Toxteth & Edge Hill Area Committee, Wednesday 14 April 2004

Seymour Street - Copperas Hill Corridor

Agreed Committee 2 papers

Toxteth & Edge Hill Area Committee agreed this item on Wednesday 14 April 2004. Below is the council's own wording, with the papers it was decided on.

Item84

Resolved

Agreed that a briefing note in relation to the forthcoming City Centre Movement Strategy project, the Seymour Street – Copperas Hill Corridor, be noted.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Toxteth & Edge Hill Area Committee, 3 pages

Purpose of report

To inform the Area Committee of the forthcoming City Centre Movement Strategy project, the Seymour Street - Copperas Hill Corridor.

City Centre Movement Strategy

The City Centre Movement Strategy is an integral part of the Local Transport Plan for 2002/2008. It is a comprehensive series of streetworks in the city centre that will see vast improvements to pedestrian movement and safety, traffic flow and public transport.

The objectives of the strategy are to support create a more balanced approach to movement in the city centre, to support key development in the city centre and to improve the quality of the city centre environment for residents, businesses, investors and visitors.

Extensive consultation was carried out regarding the City Centre Movement Strategy in November 2003 through letters/leaflets, media coverage and road shows around the city centre.

Seymour Street – Copperas Hill Corridor

The Seymour Street – Copperas Hill Corridor is part of the overall movement strategy. The principle objective of the scheme is to reduce traffic flow along Lime Street by encouraging two-way traffic movement along Copperas Hill and Seymour Street. This will create a more pedestrian friendly environment around Lime Street Station and St George’s Hall and, will independently facilitate Merseytram Line 1 along Lime Street.

The proposed remodelling of the highway around St Vincent Street and Seymour Street will create a simplified junction at London Road that will enable development on the site of the former Swan public house and allow improved junction capacity for Merseytram Line 1.

The Proposals

The proposals include:

ƒ Creation of two-way traffic along the full length of Copperas Hill.

ƒ Removal of the gyratory system around Seymour Street and St Vincent Way to simply the junction at London Road.

ƒ The widening of Seymour Street to allow two-way traffic.

ƒ Closure of St Vincent Way as a highway including landscaping

ƒ The closure of St Vincent Street at its junction with London Road only. Downgrading of St Vincent Street to act as servicing and access street.

ƒ Realignment of upper Lord Nelson Street to run parallel with Lord Nelson Street to re-establish a quality street pattern.

ƒ Reprofiling of the landscaped area opposite Seymour Terrace to accommodate the works with turfing and tree planting to retain the areas amenity value.

Consultation

Leaflets will be posted throughout the project area to all residents, businesses and building owners informing them of the outline proposals seeking their views and comments.

Several meetings are also being arranged to present the proposals to stakeholders in the area.

Further consultation will be carried out in the forthcoming months is relation to any Traffic Regulation Orders required to implement the project.

Funding and Costs

Outline costs are in the region of £2 million and the funding will come from the European Regional Development Fund Objective 1 Programme (Measure 21) and the North West Development Agency who are both supporting the wider City Centre Movement Strategy. Timescales

Consultation is currently being carried out regarding the outline proposals. Following the incorporation of comments and responses to this consultation, detail design will be developed.

On completion of detailed design, traffic modelling will be carried out to validate the design followed by the instigation of revised Traffic Regulation Orders.

It is anticipated that the project will be on site in October/November 2004 for approximately 8 months.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Seymour Street: Copperas Hill CorridorReport 3 pages DownloadRead as text
PDF
Seymour Street MapPlan 1 pages Download

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Seymour Street - Copperas Hill CorridorThis decision
  2. Land at junction Seymour Street, St Vincent Street, Liverpool 3 (Central Ward)Approved
  3. Land at the junction of Seymour Street and St Vincent Street, Liverpool 3 (Central Ward)Approved
  4. Land at the Junction of Seymour Street and Vincent Street, Liverpool 3 (Central Ward)Approved
  5. Land at Junction of Seymour Street and Vincent Street, Liverpool 3 (Central Ward)Deferred
  6. 2/16 Seymour Street (RES/124)Agreed

More from Liverpool Toxteth & Edge Hill Area Committee

All decisions
MeetingDecisionOutcome
14 Apr 2004 Public Question TimeAgreed that this Committee expresses its concern with the issues raised and agrees with the local residents that thei... Agreed Open
14 Apr 2004 Minutes of the Last MeetingAgreed that consultations be held with local Community Organisations and locals residents as to their views on whethe... Agreed Open
14 Apr 2004 Issues from Advisory MembersAgreed that Inspector Gary Hilton be asked to contact the Church to remind them of their responsibilities and to sugg... Agreed Open
14 Apr 2004 Vision for GranbyAgreed that – (i) the best thanks of the Area Committee be extended to Hazel for the presentation; (ii) this Committe... Agreed Open
14 Apr 2004 Planning ApplicationsAgreed that the Planning Committee be asked to take the following views into account when determining the application... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies