Resolved that Application No. 03PT/3996 for prior approval to erect telecommunications equipment on land at Kirkdale Road/Smith Street , Liverpool 5, comprising a 15m high column mast and antenna together with associated equipment cabin, be granted subject to the conditions proposed by the Planning Manager.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Ward: Melrose Site: Site at Kirkdale Road/Smith Street, Liverpool, L5
Proposal: To erect telecommunications equipment (15m high column mast and antenna, together with associated equipment cabin)
Applicant: O2 (UK) Ltd
Application No: 03PT/3996 Case File: n/a
D. C. Team: City North
Recommendation Prior Approval Given _______________________________________________________________
Case Officer Report
Site Description
The site forms the back edge of the pavement along Kirkdale Road, approximately 50 metres north-east of the junction of Kirkdale Road with Smith Street. The land immediately behind the site is grassed over and landscaped, with a small number of semi-mature trees further along Kirkdale Road. The site is relatively open in character, but this stretch of Kirkdale Road is a key route into the City Centre and around a dozen 12.5m high lampposts are located around the junction. There do not appear to be any other existing telecommunications installations in the immediate locality. The site is near to a number of tower blocks, which appear to house a significant amount of equipment on their roofs. The nearest residential properties are approximately 50m away, on the other side of the junction on Smith Street.
The Proposal
The proposal is to erect a 15m high ‘Slimline’ monopole-type telecommunications mast, with a small standard equipment cabin located by its side. The equipment would be located towards the rear of the pavement.
The mast would be located approximately 20m away from the nearest lamppost, designed as such to be similar in height and width to a standard lamppost. The applicants have confirmed that there are no other suitable sites available for the proposed equipment.
Planning Committee 10 February 2004 B3 Cont
Relevant Site History
None relevant to this current proposal,
Response to Consultations
No responses have been received as a result of consultation.
Planning Policy
• UDP Policies The key policy in this proposal is HD27 (Telecommunications Code System Operators)
Issues
The issues in this case relate to the siting and design of the proposed equipment and to health and safety matters.
Officer Assessment
Policy HD27 of the UDP states that permission will be granted for telecommunications equipment, providing that there is no suitable alternative site, no reasonable possibility of mast sharing and that there is no adverse impact on the visual amenity or character of the area. In this case, the applicants have satisfactorily demonstrated that there is no more suitable site available nearby that would give the necessary coverage and that mast sharing in this area is not possible, due to technical reasons. It is considered that the siting and design of the mast will blend well with the exiting lampposts that proliferate around the junction area and thus the equipment will not appear as over-dominant or incongruous. As such, the Planning Manager does not consider that the equipment will have an adverse impact on the visual amenity or character of the area.
In relation to health and safety matters the applicants have provided a statement confirming that the proposal meets the relevant ICNIRP guidelines in accordance with Government Guidance (PPG8) on health and safety. Although the Courts have held that alleged or perceived health considerations can be a material consideration the Planning Manager is of the opinion that in this particular case there are no specific circumstances that make health concerns a significant consideration in determining this application.
Planning Committee 10 February 2004 B3 Cont Summary
The Planning Manager is satisfied that the proposal fully conforms to Policy HD27 of the UDP and recommends that prior approval be given, subject to the stated conditions.
Conditions 1 - The development hereby permitted shall be commenced before the expiration of 5 years from the date of this permission.
REASON: As provided for by Section 91 of the Town and Country Planning Act 1990.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.