Merseyside Strategic Transportation Committee noted this item on Thursday 29 July 2004. Below is the council's own wording, with the papers it was decided on.
Resolved that Members note the following interim recommendations; it being also noted that such proposals are subject to ongoing work by the Merseyside authorities and that a follow-up report will be presented to the Merseyside Strategic Transportation and Planning Committee when further information is available – (i) that one of the Merseyside authorities acts as a lead authority to steer the production of a Merseyside ROWIP; (ii) that the lead authority appoints a Rights of Way Improvement Plan Officer to co-ordinate the production of the ROWIP for Merseyside who could work alongside the existing staff involved in Right of Way work; (iii) that adequate resources are likely to be needed to support the preparation of the ROWIP. A sum of £50,000 from the LTP would start the ROWIP process; and (iv) that aspects of work, which could be contracted out, be identified once the demonstration authorities have reported on their findings and good practice advice can be given to others.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Report to Merseyside Strategic Transportation Committee, 4 pages
Recommendations
Members are requested to note the following interim recommendations. However, should note that they are subject to ongoing work by the Merseyside authorities and that a follow-up report will be presented to MSTPC when further information is available.
(i) That one of the Merseyside authorities acts as a lead authority to steer the production of a Merseyside ROWIP.
(ii) That the lead authority appoints a Rights of Way Improvement Plan Officer to co-ordinate the production of the ROWIP for Merseyside who could work alongside the existing staff involved in Right of Way work.
(iii) That adequate resources are likely to be needed to support the preparation of the ROWIP. A sum of £50,000 from the LTP would start the ROWIP process.
(iv) That aspects of work, which could be contracted out, be identified once the demonstration authorities have reported on their findings and good practice advice can be given to others.
1. BACKGROUND The Countryside and Rights of Way Act 2000 (CROW) requires every highway authority to produce and publish a Rights of Way Improvement Plan for its area by November 2007. Statutory guidance was issued to local highway authorities in England in 2002.
DEFRA has indicated that ROWIP’s will form part of authorities’ Local Transport Plans from 2005. It is envisaged that rights of way improvement planning will be a distinct strand within the new Local Transport Plans and that the revised Guidance on Full Local Transport Plans (planned for 2004) will cover this point.
Whilst it is a statutory duty to publish a ROWIP, there is no requirement to implement the plans. However, there is a high expectation from user groups that that plans will be implemented by highway authorities. The ROWIP is seen as a bidding tool to fund improvements to the Rights of Way network. Funding for the implementation of the ROWIP could come from a variety of sources including the LTP, Heritage Lottery Fund, and grant aid by the Countryside Agency.
The five Merseyside authorities and Halton MBC established a joint Merseyside Local Access Forum (MLAF) in 2001. This partnership builds on the earlier precedent in developing a joint Local Transport Plan and it is anticipated that a similar approach could be adopted for the production of a Merseyside ROWIP.
Local highway authorities are required to involve local access forums before preparing or reviewing their plans. It is anticipated that the LAF will assist the authorities in setting priorities for implementing the plan and commenting on published draft plans.
2. REPORT The Countryside Agency has funded eight exemplar authorities (two authorities from each of the four Countryside Agency regions in England) to produce a “mini” ROWIP over a twelve month period. Each of these authorities has been researching two aspects of the ROWIP process. It is intended that when these authorities report on their findings, best practice will then be disseminated to other authorities via the Countryside Agency. It was originally intended that the exemplar authorities would be in a position to report on their findings by December 2003. However the length of time taken to produce a “mini” ROWIP has been considerably longer.
The outline process of producing a ROWIP based on the statutory guidance can be summarised as follows:
Preparation • Establish organisational links, steering groups, etc (internal / external) • Establish progress-monitoring system • Consider focus of plan and define scope and depth
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Merseyside Strategic Transportation Committee at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.