Merseytram - Transportand Works Act Order for Line 1 - Progress on Negotiaitons

Agreed Executive 1 paper

Executive Board agreed this item on Friday 23 April 2004. Below is the council's own wording, with the papers it was decided on.

Item172

Resolved

Resolved that this Executive Board notes - (i) the action taken to date following the City Council decision of 26 November, 2003 ; (ii) the completion of the Heads of Terms for the negotiation of an Implementation Agreement between the Council and Merseytravel on 9 March, 2004 . The intention to withdraw objections to the TWA Order for Line 1, on the signing of the Implementation Agreement with Merseytravel . In such circumstances the Council would submit evidence to the current Public Inquiry in support of the application for the Order; (iii) that as previous deadlines set for the signing of the Implementation Agreement have not been met (originally 20 March and then the start of the Public Inquiry which was on 20 April), Merseytravel will be advised that, unless the Implementation Agreement is signed by the 30 April, the Council will submit Proofs of Evidence as an objector to the Order to the Public Inquiry; (iv) the Proofs will outline in full the Council’s concerns over the consideration and granting of a TWA Order in the absence of a legal agreement that protects the interests of Liverpool’s citizens, the City’s urban fabric and ensures mechanisms are in place to deliver this major and significant project at budget cost and on time (particularly given the imperatives arising from the City being European Capital of Culture in 2008), and to address detailed concerns relating to the actual construction and subsequent operation of the tram; and (v) that an update on the position will be given to the Executive Board meeting on 30 April when the Executive Director (Regeneration) will report as to whether he is satisfied that the Council’s objections to the TWA Order can be withdrawn or whether it will be necessary for the Council to appear at the Inquiry as objectors representing the interests of the Council as, inter alia , local highway authority and local planning authority.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 9 pages

Purpose of report

To provide further information to the Executive Board following the lodging of an objection to the Transport and Works Act (TWA) Order for Merseytram Line 1 (pursuant to the decision of the City Council on 26 November, 2003) and to report on the course of action being adopted for completing negotiations on an Implementation Agreement with Merseytravel, and submitting evidence to the Public Inquiry, in furtherance of the Council’s position.

Recommendation

It is recommended that the Executive Board notes:

a) the action taken to date following the City Council decision of 26 November, 2003; b) the completion of the Heads of Terms for the negotiation of an Implementation Agreement between the Council and Merseytravel on 9 March, 2004. The intention to withdraw objections to the TWA Order for Line 1, on the signing of the Implementation Agreement with Merseytravel. In such circumstances the Council would submit evidence to the current Public Inquiry in support of the application for the Order;

c) that, as previous deadlines set for the signing of the Implementation Agreement have not been met (originally 20 March and then the start of the Public Inquiry which was on 20 April), Merseytravel will be advised that, unless the Implementation Agreement is signed by the 30 April, the Council will submit Proofs of Evidence as an objector to the Order to the Public Inquiry;

d) the Proofs will outline in full the Council’s concerns over the consideration and granting of a TWA Order in the absence of a legal agreement that protects the interests of Liverpool’s citizens, the City’s urban fabric and ensures mechanisms are in place to deliver this major and significant project at budget cost and on time (particularly given the imperatives arising from the City being European Capital of Culture in 2008), and to address detailed concerns relating to the actual construction and subsequent operation of the tram; and

e) that an update on the position will be given to the Executive Board meeting on 30 April when the Executive Director for Regeneration will report as to whether he is satisfied that the Council’s objections to the TWA Order can be withdrawn or whether it will be necessary for the Council to appear at the Inquiry as objectors representing the interests of the Council as, inter alia, local highway authority and local planning authority.

INFORMATION:

1. The City Council lodged an objection to the Transport and Works Act Order for Merseytram Line 1 (Liverpool City Centre to Kirkby) pursuant to the decision of the City Council on 26 November 2003.

2. In accordance with resolution (c) of the above City Council meeting City Council officers and their advisors have engaged in intensive negotiations with their counterparts at Merseytravel with the intention of reaching a binding agreement which would protect the City Council’s statutory and other responsibilities in order that the City Council’s objection may be withdrawn.

3. Paragraphs 5.7 – 5.16 of the November report outlined the issues on which assurances were required from Merseytravel. These included transportation, highway, urban design and conservation issues together with programming and delivery issues associated with a stated completion date of September, 2007and that in relation to funding all the required funding is in place and that no unexpected financial burdens are likely to be placed on the City Council.

Heads of Terms

4. The negotiations have to date resulted in a Heads of Terms document which was signed by the Chief Executive of the City Council and the Director General/Chief Executive of Merseytravel on 9 March 2004.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Merseytram: Transportand Works Act Order for Line 1: Progress on NegotiaitonsReport 9 pages DownloadRead as text

At this meeting

Whole meeting
172Merseytram - Transportand Works Act Order for Line 1 - Progress on NegotiaitonsThis decision

Who was there

9 of 10 attended
MS
Councillor Mike Storey CBEChair, present
WB
Councillor Warren BradleyMember, present
JC
Councillor Jeremy ChowingsMember, present
PC
Councillor Paul CleinMember, present
FC
Councillor Flo Clucas OBEMember, present
CC
Councillor Chris CurryMember, present
MF
Councillor Marilyn FieldingMember, present
PM
Councillor Peter MilleaMember, present
CN
Councillor Chris NewbyMember, apologies
RO
Councillor Richard OglethorpeMember, present

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies