Resolved
Agreed that: - 1) the report be noted; and 2) a report on the security issues be submitted to the next meeting.
Culture and Tourism Select Committee 2005/2006 agreed this item on Thursday 19 February 2004. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that: - 1) the report be noted; and 2) a report on the security issues be submitted to the next meeting.
Leisure Services Capital Budget 2003/04
3rd Quarter Forecast (April 03 to December 03)
Third Quarter - April Description to December 2003 Budget Forecast Variance Comments £'000 £'000 £'000
BLXMD27 Croxteth Hall Imp.& Enhanc. 24.0 24.0 0.0 BLXMH92 Crox Hall/Park Imps Ph2 4.0 4.0 0.0 BLXMN61 Croxteth Hall I.T. Feas. 1.0 0.0 (1.0) BLXNA46 Fire Reinst.Work Crox Hall 6.0 6.0 0.0 BLXNN93 Croxteth Hall & Park Info.Tech 1.0 0.0 (1.0) BLXPB42 Adventure Play-Crox Hall 3.0 3.0 0.0 BLXPG11 Croxteth C.P. 29.0 29.0 0.0 BLXPK89 Croxteth Park Imps Phase 3 382.0 382.0 0.0
Sub Total Croxteth Hall & Park 450.0 448.0 (2.0)
BLXMC35 Breck Rd.Library 10.0 0.0 (10.0) Cost Saving BLXMG12 Allotment Improvements 62.0 40.0 (22.0) Slippage BLXML68 St.Georges Hall 10,799.0 10,799.0 0.0 BLXMN38 Picton Pool Feasability 7.0 0.0 (7.0) Cost Saving BLXPK75 Beaufort High School 529.0 200.0 (329.0) Slippage BLXML17 Central Library 8.0 8.0 0.0 BLXNB38 Belle Vale Library 0.0 0.0 0.0 BLXLX18 Norris Green Leisure Centre 40.0 0.0 (40.0) Slippage BLXMA79 Walton Hall F'Ball/Sc.Q.Dr 11.0 11.0 0.0 BLXML54 Odoor Rms Rec Flds Club 1,376.0 1,376.0 0.0 BLXMN24 Picton Synth Pitch 3.0 1.0 (2.0) Cost Saving BLXNB89 Picton S.C.50 Metre Pool 4,365.0 500.0 (3,865.0) Slippage BLXNL49 Synthetic Pitch Ev.Pk,Pict,Tox 137.0 190.2 53.2 Funded by cost savings on other schemes & revenue BLXNT47 Picton Pitch Replace (Other) 0.0 0.7 0.7 BLXPM82 Millennium L'styles Gym Bldg 38.0 38.2 0.2 BRXLK81 L'Pool Tennis Centre 35.0 5.0 (30.0) Slippage BLKAB91 Garston Pool 30.0 30.0 0.0
Sub Total Other 17,450.0 13,199.1 (4,250.9)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Leisure Review Qtr 3- capitalReport | 1 pages | DownloadRead as text |
PDF |
Leisure Review Qtr 3- revenueReport | 1 pages | Download |
PDF |
Leisure Services Financial Monitoring Report: Third Quarter 2003/04Report | 4 pages | Download |
Follow Culture and Tourism Select Committee 2005/2006 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Mar 2006 | Called in item - picton 50m swimming pool - revenue and capital (l23)Agreed that the recommendation of the Executive Board be approved. | Agreed | Open |
| 27 Mar 2006 | Minutes of the last meetingAgreed that the minutes of the last meeting of the Select Committee held on 13 February 2006 be approved and accepted... | Agreed | Open |
| 27 Mar 2006 | Culture inspectionAgreed that the Committee noted the Cultural Services – Self Assessment report and any additional information, commen... | Agreed | Open |
| 27 Mar 2006 | Executive member/director question timeAgreed that a report be submitted to the Committee in relation to the pilot project as soon as details were received.... | Agreed | Open |
| 27 Mar 2006 | Annual report 2005/06Agreed that the Committee noted the draft annual report and that any further comments or amendments be forwarded to t... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.