Agreed that this matter be clarified with Enterprise – Liverpool and information be submitted to the next meeting. b) Minute 5 – Youth Sub Groups Concern was expressed that the information requested at the last meeting in relation to the bidding process and the £5,000 allocation to Committees, has not been submitted. Agreed that the Head of the Youth Service be requested to provide this information to all Area Committee Chairs as soon as possible. c) Minute 8 – Lead Officers and Executive Members Members were advised that the Leader of the Council will act as Executive Member to the Clubmoor , Gillmoss and Pirrie Area Committee and that consideration is being given to the appointment of a Lead Officer to the Gateacre Area Committee. d) Minute 9 – Advisory Members It was accepted that the role of Advisory Members should be discussed at a future meeting. e) Minute 10 – Publicity Members were advised that the likely publication date for the publicity posters is 12 September. Agreed that the Minutes of the last meeting be approved and the action detailed above be implemented.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Chairs Area Committee Lead Officer Richard Roberts (A) Dave Boyer Rose Bailey (B) (C) Kevin Firth (D) John Kelly Keiron Reid (E) Eric Wilkinson (F) Chris Walsh Jan Clein (G) Sally Medlyn John Coyne (H) Robert Corbett Frank O’Donaghue (I) (J) Ben Dolan (K) Mike Burchnall
Apologies for absence were received from Councillors Ann Hines, Frank Prendergast, Erica Kemp, Chris Byrne and Ann Melville
Officers
Penny Wakefield Director of Liverpool Partnership Group Martin Joyce Liverpool Enterprise Mike Cockburn Liverpool Enterprise Mike Eccles Planning Service Chester Morrison Head of Youth Service
1. Declarations of Interest
None was submitted
2. Minutes of the Last Meeting
It was agreed that the minutes of the last meeting held on 25 April 2003 be approved as a true record. 3. Matters Arising
Penny Wakefield advised the Committee of the progress in developing the neighbourhood management agenda.
It was stated that: –
i. 5 of the 7 neighbourhood co–ordinators who had now been appointed and the list was circulated ii. the boundaries of the 7 areas identified were operational boundaries; and iii. that a series of presentations will be arranged for individual area Committees outlining the details of how it would operate.
4. Enterprise Liverpool Direct Limited
The Committee received a presentation from Martin Joyce, Liverpool Enterprise detailing the joint venture, the terms of the contract and how the service was to be provided in the areas.
It was stated that: –
a) a representative would be appointed to attend each area committee; and b) the shift work patterns for the area would also be circulated to local ward members.
Members raised the following issues: –
i. whether the area committee could have an input in respect of shift patterns and whether the shift patterns had been agreed with the staff concerned. ii. whether the performance under the contract could be reported to the area committees in terms of the indicators identified iii. how had the street lighting programme been determined iv. street cleansing and highways maintenance activities which are taking place needs to be co–ordinated
v. whether elected members could be provided with a priority number to use vi. would the work compliment the work of INclude (environment) which had undertaken a number of initiatives in the Dingle area and therefore ensure plurality vii. was there any money available for the provision of litter bins in local areas M. Joyce stated: –
(a) the criteria for the lighting programme was determined through the areas with the highest incidents recorded and was run by a Community Safety/City Safe Initiative (b) feedback would be given to local area committees on the performance under the contract (c) consultation was still in progress on the shift patterns and these would be reported to the area committees (d) calls will be dealt with by Liverpool Direct and service areas were looking at the scripts to be used to make it more efficient (e) the work of INclude would be accommodated (f) area committees would be asked for their views on the placement of litterbins and a sum of money had been allocated in the budget for this (g) work had been ongoing with colleagues in Onyx to co–ordinate activities with highways maintenance and environment
5. Youth Sub Groups
The Committee discussed the arrangements for the roll out of the Youth Advisory Groups.
Chester Morrison outlined:
i. the timetable for the first meetings of the advisory groups ii. it was proposed there would be 4 meetings per year iii. £5K will be allocated to each area committee to promote the work of the advisory groups
Members raised the following issues: –
i. the success of 2 of the pilots under Pirrie/Clubmoor/Gilmoss and Gateacre Area Committees ii. which area committees had received £5K to date? iii. letters had been circulated to members as part of a bidding process for financial support for the advisory groups
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Terms of Reference and ProtocolsAgreed that the present terms of reference and protocols be recommended for approval subject to – a) the introduction...
Appointment of Advisory MembersAgreed that – a) The proposal be accepted in principle at this stage; b) All Area Committees be requested to consider...
Annual Report for Area CommitteesAgreed that the format detailed in Report LS/13/05 be approved and an annual report be prepared in respect of the ope...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.