Resolved
Agreed that consideration of this matter be deferred and the Officers be requested to submit a further report to this Committee following a re-assessment of the proposed access point to the footpath.
Liverpool East Area Committee agreed this item on Wednesday 29 September 2004. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed that consideration of this matter be deferred and the Officers be requested to submit a further report to this Committee following a re-assessment of the proposed access point to the footpath.
To seek support and approval for the new pedestrian access footpath across the school field, pedestrian guard rail and associated signage.
INFORMATION
1.1As part of the Merseyside TravelWise initiative, Liverpool City Council have been working closely with a number of schools to develop School Travel Plans with the aim of encouraging more people to walk, cycle and use public transport. School Travel Plans are unique to the specific issues associated with individual school sites, consequently detailed consultation with the school and surrounding residents is essential if effective measures are to be identified.
1.2Generally, to alleviate the current disruption caused as a result of the school ‘drop off’ and ‘pick up’, measures to assist both the school, pupils and local residents are promoted following the investigation of specifically identified problems. The measures proposed as part of this initiative are of a more proactive nature. Since the measures identified are from extensive consultations with the schools concerned and are intended to promote a safer highway environment, especially for school children travelling to and from the schools.
1.3St Paul’s and St Timothy’s Infants School and St Paul’s Junior School are situated in a residential area, enclosed on three sides by residential properties and accessed primarily by a single entrance to both schools on South Parkside Drive and Spring Grove.
1.4Extensive studies and surveys by the school on its pupils identifying where they travel from have been undertaken.
1.5Future developments in the area show that there is a major housing estate, (approx 600 properties) to the northeast which falls within the catchment area of the school.
1.6Potential pupils travelling to the school will use this new access.
1.7The school travel plan developed by the school shows that there is a need for an additional entrance / exit to the school grounds.
1.8The results of the consultation process show however that there is a clear split of opinion to the scheme.
1.9The residents currently experiencing the disruption during the school ‘drop off’ and ‘pick up’ are in favour of the proposals. While the residents located in the vicinity of the proposed access are strongly against it.
1.10Those against the proposals identify it as a transfer of vehicle numbers along Crown Road and the surrounding area, increased parking from parents and noise disruption.
1.11A planning application was submitted to Liverpool City Councils Planning Department, detailing the proposals.
1.12On Tuesday 13 April 2004 at a Planning Committee held in Council Chambers the schools gave a presentation outlining
2 their proposals followed by the local residents who objected to the scheme.
1.13The planning application for the school access and footpath was granted planning permission.
2.0Proposals
2.1It is proposed to construct a new 2.0m wide footpath across the school playing field from Crown Road to the school play ground, (approx 135m long), install a new pedestrian access through the existing fence and install pedestrian guard rail and school keep clear markings in Crown Road across the school access. Drawing Number: 2020/TP/TC0180/01/01.
2.2The proposed pedestrian access will be managed by the site manager for the schools. It will be closed between 1600hrs – 0830hrs.
3.0CONSULTATIONS
3.1Information concerning these proposals has been delivered to those residents directly affected and the views of Ward Members, Emergency Services, cycling organisations and Merseytravel have been sought. As yet no objections have been raised by the formal consultees. If any objections are raised these will be reported on verbally at Committee.
3.2In terms of resident responses, of the 65 letters distributed locally there have been 38 responses, 12 of which support the outlined proposals and 26 against the proposals.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
St. Paul's and St. Timothy's Infants School / St. Paul's Primary School: New Pedestrian Footpath and AccessReport | 4 pages | DownloadRead as text |
Follow Liverpool East Area Committee at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Apr 2005 | Knotty Ash One Stop Shop - Review of HoursAgreed that the report be noted. | Agreed | Open |
| 13 Apr 2005 | Royal Liverpool Children's NHS Trust - Development ProposalsAgreed that with reference to the proposed loss of parkland which is considered wholly unacceptable the Area Committe... | Agreed | Open |
| 13 Apr 2005 | Merseyside Police - Neighbourhood Policing UpdateAgreed that the Committee place on record it appreciation for all the hard work undertaken by Inspector Harris in the... | Agreed | Open |
| 13 Apr 2005 | Eastern Link Neighbourhood Management Services UpdateAgreed that the report be noted. | Agreed | Open |
| 13 Apr 2005 | Pedestrian Safety - East Prescot Road L14Agreed that the Motion be approved and the Executive Member for Regeneration be requested to seek proposals from Offi... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.