Resolved that – (i) Liverpool City Council acts as Accountable Body for Objective One funding in respect of the Bemrose Industrial Estate; (ii) on the receipt of an offer letter from the Government Office North West that - · authority to be granted for the Executive Director (Regeneration) to accept ERDF grant (at 40% of total eligible cost) of up to £2,441,673towards the cost of delivering the scheme; · the Divisional Manager (Regeneration Programmes) be appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises; · the City Council’s capital programme be adjusted to reflect ERDF expenditure on this project of £296,386 during the financial year 2004/05 and £2,145,287 during financial year 2005/06 ; and · the capital expenditure be committed; and (iii) further reports to be submitted to Members as and when appropriate to update on progress.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
1. Liverpool City Council, as a key partner in the regeneration of the City, often has to act as the Accountable Body for Objective One ERDF to allow the funding to be accessed and then used towards the delivery of a number of capital works schemes. The redevelopment of the Bemrose Industrial Estate, a speculative industrial development project to be undertaken at Long Lane/Hanson Road, Aintree Industrial Estate. Plans of the scheme are attached at Appendices 2A, 2B and 2C, is the latest initiative requiring agreement by the City Council to act as Accountable Body.
2. The project will be delivered by Centaur Property Investments Limited, supported by the City Council as Accountable Body for the Objective One grant. The project is included within the approved Approach 580 Strategic Investment Area IDP and Year 4 Delivery Plan as a key site for investment. The Delivery Plan is complementary to the City Council's corporate objectives and those of Liverpool First, the City’s Community Strategy. Liverpool First is committed to create a competitive, sustainable and inclusive City of major international significance.
3. Appendix 1 describes briefly the project, its funding package, timescale for delivery and anticipated outcomes. The project requires a bid for Objective One funding and this report seeks authority from LCC to act as Accountable Body for the Objective One funding, effectively applying for and accepting grant, and then facilitating the processing of Objective One grant claims and the payment of the grant to the private developer involved. There is no requirement to fund this project from LCC budgets but the City Council does need to act as a conduit for the £2,441,673 Objective One grant involved. Executive Member/Director recommendation. Councillors Peter Millea and Keith Turner / Charlie Parker –
That -
(i) Liverpool City Council acts as Accountable Body for Objective One funding in respect of the Bemrose Industrial Estate;
(ii) On the receipt of an offer letter from the Government Office North West that:
(a) Authority to be given to the Executive Director Regeneration to accept ERDF grant (at 40% of total eligible cost) of up to £2,441,673 towards the cost of delivering the scheme;
(b) The Divisional Manager for Regeneration Programmes is appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises;
(c) The City Council’s capital programme be adjusted to reflect ERDF expenditure on this project of £296,386 during the financial year 2004/05 and £2,145,287 during financial year 2005/06;
(d) The capital expenditure is committed.
(iii) Further reports to be submitted to Members as and when appropriate to update on progress.
Key Decision: Yes
Forward Plan: Yes
Implementation effective from: 5 November 2004
Timescale for action:
Project to be delivered between January 2005 and March 2006. Planning consent for the scheme was granted on 18th November 2003. Reason(s) for Recommendation:
To seek formal approval for Liverpool City Council to act as Accountable Body for ERDF grant that will allow the project to proceed.
Alternative Options to be considered:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.