Liverpool City Council
Executive Board, Friday 3 October 2003

Ground Floor, 191 Scargreen Avenue

Approved Executive 1 paper

Executive Board approved this item on Friday 3 October 2003. Below is the council's own wording, with the papers it was decided on.

Item194

Resolved

Resolved that approval be given - (i) for the City Council to take a new lease of the ground floor, 191 Scargreen Avenue from a date to be agreed, for a term of 2 years at a rental of £5,200 per annum and otherwise on terms and conditions agreed by the Operations Manager Land and Development Services; and (ii) to draw down £19,000 from the £1million Sure Start capital funds included within Education capital programme
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 4 pages

Executive summary

The purpose of this report is to seek authority to for Liverpool City Council to take a new lease of ground floor premises at 191 Scargreen Avenue for Norris Green Sure Start to deliver Sure Start services advice in the heart of Norris Green area.

It is proposed that the City Council take a lease of the ground floor of 191 Scargreen Avenue for a term of 2 years to terminate on a date to be agreed at a rental of £5,200 per annum. The lease will incorporate a 6-month rent-free period from the start of the term.

The property is situate on a fairly busy parade close to the junction of Scargreen Avenue and Utting Avenue East. It comprises a former shop recently used as an office, 4 rear offices, kitchen and disabled toilet. The City Council will undertake some internal refurbishment including a new suspended ceiling with integral light fittings, redecoration throughout, new flooring and alterations to electrical and plumbing, joinery and general fitting out to make the premises fit for purpose. The cost of these works will be met from secured Sure Start funding.

Norris Green Sure Start propose to develop a new-build Sure Start Centre in Norris Green and this property is intended for their interim use until the new centre is built. Should they decide to renew the lease at the end of the term however the City Council’s improvements will be excluded from consideration at lease renewal.

In order to promote its services to maximum effect in the Norris Green area the Sure Start requires premises with a good level of visibility and accessibility within the heart of Norris Green and this Unit meets their criteria.

The Operations Manager of Land & Development Services has provisionally agreed terms for a lease to the City Council from a date to be agreed for a term of 2 years. The rent to be £5,200 per annum without review. Executive Director recommendation: That -

1. approval be given for the City Council to take a new lease of the ground floor, 191 Scargreen Avenue from a date to be agreed, for a term of 2 years at a rental of £5,200 per annum and otherwise on terms and conditions agreed by the Operations Manager Land & Development Services.

2. approval be given to draw down £19,000 from the £1million Sure Start capital funds included within Education capital programme

Key Decision: No

Forward Plan: No

Implementation effective from: 10 October 2003

Timescale for action:

The Head of Legal Services will be instructed to complete the documentation concluding matters at the earliest opportunity.

Reasons for recommendation

The Norris Green Sure Start requires this premises as a temporary office in which to offer public access and facilities as well as an administrative base order to deliver the Sure Start service more effectively within the Norris Green area. It is intended as an interim base pending the development of the new- build facility that is proposed for the site of the former William Roberts Baths, Utting Avenue East.

The Operations Manager of Land and Development Services is of the opinion that the provisionally agreed rent represents the best reasonably obtainable at the present time.

Alternative options to be considered:

There are no alternative premises available in immediate area Consultation:

1. David Henshaw, The Chief Executive and Liam Murphy , former Executive Director Alt Valley Partnership agreed to the commencement of negotiations for the new lease

2. Nicky Green, Principal Finance Officer – Sure Start, Education Finance has confirmed that the total expenditure for the scheme can be met from the existing and future Sure Start budget provision

Financial implications

The project is specifically funded from an external grant under the Central Government Sure Start Scheme

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Ground Floor, 191 Scargreen AvenueReport 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Ground Floor, 191 Scargreen AvenueThis decision
  2. Update – Ground floor, 68 Falkner Street, Liverpool L8 7QA (M/41)Agreed
  3. Disposal of a Ground Floor Two Bedroomed Flat in Kremlin Drive (NH/26)Approved
  4. IT Data Centre - Lower Ground Floor, Basement and Sub-Basement, India Buildings, Water Street (RES/106)Approved
  5. Front Ground Floor Office, 291-299 KensingtonAgreed
  6. Ground Floor Car park, Kingsway House, Hatton GardenDecided

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies