Resolved that consideration of this application be deferred to 24 August 2004 to enable the Planning Manager to discuss with the applicants the concerns expressed by the Committee over the scale of the building and close proximity to neighbouring properties at the Cheapside end of the development. _____
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Report to Planning Committee 2010/21 old, 18 pages
Ward: Everton Site: Former Hatton Garden Fire Station site including Gales Building, Hatton Garden, Liverpool, L3
Proposal: To develop site for retail, office and residential purposes, involving a mixture of new build and conversion, including the conversion of the former Fire Station to A1, A2 and/or A3 ground floor uses with residential uses above and new build blocks comprising 3 levels of underderground parking, ground and first floor A1, A2 and/or A3 uses in 2 towers with residential units above (following demolition of existing structures, including Gales Building)
Applicant: Downing Developments
Application No: 04F/1062 Date Valid: 16th March 2004
D. C. Team: City Centre
Recommendation Approve with Conditions _______________________________________________________________
Case Officer Report
This report also relates to the accompanying applications for listed building consent (04L/1059) to refurbish and convert the former Hatton Garden Fire Station and for conservation area consent (04C/1060) to demolish Gales Building.
Site Description
The application site runs between Hatton Garden to the east and Cheapside to the west. The site is flanked to the north by the former Parcelforce building and to the south by the Grade II listed former Hatton Garden Fire Station. The site lies within the Castle Street Conservation Area and within the boundaries of the proposed World Heritage Site; it is currently occupied by Gales Building that is a non listed vacant building fronting Hatton Garden and within the boundaries of the conservation area. The building was formerly used as offices in connection with the fire station.
The Proposal
Planning Committee 8 June 2004 The proposal is to develop the site for retail, office and residential purposes. This involves a mixture of new build and refurbishment, including the conversion of the former Fire Station to commercial and residential uses. The new build element comprises the erection of two blocks to accommodate a mixture of residential and commercial uses with 3 levels of underground parking. The scheme also involves the demolition of Gales Building.
In detail, the components of the development comprise the erection of two buildings which are respectively 10 storeys and 12 storeys in height. The 10 storey building fronts Hatton Garden and has 63 self contained apartments on the upper floors with mixed ground floor and mezzanine commercial activity including A1 and A3 uses. The 12 storey building fronts Cheapside and has a similar combination of commercial ground floor uses with 58 residential apartments on the upper floors. The development also includes the creation of a 3 levels of basement car parking to accommodate 131 vehicles. Access and egress to and from the car park is from Cheapside.
Separate applications for listed building consent (04L/1059) and for conservation area consent (04C/1060) have been submitted as part of this development. Respectively, these are for works associated with the conversion of the former fire station to accommodate commercial units on the ground floor with 22 apartments on the upper floors; and for the demolition of Gales Building which is required in association with the new elements of the scheme.
The development will also result in the creation of a significant amount of new landscaped public open space around the buildings. This will benefit both the occupiers of the development and will improve pedestrian circulation in the area and create a direct pedestrian link between Hatton garden and Cheapside. The present development, in its entirety, has been submitted as an alternative to the previous application (02F/3412) that was refused.
Relevant Site History
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.