Resolved
It was agreed that the report inform members on the proposed upgrades of existing bus stop infrastructure within the North and Central area of Liverpool City Centre be noted.
North & Central Area Committee agreed this item on Wednesday 24 March 2004. Below is the council's own wording, with the papers it was decided on.
Resolved
It was agreed that the report inform members on the proposed upgrades of existing bus stop infrastructure within the North and Central area of Liverpool City Centre be noted.
2.1The City Centre Movement Strategy (CCMS) being developed by Liverpool City Council and its partners Merseytravel and Liverpool Vision includes a £73 million package of works. These works are aimed at improving the highway network and the public realm to aid regeneration and to support the Merseytram project. The first 2 phases of this programme are due for completion in 2007 in time for Liverpool becoming the Capital of Culture in 2008.
2.2Merseytravel’s contribution to the Strategy includes improvements to all modes of public transport:
Mersey Ferries – extensive refurbishment of both Seacombe and Pier Head terminals Rail – refurbishment of city’s underground stations Bus – see 2.3 below Merseytram – Line 1 to Kirkby plus a city centre loop
These improvements dovetail with the over-arching Strategy and will complement and support the highway improvements proposed under the CCMS.
2.3A summary of the bus improvements includes: Bus stop infrastructure improvements Interchange schemes Bus priority schemes Layover Marketing/publicity
3. Proposals
3.1There are currently 199 bus stops within the agreed city centre boundaries for CCMS. Current CCMS proposals and other developments
Area Committee 24 March 2004 will result in the creation of 24 new stop locations and the loss of 23 bus stops leaving 200 bus stops from 2008.
3.2The programme for LTP Centre 1 seeks to upgrade all or the majority of bus stops within the defined area to LTP SMART standard.
3.4The proposed works are split into 2 areas:
(a) Civil Works
(i) At all bus stops, it is proposed to introduce access kerbs, appropriate to the streetscape to provide near level boarding and alighting. (ii) Enhanced bus stop markings will be introduced at bus stops, to give the bus a higher profile in conjunction with a 24 bus stop clearway order to deter vehicles from parking within the designated area. (iii) To further enhance the bus stops accessibility, tactile dropped crossings and other footway improvements will be introduced.
(b) Infrastructure
(i) It is proposed that where possible, infrastructure is upgraded to the latest SMART standard (shelters and CD’s). (ii) RTPI passenger information points will be provided but initially only at those bus stops served by the SMART 1 and SMART 4 services. (iii) Information will be provided at all stops within an integrated information display, which is part of the shelter. This will help to reduce street cluster.
3.5On streets within the core area of the city centre it is proposed that bus stop design and implementation will be lead by Liverpool City Council as part of the CCMS highway works. However on streets outside the core area where less works are proposed under the CCMS programme the work to design and implement bus stop works will be lead by Merseytravel.
3.6The first package of these works is attached as appendix 1 and lists 20 bus stops chiefly in the area on the southeast periphery of the city centre. 4 of the 20 stops are on Princes Dock and these are enclosed for information only as they are on a private road.
3.7The works will mirror similar works carried out on the LTP Bus Corridors in recent years e.g. Childwall Valley Road and Wavertree Road last year.
3.8Some of the bus stops are located within designated conservation areas. Merseytravel are aware of this issue and are sensitive to the use of certain materials/colours.
3.9Merseytravel have recently appointed consultants Hyder Consulting to carry out the design and supervision of these works and it is envisaged, subject to all the necessary approvals being granted that these works will be implemented in May/June 2004. 4. Summary
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix 2Appendix 2 | 1 pages | Download |
PDF |
Appendix 3Appendix 3 | 1 pages | Download |
PDF |
Bus stop infrastructure: City Centre movement strategyReport | 3 pages | DownloadRead as text |
PDF |
Merseytravel Package One revision 1Report | 1 pages | Download |
Follow North & Central Area Committee at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Mar 2004 | Public Question TimeAgreed a report be produced concerning consultation on the ring road proposals in the area b) I. Janet Kent, Hope Pla... | Agreed | Open |
| 24 Mar 2004 | Marybone Road closures - Notice of Motion Councillors George Knibb and Pauline ConnollyIt was agreed to request the Executive Member for Regeneration to stop forthwith the recent proposals for road closur... | Agreed | Open |
| 24 Mar 2004 | Atlantic Point and City Centre Anti Social behaviour from students Notice of motion from Councillors George Knibb and Pauline ConnollyIt was agreed that a request be made to the City Centre Manager to report on what proposals are in place to combat th... | Agreed | Open |
| 24 Mar 2004 | Block of flats Lace Street. Notice of motion from Councillors George Knibb and Pauline ConnollyIt was agreed to request the City Centre Planning Officer to respond to complaints that residents are unable to watch... | Agreed | Open |
| 24 Mar 2004 | St Josephs Youth Centre Notice of motion from Councillors George Knibb and Pauline ConnollyIt was agreed to call upon the Executive Board to instruct officers to undertake an assessment of the special circums... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.