Resolved that – (i) Norris Village Phase 2 and Phase 3 be included in the City-wide Decanting Programme, adding them onto the City-wide order of priorities; (ii) Officers commence discussions with tenants and owner occupiers about their rehousing requirements; (iii) Land and Development Services commence negotiations to acquire owner occupied properties; and (iv) the properties be included in the Councils Demolition Programme of the Housing Capital Programme.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Portfolio: Regeneration Executive Member/Director: Councillor Flo Clucas / Charlie Parker
Date of submission: Monday, Subject: Phase Two and Phase February 9, 2004 Three Decanting from Norris Green Redevelopment Area (Boot Estate)
Report No. EDR/27/04 Background Contact officer: Angela Forshaw papers : Neighbourhood Manager Alt Valley Alt Valley Neighbourhood Service
Executive summary The principle of developing a Master Plan for the Boot Estate was originally approved in June 1999 and initiated a major consultation exercise in the area. A number of decisions regarding development proposals have since been taken, including decisions about the order of priority for rehousing.
Rehousing residents from the first Decant area began in October 2000 and subsequently overriding priority status was granted to people in a small part of that area in June 2001. In June 2003 the Decant area was widened to include some properties in the Broad Lane area and partially around Ellergreen Leisure centre. The scale of the rehousing commitment from this area has been significant but a great deal of progress has now been made, both in terms of rehousing and demolition.
The Developers, Bishop Loch, now have planning approval to build show houses in the Lewisham Road / Utting Avenue area and a further separate approval to build the first phase, immediately adjacent to the show houses. It is anticipated work will start on site in February 2004. The timing of the next phase to be developed will very much depend on demand for the first.
Within the Norris Village Action Plan it was stated the next area to be Decanted would be agreed in Summer 2003. Given the need to negotiate with Bishop Loch, Cobalt Housing Association and Highways and Planning, this process was delayed and residents and elected members were advised the next Decant area would be declared early in 2004.
The proposal now is to include an area that stretches across the estate from Monksdown School to Ellergreen Leisure Centre in the Decanting programme. This is a large tract of land however many properties are already void; some blocks have already been demolished; and, only 177 families remain including seven who are owner-occupiers.
It is recommended that families living around Monksdown School be given priority for rehousing as part of Norris Village Phase 2 and those towards Ellergreen, as part of Norris Village Phase three. This will enable the area around the school to be cleared quickly and an enhanced site treatment programme to deal with the blight that has contributed to incidents of anti- social behaviour.
Declaring the two areas simultaneously, helps those families that are now living in isolated conditions, or are the only residents on a block. Some would be happy to accept permanent rehousing to relets within the wider Cobalt or Council stock areas. These families may be assisted comparatively quickly. For those who wish to wait for new build in future development areas, the possibility of temporary rehousing to lesser demand relets or to temporary accommodation elsewhere on the Boot estate has already been established.
The profiles of the proposed phases are as follows:
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.