Resolved
Agreed that the Executive Board decision be implemented and a report be submitted to the next meeting on the implications of the Prudential Code.
Resources Select Committee 2005/2006 agreed this item on Wednesday 22 October 2003. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that the Executive Board decision be implemented and a report be submitted to the next meeting on the implications of the Prudential Code.
CITY STATUS – PUBLIC RES/33 Portfolio: Resources Executive Member: Councillor Chris Curry Date of submission: Subject: 3 September 2003 Capital Programme 2003/04 Report No: Contact Officer: FMS/22/03 Robert Corbett AED Financial Management Tel: 0151 225 2200 [email protected] Executive Summary
1. This report seeks the approval to the attached proposed Capital Programme for the financial year 2003/04. In preparing the proposed Capital Programme consideration has been taken into account of the revised assessment of the capital resources available to the City Council and to the capital expenditure commitments from previous years.
2. The revised assessment of the Council’s commitment to the delivery of capital based schemes and initiatives has identified that the Council’s Capital Programme for the current financial year should be £172.9 million. This Programme now takes into account slippage from previous years, a prioritised assessment of capital initiatives for future years and a number of recently approved initiatives that were not included within the Programme presented to Council on the 10th March.
3. The key features of this proposed Capital Programme are expenditure of :
¾ £37.4 million on Housing initiatives of which £19.9 million relate to improvements to Council owned stock. ¾ Highways maintenance and improvements (including traffic safety measures) totalling £30.2 million. ¾ £35 million on Education developments. ¾ £30.7 million on Regeneration and Environmental initiatives.
4. The schemes and initiatives within the Programme will attract specific capital financing resources by way of grant and specific borrowing approvals totalling £122.6 million – approximately 71% of the total estimated cost of the programme. 5. However, the proposed Capital Programme for 2003/04 will also require £50.3 million of general capital resources to be provided by the City Council. Alternatively, the Council could consider removing schemes to this value although this would have a severe impact on the infrastructure across the City and is therefore not recommended.
6. It should be noted that the Council has submitted bids for Government grants for a number of schemes. In the event of the bids being successful before committing Council expenditure to these schemes the Council may need to consider the overall net cost of the scheme against other priorities.
Executive Member’s recommendation (Councillor Chris Curry)
That, having regard to the financial implications identified in this Report:
a. the Capital Programme for 2003/04 as attached and totalling £172.9 million be approved and officers be directed to ensure, in accordance with the City Council’s Standing Orders, the implementation of all schemes and initiatives within this Programme.
b. the Capital Programme for 2003/04 be financed as follows:
£ million
Government Grants 103.3 Specific Scheme Borrowing 7.0 Private Sector Contributions 9.0 Other Specific Financing 3.3 122.6
General Borrowing 18.6
Capital Receipts Generated in the year 11.0 Brought Forward 2.2
Capital Expenditure from Revenue Specific Initiatives 2.3 Brought Forward to fund Slippage 2.7
Additional Borrowing Approvals or Use of Reserves 13.5 172.9 c. Executive Director (Resources) and the Assistant Executive Director (Financial Management) take appropriate decisions to fund this Capital Programme, having regard to the availability of alternative resources during the year and report to the Resources Select Committee on 10th December 2003.
Key Decision
Yes – the Report seeks the approval of a revised Capital Programme for 2003/04.
Forward Plan/5 days notice/special urgency
No, an appropriate notice will be published in accordance with the constitution.
Implementation effective from
26 September 2003 Timescale for action
The Report gives authority to officers to ensure accordance with the City Council’s Standing Orders the prompt implementation of all schemes and initiatives within the Programme.
Reason(s) for Recommendation
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Called In Item: Capital Programme 2003/04Report | 6 pages | DownloadRead as text |
Follow Resources Select Committee 2005/2006 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Apr 2006 | Minutes of the Last MeetingsAgreed that the minutes be approved. | Agreed | Open |
| 5 Apr 2006 | Called In Item - Percy Street/Upper Parliament Street/Parliament StreetAgreed that in view of the concerns expressed by members, consideration of this proposal be deferred pending the subm... | Agreed | Open |
| 5 Apr 2006 | Response to Motion - Properties in Newsham ParkAgreed that the Executive Member for Resources be requested to ensure that all long term vacant Council properties in... | Agreed | Open |
| 5 Apr 2006 | Revenues and Benefits Service PerformanceAgreed that the content of the report be noted. | Agreed | Open |
| 5 Apr 2006 | Green Paper - A New Deal For Welfare Empowering People to WorkAgreed that – a) The contents of the report be noted; b) The views of the Committee, particularly in relation to the ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.