Resolved
Agreed that – (i) the report be noted, and (ii) the thanks of this Committee be given to John Kilbride and his staff for the progress being made.
Customer and Corporate Services Select Committee 2005/2006 agreed this item on Thursday 23 September 2004. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that – (i) the report be noted, and (ii) the thanks of this Committee be given to John Kilbride and his staff for the progress being made.
On 8 April 2004 the Community Equality and Values Select Committee considered a report which set out an agreed approach towards the implementation of the Disability Discrimination Act. This report provides an update on the present position.
That the exceptional progress towards the implementation of the Disability Discrimination Act within operational premises (managed by the Premises Management Unit) of the City Council is noted.
TEAMS/PMU/FACMAN/REPORTS/2004/DDA REPORT BACKGROUND INFORMATION 1. In April 2004 the Community Equality and Values Select Committee agreed a report which detailed the strategic approach in operational premises towards the implementation of the Disability Discrimination Act.
The following approach was agreed:
Access Audits – to be undertaken in all premises to identify and cost all improvement works required so that the works can be prioritised in accordance with the agreed Access Rating (all priority areas to be completed by March 2004).
Action Planning – establish criteria/timescale to be used to remove the obstacles identified in the access audits – establish key priority areas within the council (all to be agreed by March 2004).
Access Guide – a clear statement that explains current accessibility of the facility and provides information to the general public before they visit a facility, with reference to the Action Planning process (all to be agreed by September 2004).
2. Present Position
2.1Percentage of Access Audits Completed
2.1.1 Central Services • City Centre Administrative Buildings 100% • One Stop Shops 100% • Customer Focus Centres 100%
2.1.2 Education Library and Sports • Libraries 100% • Sports Centres 100% • Education (Non Schools) 100 %
2.1.3 Supported Living • Day Centres 100% • Homes for Older People 100%
2.1.4 Civic Buildings • Town Hall and Croxteth Park 100%
Access Audit at St George’s Hall will not be carried out until refurbishments works are complete.
Teams/PMU/FACMAN/Reports/2004/Committee Report DDA 3 Action Planning
3.1The Access Audit identifies improvement work required and the works are then prioritised to enable an action plan to be developed that addresses the main obstacles first.
Percentage of Action Plans Completed
3.1.1 Central Services • City Centre Administrative Buildings 100% • One Stop Shops 100% • Customer Focus Centre 100%
3.1.2 Education Library and Sports • Libraries 100% • Sports Centres 100% • Education (non schools) 100%
3.1.3 Supported Living - Day Centres 100% - Homes for Older People 100%
3.1.4 Civic Buildings Town Hall and Croxteth Park 100%
Action plan to be completed on St George’s Hall, following refurbishment works.
This report concentrates on Operational Premises managed by PMU and Members may require that separate reports should be presented, by appropriate Executive Director, to cover other key areas eg. parks and car parks.
4 Priority Areas
In April 2004 Members agreed that the main priority areas within operational premises are:
- Buildings with the highest level of Public Access – One Stop Shops, Sports Centre, Libraries, Main City Centre Buildings.
- Specialist Buildings – Day Nurseries, Day Centres, Homes for Older People, Crematoria.
It should be noted that in areas of a building not open to the public the requirement to make reasonable adjustments will only apply when required to meet the specific needs of a member of staff or by October 2006.
Teams/PMU/FACMAN/Reports/2004/Committee Report DDA To assess progress made in the priority areas it was agreed to use an indicator of √, √√ or √√√ based on the key areas of the access audit as a guide.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Disability Discrimination ActReport | 16 pages | DownloadRead as text |
Follow Customer and Corporate Services Select Committee 2005/2006 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Apr 2006 | Minutes of the Last MeetingAgreed that the minutes of the last meeting of this Committee held on 2 March 2006 be approved as a true record. | Agreed | Open |
| 20 Apr 2006 | Customer and Corporate Services Select Committee Annual ReportAgreed that the Committee’s Annual Report for 2005/06 be approved. | Agreed | Open |
| 20 Apr 2006 | Internet/Intranet/Extranet DevelopmentsAgreed that the report be noted. | Agreed | Open |
| 20 Apr 2006 | Learning and Development Service Progress ReportAgreed that the report be noted. | Agreed | Open |
| 20 Apr 2006 | Diversity and Social Inclusion Update for 2005/06Agreed that the report be noted and the recommendations set out in relation to the 2006/07 programmes, be approved. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.