Resolved that – (i) the recommendation be approved but that Officers be asked to look at the feasibility for the work to be undertaken by a social business; and (ii) a report be submitted to a future briefing meeting for the Leader and Executive Members on the progress with regards to Liverpool Plus.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Portfolio: Environment Executive Member/Director: Councillors Richard Oglethorpe and Chris Curry
Date of submission: 6 November Subject: St James Gardens open 2003 space improvement project.
Report No./273/03 Background Contact officer: Rob Wallace papers 233 6384 Background Report EDR/407/02 EIP Performance plan 2003/4
Executive summary St James Gardens, also known as St James Cemetery, lies adjacent to the Anglican Cathedral and Hope Street, and is the area’s principal area of public open space. The gardens are also potentially a popular visitor attraction due to their very close association with the Cathedral.
The site is often perceived as a hidden garden as it lies in a former quarry site and is poorly signposted with limited access points. Due to it’s concealed nature and close proximity to the city centre it has severe problems with crime and anti-social behaviour, with large numbers of syringes having to be cleared from certain areas on regular occasions. The gardens also contain several important historical features that are in a state of dilapidation, including the Huskisson Monument and several large catacombs. The footpaths are currently in a bad state of repair, and there is no seating or litter bins.
The project aims to alleviate some of the crime and anti-social behaviour problems in the gardens, and at the same time encourage visitors, both tourists and local people. Additional aims are to carry out exploratory and remediation works to key historical features, re-instate the footpaths, and provide seating and litter bins.
The design for the project has evolved from priorities that have been highlighted by the City Councils Parks and Environment Division and a local community group (The Friends Of St James). Consultation with the Joint Agency Group and City Safe has also taken place.
The project has been designed to an advanced stage, and is expected to cost up to £220,000 (including fees). The works will be 100% funded though the City Centre Environmental Improvement Programme (EIP), as detailed in the 2003/4 performance plan. An application for funding is currently being internally appraised within the City Council, following the granting of delegated powers within the City Centre EIP for any project up to the value of £250,000. Executive Member/Director recommendation (Councillors Richard Oglethorpe and Chris Curry/Charlie Parker)
That in relation to St James Gardens public space improvement project,
(i) authority be given to the Executive Director (Regeneration) to accept up to £220,000 of City Centre Environmental Improvement Programme Grant allocation, phased over the financial years 2003/04 and 2004/05 to finance the St James Gardens project;
(ii) the Team Leader City Centre Projects Team, will be appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant. (This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises);
(iii) the City Councils capital programme be adjusted to reflect expenditure on this project to a maximum of £220,000 phased over the financial years, 2003/04 (up to £215,000) and 2004/05 (£5,000) together with the grant income to finance the expenditure;
(iv) subject to the works contract not exceeding £220,000 and compliance with Standing Orders and Financial regulations, authority be given to accept tenders on the St James Gardens public space improvement project, and to subsequently appoint a contractor to undertake the works; and
(v) subject to the works contract and professional fees not exceeding £220,000 and compliance with Standing Orders and Financial regulations, authority be given to commit expenditure on the St James Gardens public space improvement project.
Key Decision
Yes
Forward Plan
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.