Resolved
It was agreed that the proposal be supported.
Fairfield and Stoneycroft Area Committee agreed this item on Monday 29 March 2004. Below is the council's own wording, with the papers it was decided on.
Resolved
It was agreed that the proposal be supported.
The intention of this report is to inform the Area Committee of the need for, and seek support for, upgrading of the 5 existing road closures to a more robust layout, in the roads listed above.
INFORMATION
Over a number of years Liverpool City Council has received numerous complaints from local residents regarding the abuse of the existing road closures within the area between Queens Drive West Derby / Derby Lane and Green Lane.
The existing closures are subject to a high level of abuse from motorists, who drive through the closures as a means of accessing and egressing the adjoining roads. This creates a hazard for both pedestrians and other road users who are not expecting vehicles to be traversing the closures in such a manner.
The existing closures with a low kerb face, whilst maintaining access for emergency vehicles, enables other motorists to drive through with relative ease.
The roads that the existing closures were located on were, and indeed still are, important routes for the fire brigade. This means that access for fire engines must be maintained and any changes to these closures must be in-keeping with this.
Proposals
In order to resolve the situation it has been determined that the closures should be upgraded to the type used within both Sandstone and Derwent Road in the area. This ‘upgraded closure’ type has proved successful in reducing the levels of abuse by motorists.
The new layout will continue to maintain access for fire service vehicles, as, to mount the closure a significant amount of ground clearance is required. Vehicles without such clearance run a significant risk of vehicular damage should they attempt to traverse the closure.
It is also proposed to introduce a gap for cyclists within the closure arrangement, and an exemption be included within the Traffic Regulation Order (TRO) so that pedal cyclists will be able, both easily and legally, to negotiate the closures. At present there is no cycle gap within the closure as well as there being no exemption for cyclists within the TRO.
The views of Ward Members, emergency services and residents in the affected area have been obtained. To date no objections have been received from Ward Members or the emergency services.
Of approximately 1200 questionnaires sent out to residents, around 40% were completed and returned to the City Council. From the returned questionnaires, 393 households (81%) were in favour of upgrading the closure whereas 80 households (17%) would prefer the closures removed entirely. Approximately 2% preferred neither option or for the City Council to leave the closures as they are.
In addition to the above, statutory consultations will be carried out as part of the Order making process.
Information held on files within the Traffic Management section has been used in the preparation of this report.
Officer Contact: Jamie Povall Tel. No. 225 3677 Highways Management Client Officer: David Boyer Tel. No. 225 3677 Service Manager – Highways Management ANNEX
Schedule
(i) No person shall cause or permit any vehicle, other than a pedal cycle or an emergency service vehicle, to proceed in the roads or lengths of roads specified in Column One of this Order to the extent specified in Column Two of the said Order.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
TRAFFIC REGULATION ORDER: MOSCOW DRIVE AND SURROUNDING ROADSReport | 5 pages | DownloadRead as text |
Follow Fairfield and Stoneycroft Area Committee at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Mar 2004 | Public question timeIt was agreed that the Conservation Officer be requested to inspect the Park gates with the Tuebrook and Kensington W... | Agreed | Open |
| 29 Mar 2004 | Planning applicationsObjection on the following grounds – (a) the proposed telecommunications equipment damages the rhythm and style of th... | Decided | Open |
| 29 Mar 2004 | Advisory members' issuesIt was agreed that Keith Pickup be requested to submit a full report to this Area Committee on all the above issues. | Agreed | Open |
| 29 Mar 2004 | Minutes of the last meeting/action updateIt was agreed to note a report on telecommunications equipment and specifically, evidence of mast sharing by operator... | Agreed | Open |
| 29 Mar 2004 | St. sebastians primary school, liverpool 7 - traffic calming and 20 mph speed restriction (tro - tm2445)It was agreed that the proposal be supported. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.