Resolved
Agreed that - a) The thanks of the Committee be extended to the staff in this service for their performance; and b) Future reports include an explanation of the abbreviations included
Resources Select Committee 2005/2006 agreed this item on Tuesday 9 September 2003. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that - a) The thanks of the Committee be extended to the staff in this service for their performance; and b) Future reports include an explanation of the abbreviations included
To advise Members on the activities and performance of the Treasury Management operation in 2002/2003 in accordance with the CIPFA Code of Practice.
That the Treasury Management Annual Report 2002/2003 be noted.
INFORMATION:
Financial Regulations require that an annual report on Treasury management activities for each financial year is presented to members in accordance with the CIPFA Code of Practice for Treasury Management in Local authorities. The report appended to RTRM/05/2003 constitutes that annual report for 2002/2003.
None stemming directly from this report.
TIMESCALE FOR ACTION:
Treasury Management is a continuous activity.
Not appropriate for this report.
BEST VALUE:
The report details the way in which Treasury Management is contributing to Best value.
None.
CORPORATE STRATEGY:
Treasury Management is an important aspect of the Council’s budget strategy.
COMMUNITY SAFETY IMPLICATIONS:
None.
RTRM/04/02 – Treasury Management Strategy 2002/03 RTRM/11/02 – Interim Treasury Management Report 2002/03 Treasury Management in the Public Services – Code of Practice Standing Orders and Financial Regulations Appendix 1
TREASURY MANAGEMENT ANNUAL REPORT 2002/2003
INTRODUCTION
1. The CIPFA Code of Practice for Treasury Management in Local Authorities has been adopted by the Council. The Code requires that Treasury Management activities are subject to regular reports to Members. This report represents the final report on Treasury Management for 2002/2003.
2. The strategy for the year was identified in the Treasury Management Strategy Statement 2002/2003 (Report No.RTRM/04/2002) submitted to Members in March 2002. The strategy covers the following areas:
(a) - prospects for interest rates; (b) - capital borrowings required and the portfolio strategy; (c) - debt rescheduling opportunities; (d) - responses to different interest rate regimes; (e) - other capital financing facilities; (f) - temporary investment strategy;
PROSPECTS FOR INTEREST RATES
3. The 2002/2003 Strategy Statement indicated that base rates (short term) at 4% were probably at the low point of the cycle and were likely to remain at that level until the recovery in world demand became established. If the recovery occurred as predicted then some tightening of monetary policy would be expected and base rates could reach 4.75% by the end of the financial year. Recovery was slow and growth assumptions were revised downwards resulting in downward pressure on base rates and the MPC reduced the rate to 3.75% at its February 2003 meeting after 14 months unchanged at 4%.
4. Long term interest rates which reflect the yield on government bond issues (gilts) were expected to remain in a range from 5.00% at the shorter end to 5.50% for longer periods providing there were no major shocks to the forecasts. Long term rates were stable in the first quarter of the year then fell in the second quarter as a flight to quality from the equity market to gilts took place amid financial scandals, stock market collapses and fear of war with Iraq. Rates rose in the third quarter before falling again as the hoped for recovery in world markets failed to transpire. At the end of the financial year PWLB rates had fallen to a range of 3.50% at the shorter end to 4.80% at the long end of the yield curve.
CAPITAL BORROWINGS REQUIRED AND THE PORTFOLIO STRATEGY
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Treasury Management Annual Report 2002/03Report | 9 pages | DownloadRead as text |
Follow Resources Select Committee 2005/2006 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Apr 2006 | Minutes of the Last MeetingsAgreed that the minutes be approved. | Agreed | Open |
| 5 Apr 2006 | Called In Item - Percy Street/Upper Parliament Street/Parliament StreetAgreed that in view of the concerns expressed by members, consideration of this proposal be deferred pending the subm... | Agreed | Open |
| 5 Apr 2006 | Response to Motion - Properties in Newsham ParkAgreed that the Executive Member for Resources be requested to ensure that all long term vacant Council properties in... | Agreed | Open |
| 5 Apr 2006 | Revenues and Benefits Service PerformanceAgreed that the content of the report be noted. | Agreed | Open |
| 5 Apr 2006 | Green Paper - A New Deal For Welfare Empowering People to WorkAgreed that – a) The contents of the report be noted; b) The views of the Committee, particularly in relation to the ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.