Resources Select Committee 2005/2006, Tuesday 27 January 2004

Replacement of Human Resource Payroll System

Agreed Committee 2 papers

Resources Select Committee 2005/2006 agreed this item on Tuesday 27 January 2004. Below is the council's own wording, with the papers it was decided on.

Item77

Resolved

Agreed that the contents of the report be noted.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Resources Select Committee 2005/2006, 4 pages

Purpose of report

1. To report upon the progress in establishing the control arrangements in respect of the replacement HR & Payroll System, RECOMMENDATION:

2. That the actions being taken to improve the HR & Payroll System control environment be noted.

INFORMATION:

3. The Committee will recall, at its meeting on the 10th December 2003 it considered a report (FMS/60/03) identifying the actions being taken to improve the HR & Payroll System internal control environment. The following are the key Service Improvement Objectives and associated target dates.

Service Improvement Objective Target Date

Development and availability of revised payroll January accounting information for Service managers and Head 2004 Teachers. (#)

Completion of Service establishment structures onto March Oracle HR & Payroll database. (*) 2004

Full reconciliation of payroll accounting information to March the General Ledger for 2003/04. (#) 2004

Completion of establishment of key control environment March for HR & Payroll systems. (*) (#) 2004

Verification of personal details by employees. June 2004

Completed roll out of self service HR system for June 2004 managers.

Recovery of overpaid employees pay relating to June 2004 2003/04 or prior. (#) 4. Those key improvement objectives marked (*) are to be the subject of further reviews by Internal Audit over the period January to March 2004.

5. Those key improvement objectives marked (#) will be subject to review by the Council’s External Auditors as part of their Audit of the Council’s Accounts and supporting systems and internal control.

PROGRESS REPORT

6. In respect of those objectives with a target date of on or before March 2004, the current position is as follows:

Development and availability of revised payroll accounting information for Service managers and Head Teachers

7. Service managers and Head Teachers have now received financial information relating to payroll data for all months up to and including the end of December 2003.

8. In addition, the additional information that schools have requested relating to the provision of a pay code analysis has also been provided for the month of December 2003 and will be regularly provided from now on.

9. Further financial information for schools relating to journalised adjustments carried out during this financial year to the end of December 2003, will be provided to schools by the end of January 2004 – and on a monthly and regularly basis thereon.

Completion of Service establishment structures onto Oracle HR & Payroll database

10. Attached is Annexe A to this report, which is an outline of the timetable being worked to, to ensure that the Service establishment structures of Portfolios are correctly recorded on the Oracle HR & Payroll database.

11. There are currently no significant variations in this programme and LDL are confident that with the continued co-operation of officers of the City Council that the exercise will be completed within the target time. Full reconciliation of payroll accounting information to the General Ledger for 2003/04

12. The payroll accounting information for the months of July to November 2003 have now been fully reconciled. At this time it is still considered that the full reconciliation between the Oracle HR & Payroll database and the City Council’s General Ledger accounting system will be completed by the 31st March 2004.

Completion of establishment of key control environment for HR & Payroll systems

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
FMS1904: Development of HR Payroll System: Annexe AAppendix 2 pages Download
PDF
Replacement of Human Resource Payroll SystemReport 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Replacement of Human Resource Payroll SystemThis decision
  2. Replacement of Human Resources Payroll ServicesAgreed

More from Liverpool Resources Select Committee 2005/2006

All decisions
MeetingDecisionOutcome
5 Apr 2006 Minutes of the Last MeetingsAgreed that the minutes be approved. Agreed Open
5 Apr 2006 Called In Item - Percy Street/Upper Parliament Street/Parliament StreetAgreed that in view of the concerns expressed by members, consideration of this proposal be deferred pending the subm... Agreed Open
5 Apr 2006 Response to Motion - Properties in Newsham ParkAgreed that the Executive Member for Resources be requested to ensure that all long term vacant Council properties in... Agreed Open
5 Apr 2006 Revenues and Benefits Service PerformanceAgreed that the content of the report be noted. Agreed Open
5 Apr 2006 Green Paper - A New Deal For Welfare Empowering People to WorkAgreed that – a) The contents of the report be noted; b) The views of the Committee, particularly in relation to the ... Agreed Open