Called In Item Project Jenifer

Agreed Committee 1 paper

Regeneration & Environment Select Cttee 2005/2006 agreed this item on Thursday 4 March 2004. Below is the council's own wording, with the papers it was decided on.

Item75

Resolved

Resolved that – ( i ) the recommendation of the Project Jennifer Evaluation Panel to select St. Modwen Developments Ltd. as their preferred developer partner to deliver a new district centre at Scotland Road/Great Homer Street, be endorsed; (ii) Officers be authorised to negotiate detailed terms with St. Modwen Developments Ltd. for a development agreement in respect of this proposal; (iii) St. Modwen Developments Ltd. be invited to prepare a detailed Masterplan for the creation of a new district centre at Scotland Road/Great Homer Street in consultation with Council members, Officers, other public agencies, the local community and businesses that will be affected by the proposals; and (iv) the completed Masterplan and a summary of the negotiated detailed terms be reported back to the Executive Board for approval in due course. ____ Councillor Jane Corbett explained that the item had been called in because of concerns about the loss of a library for the community around Great Homer Street and that if the only remaining library provision is on Vauxhall Road this would bedifficult for people living around Great Homer Street to access . John Kelly updated the meeting on the present proposal and the finance available to build a new library on Vauxhall Road, together with the revenue implications of providing a library in the new district centre. He said that the bid had been submitted, but no final decision had yet been taken by the City Council, and it couldstill be possible to have library provision in the district Centre if there was a demand for it. Agreed that – (i) the recommendation of Executive Board approved; and (ii) in order to discuss the library provision in the area the Executive Member for Regeneration, the Chairman of this Committee and Councillors Jane Corbett and Ann Hines together with appropriate officers undertake a site visit to the area as soon as possible.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Regeneration & Environment Select Cttee 2005/2006, 15 pages

Executive summary

1. Pre-qualification

1.1The Executive Board of 25th April 2003 authorised officers to market the opportunity to develop a new district centre at Scotland Road/Great Homer Street on the site of the Taylor Street Industrial Estate.

1.2Interested parties were invited to complete a pre-qualification questionnaire (PQQ) and return it by 11th June 2003.

1.3The PQQs received by the closing date were evaluated and scored by a multi-disciplinary team of Officers. Having considered the scores which resulted the Executive Board of 19th September 2003 approved the short-listing of the following companies:

David McLean Developments Ltd. Maro Developments Ltd. Neptune Developments Ltd. St. Modwen Developments Ltd. Tesco Stores Ltd.

1.4Tender documents were sent to the five short-listed bidders with a closing date for the return of bids of 12th November 2003. 2. Technical Evaluation Process

2.1Bids were received from all five short-listed bidders.

2.2They were evaluated by a multi-disciplinary team of officers. The marks in respect of some areas of the technical evaluation were weighted as being more important than others.

2.3The result of this exercise was that the bidder with the highest score was St. Modwen Developments Ltd.

3. Community Forum

3.1An exhibition of the five proposals was held for the Community Forum in the new visitor centre at the rear of St. Anthony’s Church, Scotland Road on 28th November.

3.2The overall outcome was that St. Modwen emerged as the most popular scheme.

4. Evaluation Panel

4.1The Panel met on 10th December 2003 and received presentations from each of the five short-listed bidders.

4.2Following each presentation the Panel members asked the bidders probing questions on their proposals and their ability to deliver them.

4.3Having considered the presentations, the answers to the questions, the technical appraisal, and the outcome of the Community Forum meeting, the Panel decided to select St. Modwen Developments Ltd. as their preferred developer partner.

5. Next Steps

5.1If the nomination of St. Modwen Developments Ltd. is endorsed by the Executive Board they will be required to prepare a master-plan for the development of the site and to negotiate with the City Council terms for the development agreement which will control its delivery.

5.2The master-plan and the detailed heads of terms for the development agreement will be reported back to the Executive Board for approval.

Executive Member/Director recommendation Councillors Peter Millea and Chris Curry/Charlie Parker.

That:

(i) the recommendation of the Project Jennifer Evaluation Panel to select St. Modwen Developments Ltd. as their preferred developer partner to deliver a new district centre at Scotland Road/Great Homer Street be endorsed;

(ii) Officers be authorised to negotiate detailed terms with St. Modwen Developments Ltd. for a development agreement in respect of this proposal;

(iii) St. Modwen Developments Ltd. be invited to prepare a detailed Masterplan for the creation of a new district centre at Scotland Road/Great Homer Street in consultation with Council members, Officers, other public agencies, the local community and businesses that will be affected by the proposals; and

(iv) the completed Masterplan and a summary of the negotiated detailed terms be reported back to the Executive Board for approval in due course

Key Decision

Yes

Forward Plan

Yes

Implementation effective from

13 February 2004

Timescale for action

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Called In Item Project JeniferReport 15 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Called In Item Project JeniferThis decision
  2. Called in Item - Hall Lane Strategic Gateway Project and RLUH Redevelopment (A&D/24)Approved
  3. Called in Item: Deprived Area Fund and Working Neighbourhoods Fund Projects 2008-9 (EDE/19)Approved

More from Liverpool Regeneration & Environment Select Cttee 2005/2006

All decisions
MeetingDecisionOutcome
30 Mar 2006 Neighbourhood Management Boundary Review - PresentationAgreed that – (a) the report and the views expressed by Members be noted and taken into consideration in the preparat... Agreed Open
30 Mar 2006 Liverpool Plus - Strategic Investment FundAgreed that (a) the report be noted; and (b) a further report be submitted to the Committee in due course Agreed Open
30 Mar 2006 Annual ReportAgreed that the annual report of the Select Committee for 2005/06 be noted. Agreed Open
30 Mar 2006 Carbon Dioxide EmissionsAgreed that (a) the report be noted; and (b) a further report be submitted in 6 months time to include - · the progre... Agreed Open
30 Mar 2006 Response to Council Motion - Pedistrian Crossing Muirhead AvenueAgreed that a report on the results of the traffic survey be submitted to the appropriate Neighbourhood Committee as ... Agreed Open