thereby ensure that Phase 4 capital project is completed during the 2003/04 financial year; and (v) the tender of £1,230,425.65 submitted by Dowhigh Ltd in respect of the A565 Atlantic Avenue Phase 4 Project be accepted and a contract be entered into with them to construct the works as specified in the contract documents and drawings.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
• Update Members on the progress of the A565 Atlantic Avenue scheme.
• To advise Members of, and seek approval for the revised financial implications and contract sums
Background
2.1Originally promoted by the Merseyside Development Corporation (MDC), the overall aim of the A565 ‘Atlantic Avenue’ project is to provide the Liverpool North Docks (Atlantic Gateway) SIA with a strategic, modern and high quality road link which will;
• Maximise the development of new employment sites – and therefore the regeneration of the area - by improving transportation links to the rest of the city and the wider area.
• Support existing businesses by improving the said same transport links.
• Help to reduce the environmental impact of traffic on the local community by transferring inappropriate vehicles from the environmentally sensitive roads (such as the A5036 Commercial Road/Vauxhall Road corridor) onto the A565. • Reduce congestion and delays and thereby levels of pollution.
2.2The first two phases – Leeds St and Sandhills Lane junction improvements – were undertaken by MDC. Phase 3 was carried out by the City Council and was completed in August 2000. The fourth phase involves widening a 0.9km length of the A565 from Athol St to Errington St to create a new section of dual carriageway (a copy of the plan is available from Design Consultancy’).
2.3In addition to the widening works, the scheme will also involve the construction of new footways, drainage systems, and the provision of new signs, street lights, safety fencing/pedestrian guardrails, and traffic signals (these will incorporate facilities for pedestrians and cyclists).
3 Programme Update
3.1Tenders were returned on 20 January 2003 and following a detailed evaluation, a preferred contractor has been identified. However, the City Council has not, as yet, entered into any formal contractual arrangement with the preferred bidder.
3.2Detailed funding bids were submitted to GONW (via the European Team) in March 2003. The Project was considered and approved at the Projects Panel on 3 April 2003 and the formal offer letter was received on 24 April 2003.
3.3If approval is given to the recommendations set out in this paper, it is anticipated that the works will commence with 4-6 weeks. The expected completion date will be sometime towards the end of March 2004.
3.4The final two stages of the project - Phases 5 and 6 - are planned to be constructed in the next 3-4 years. These will extend the dual carriageway from Athol Street to Leeds Street in the south and up to Millers Bridge in the north, thereby creating a high-quality link road from the City Centre to the ‘Atlantic Gateway’ SIA.
4 Funding and Costs
4.1The estimate now for Phase 4 is £2,111,874 (this includes statutory undertakers costs and other fees) which will be delivered through the 2003/04 Transport Capital Programme, funded by a combination of City Council General Resources (£456k) and Supplementary Credit Approvals(£600k), and the remainder from ERDF grant.
4.2Design fees and other related expenditure to a value of approximately £135,000 have already been incurred in 2002/03 in developing the scheme and procuring the works contract. 5. Maintenance Arrangements
5.1The length of the A565 which is the subject of the planned improvement is currently an adopted highway. Hence, once the works have been completed, they will be maintained by Enterprise-Liverpool under the current highways maintenance agreement.
Executive Member/Director recommendation (Councillors Peter Millea and Chris Curry/ Charlie Parker)
That -
i) the contents of this report be noted:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.