Regeneration & Environment Select Cttee 2005/2006 agreed this item on Thursday 22 January 2004. Below is the council's own wording, with the papers it was decided on.

Item19

Resolved

Agreed that the report be noted and Councillor Jane Corbett be provided with a breakdown of the sources for funding for the different budget lines identified within the report.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Regeneration & Environment Select Cttee 2005/2006, 5 pages

Purpose of report

1. To provide the financial review for the Regeneration Portfolio for third quarter of the current financial year.

Recommendations

2. Members note that there is no forecast variation being projected for the financial position of the Regeneration Portfolio.

INFORMATION

3. This report provides an update on the financial position for the non- housing services provided through the Regeneration Portfolio on the basis of the best information available. A separate report has been prepared for the Housing General Fund services delivered through the Regeneration Portfolio. It is anticipated that these will be amalgamated into a single overall Regeneration Portfolio report in the near future.

Revenue

4. The total net revenue budget for the Regeneration Portfolio for the current financial year is £77.082 million as indicated in Appendix A.

5. It is anticipated that overall spending at the year-end for services provided by Regeneration will be in line with allocated budgetary resources.

6. The overall Regeneration budget depends on the achievement of a number of income targets, including external grants, markets, depots, capital receipt, pest control and trading standards fees and charges, design consultancy fees, planning fees, trade waste fees, traffic regulation orders, car parking, cemeteries and crematoria, and achieving order-books. These have been and remain at risk budgets. All income budgets are closely monitored throughout the year to ensure that the financial position is carefully managed.

Income in many areas is dependent upon external market forces, which is largely outside the direct control of the Portfolio:

• Land and Development Services – additional income is expected over and above currently budgeted levels from fees generated from capital receipts, and from valuations for right to buy properties due to the growth of private investment within the city. Also additional rental income is anticipated from the Commercial and Industrial Estate as a result of the increasing economic activity within the city. The impact of the 2o2o partnership is also beginning to accrue benefits in this area.

• Planning and Development – as a result of the ongoing successful regeneration of the city and the extent of major developments underway, income generated from planning and building control fees is expected to be over and above currently budgeted levels.

Other income budgets are currently forecast as performing to or above budget, with the following exceptions: City Centre – certain costs previously anticipated as funded through external grant will now have to be funded from the General Fund.

Design Consultancy – during the year there have been ongoing reviews of the order-book. However, with effect from 1st October 2003, this service was transferred into 2o2o Liverpool. A full reconciliation of the income and expenditure position at 30th September 2003 is underway, and will be complete as 2o2o transfer to new systems.

Environmental Services - income is currently forecasting below budget and a review of the order-book is being undertaken.

Waste Management – there has been a loss of order book as a result of the markets joint venture arrangement effective from 1st April. A review of the order-book is being undertaken.

7. Highways and Street Lighting – the forecast favourable variance is primarily a result of employee issues. Considerable efforts are underway to ensure that these issues are resolved, and as a result there has been minimal impact on service delivery.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Regneneration Financial Review 3rd QuarterReport 5 pages DownloadRead as text

At this meeting

Whole meeting

More from Liverpool Regeneration & Environment Select Cttee 2005/2006

All decisions
MeetingDecisionOutcome
30 Mar 2006 Neighbourhood Management Boundary Review - PresentationAgreed that – (a) the report and the views expressed by Members be noted and taken into consideration in the preparat... Agreed Open
30 Mar 2006 Liverpool Plus - Strategic Investment FundAgreed that (a) the report be noted; and (b) a further report be submitted to the Committee in due course Agreed Open
30 Mar 2006 Annual ReportAgreed that the annual report of the Select Committee for 2005/06 be noted. Agreed Open
30 Mar 2006 Carbon Dioxide EmissionsAgreed that (a) the report be noted; and (b) a further report be submitted in 6 months time to include - · the progre... Agreed Open
30 Mar 2006 Response to Council Motion - Pedistrian Crossing Muirhead AvenueAgreed that a report on the results of the traffic survey be submitted to the appropriate Neighbourhood Committee as ... Agreed Open